Bangalore/Project record

K-RERA · the public record

Queens Gate Block 4

Bengaluru South · Suadela Constructions

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Nov 2021declared completionK-RERA registration · read 20 Sep 2026
432registered unitsK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Nov 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

Retail
1

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

0.6registered acres

697.3registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/310/PR/171016/000971

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion30 November 2021
Land area2,507 sq m (0.6 acres)
Units registered432
Tower/wing entries1
Unit mix1 × Retail

In context

Density697.3 units per acre
Density in context100th percentile of 787 Bengaluru South projects (median 77.3)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units432Total inventory registered with K-RERA.
Official carpet area318 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Registered land area2,507 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI~17.99Sanctioned floor-area ratio (≈45,094 sqm sanctioned FAR area ÷ 2,507 sqm land) — higher means a denser vertical build.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)378Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date21-12-2016

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
Retail1100%318 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Queens Gate Block 428432378-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 432 official flat/unit rows, matching the 432 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2BHK162678.0-848.0 sqft51.6-63.5 sqft162
3BHK1621,038.0-1,169.0 sqft78.0-88.9 sqft162
1BHK108402.0 sqft31.2 sqft0 (108 with 0)

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Queens Gate Block 4432402.0-1,169.0 sqft31.2-88.9 sqft324 (108 with 0)
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
A 101Queens Gate Block 413BHK1,169.0 sqft88.9 sqft1
A 102Queens Gate Block 412BHK848.0 sqft63.5 sqft1
A 103Queens Gate Block 413BHK1,038.0 sqft78.0 sqft1
A 104Queens Gate Block 413BHK1,169.0 sqft88.9 sqft1
B 101Queens Gate Block 411BHK402.0 sqft31.2 sqft0
B 102Queens Gate Block 411BHK402.0 sqft31.2 sqft0

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

6 of 35 compliance document slots are filed as Not Applicable; the remaining 29 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 30 Nov 2021, extended (Covid Extension) to 30 Aug 2022 — both dates have passed with no OC on file.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (All NOCs from Authority)
Water & sewage (BWSSB/KWSSB)✓ On file (All NOCs from Authority)
Fire NOC✓ On file (All NOCs from Authority)
Pollution control (KSPCB)✓ On file (All NOCs from Authority)
Environmental clearance✓ On file (All NOCs from Authority)
Airport Authority height clearance✓ On file (All NOCs from Authority)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Complaints on this project's K-RERA page (1 complaint listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/221007/0010063
07-10-2022
Delay in giving posession of the apartmentEvita (another project by this promoter)DISPOSED AUTHORITY BENCH4

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Project team & certifications

RERA filing

K-RERA names 3 project professional/vendor rows across Architect, Contractor, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectArchitect Hafeez Contractor-1982Sonawall blg, 29 Bank street
ContractorRSP United Infra Constructions Private Limited-2011No 6 MLA Layout, RT Nagar
Structural engineerMahimtura ConsultantsPvt. Ltd---

Builder track record

RERA filing

Suadela Constructions has 2 other K-RERA-registered projects in our records. 2 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a higher delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹48.1 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: ICICI Bank Powai Branch (IFSC ICIC0000020, a/c …3434). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.

Location & Connectivity

The nearest major job hub is ~11 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
MG Road / city centre7 km
Bellandur–Marathahalli belt11 km
Electronic City11 km
Outer Ring Road / Manyata14 km
Whitefield IT hub18 km
Kempegowda Int'l Airport34 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Suadela Constructions.
Suadela Constructions has 3 projects registered in Bangalore.
2 complaints on the K-RERA register against Suadela Constructions in Bangalore.

Other projects by this builder in Bangalore

Other RERA-registered projects in Jayanagar

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.