31 Oct 2022declared completionK-RERA registration · read 20 Sep 2026
216registered unitsK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Oct 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

RESIDENTIAL
152

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

2.2registered acres

98.3registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/310/PR/181122/002166

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 October 2022
Land area8,893 sq m (2.2 acres)
Homes registered216
Tower/wing entries1
Unit mix152 × RESIDENTIAL

In context

Density98.3 homes per acre
Density in context79th percentile of 787 Bengaluru South projects (median 77.3)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units216Total inventory registered with K-RERA.
Official carpet area35,586 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Registered land area8,893 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI~4.80Sanctioned floor-area ratio (≈42,680 sqm sanctioned FAR area ÷ 8,893 sqm land) — higher means a denser vertical build.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)346Separate filed counts; these categories may overlap and are not added together.
Open-parking field19Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date01-11-2018

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
RESIDENTIAL152100%35,586 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
PICCASSSO23216346-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 216 official flat/unit rows, matching the 216 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3BHK150120.6-151.2 sqm31.2-39.1 sqm150
4BHK440.0-308.8 sqm64.1-80.0 sqm88
2BHK22102.4 sqm26.5 sqm22

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
PICCASSSO2160.0-308.8 sqm26.5-80.0 sqm260
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
1PICCASSSO04BHK287.5 sqm74.4 sqm2
2PICCASSSO03BHK136.5 sqm35.3 sqm1
3PICCASSSO03BHK151.2 sqm39.1 sqm1
4PICCASSSO03BHK151.2 sqm39.1 sqm1
5PICCASSSO04BHK247.7 sqm64.1 sqm2
6PICCASSSO03BHK125.4 sqm32.4 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

8 of 35 compliance document slots are filed as Not Applicable; the remaining 27 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Oct 2022, extended (Extension) to 30 Jul 2026 — both dates have passed with no OC on file. The extension on file was granted on 27 Jan 2025 (K-RERA extension no. EX/PRM/KA/RERA/1251/310/PR/250127/002166) — it has been used, its deadline has also passed, and no further extension is recorded.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (BESCOM)
Water & sewage (BWSSB/KWSSB)✓ On file (BWSSB)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

1 K-RERA order on this project (PROJECT MODIFICATION) — read the order copies on the K-RERA portal.

K-RERA complaint orders (1 complaint against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
Madhavi Ramam vs RAJARAJESHWARE BUILCON PVT LTDRefund of amount paid with interest.AUTHORITY14/05/2025

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Project team & certifications

RERA filing

K-RERA names 2 project professional/vendor rows across Architect, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectKEMBHAVI ARCHITECTURE FOUNDATION-19724 TH 'T' BLOCK. JAYANAGAR, BANGALORE PINCODE-560041.
Structural engineerRAJESH MANKANI---

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹53.9 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: STATE BANK OF INDIA SSI KumaraPark(08577) (IFSC SBIN0008577, a/c …2006). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~11 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
MG Road / city centre6 km
Bellandur–Marathahalli belt11 km
Electronic City11 km
Outer Ring Road / Manyata14 km
Whitefield IT hub18 km
Kempegowda Int'l Airport34 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Rajarajeshware Buillcon.
1 complaints on the K-RERA register against Rajarajeshware Buillcon in Bangalore.

Other RERA-registered projects in Jayanagar

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Piccassso?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026