76%construction reportedQ4 2025 filing
42units not bookedof 59 · Q4 2025 filing
59registered unitsK-RERA registration · read 16 Jul 2026

The record · free to read

Registration read 16 Jul 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q4 2025

declared completion

Not recorded

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 16 Jul 2026

Inventory & scale

What this registration contains.

2BHK+Study, 3BHK, 3BHK+Study
59

Filed categories, unchanged · K-RERA registration · read 16 Jul 2026

The whole registration

0.6registered acres

95.7registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1257/334/PR/091123/006400

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Land area2,496 sq m (0.6 acres)
Homes registered59
Tower/wing entries2
Unit mix59 × 2BHK+Study, 3BHK, 3BHK+Study

In context

Density95.7 homes per acre
Density in context65th percentile of 4882 projects in this register (median 82.1)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units59Total inventory registered with K-RERA.
Official carpet area7,379 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area9,872 sqmUseful scale context when comparing density and project cost.
Registered land area2,496 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI4.34Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries2Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)96Separate filed counts; these categories may overlap and are not added together.
Covered-parking field96Separate filed counts; these categories may overlap and are not added together.
Open-parking field19Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberE4/BE 59/2022-23 (145793)Use this to match the sanctioned drawing set shown by the builder.
Plan approval date02-02-2023
Project start date01-11-2023

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
2BHK+Study, 3BHK, 3BHK+Study59100%7,390 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Block -A12525439.99 m
B474215 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 59 official flat/unit rows, matching the 59 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3 BHK33110.0-128.0 sqm34.0-57.0 sqm33
3.5 BHK25123.0-137.0 sqm36.0-57.0 sqm25
2.5 BHK196.0 sqm29.0 sqm1

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Block -A5296.0-137.0 sqm29.0-57.0 sqm52
B7110.0-112.0 sqm34.0 sqm7
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
A-001Block -A02.5 BHK96.0 sqm29.0 sqm1
A-002Block -A03 BHK115.0 sqm34.0 sqm1
A-003Block -A03.5 BHK123.0 sqm36.0 sqm1
A-004Block -A03 BHK119.0 sqm35.0 sqm1
A-101Block -A13.5 BHK131.0 sqm42.0 sqm1
A-102Block -A13 BHK121.0 sqm41.0 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

All 37 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (Electricity Permission Letter)
Water & sewage (BWSSB/KWSSB)✓ On file (Water Permission Letter)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)Not found in catalog
Environmental clearanceNot found in catalog
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

1 of 3 applicable approvals are on file; still outstanding: Water supply and sewage board and KPTCL- BESCOM. Confirm each has been granted, not merely applied for, before booking.

7 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardTo Be Applied-View NOC
KPTCL- BESCOMTo Be Applied-View NOC
Fire and SafetyApproved19-09-2022R&S Bellevue - Fire & Safety Approval.pdf

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantSHREYANK S SHETTY2533672020Bengaluru Urban, Karnataka - 560003
EngineerMAHESH KUMAR16-50-298/2018-19(DCE)2018Bengaluru Urban, Karnataka - 575002
ArchitectH.A. ANANDA PRAKASHCA/89/125651991Bengaluru Urban, Karnataka - 560055
ContractorR & S Turnkey Contractors Pvt Ltd-2005Bengaluru Urban, Karnataka - 560005

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2025-Q4): ₹4.69 Cr collected from buyers, ₹4.69 Cr withdrawn from the project's escrow account.

Construction progress73% → 76% (+3 pts)
Units sold/booked as registered17/59 (29%)
Buyer collections in available QPRs₹6.76 Cr
Escrow withdrawals in available QPRs₹6.76 Cr (1.00x collections)
  • Construction progress moved from 73% to 76% across the filed QPR window.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹47.7 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: Bank of Baroda Mayo Hall IFSC Code : BARBOVJMAY0 Pin Code : 560001. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~13 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
MG Road / city centre10 km
Electronic City13 km
Bellandur–Marathahalli belt14 km
Outer Ring Road / Manyata17 km
Whitefield IT hub22 km
Kempegowda Int'l Airport36 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Amp; Turnkey.

Other RERA-registered projects in Kumaraswamy Layout

Vaishnavi AT-ONE Krishna Brindavan
Shriram Southern Crest - Phase -2

Major developers building in Kumaraswamy Layout

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.