RELIAABLE DOLLAR COLLONY Phase 2B
Anekal · RD Buildtech and Developers(Kar)
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 20 Sep 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
17 Aug 2020
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
K-RERA registration · read 20 Sep 2026
Inventory & scale
What this registration contains.
Filed categories, unchanged · K-RERA registration · read 20 Sep 2026
The whole registration
9.9registered acres
The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
K-RERA · PRM/KA/RERA/1251/308/PR/171031/001688
This project, on the record
The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.
On the register
Values as crawled from the official K-RERA record; context percentiles name their comparison population.
Official Registry Facts
Official project scale
RERA filingRegistration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.
| Disclosure | Official value | Why it matters |
|---|---|---|
| Registered land area | 40,164 sqm | The land area attached to this K-RERA registration. |
| Open-parking field | 0 | Separate filed counts; these categories may overlap and are not added together. |
| Garage field | 0 | Separate filed counts; these categories may overlap and are not added together. |
| Project start date | 17-08-2017 |
Legal, Approvals & Project Team
Litigation & compliance
RERA filingNo litigation declared on this project's K-RERA filing.
All 15 standard compliance document slots have usable uploaded filings.
No completion certificate (OC) on file yet — project has not been declared complete.
⚠ Registration validity has lapsed: originally due 17 Aug 2020, extended (Covid Extension) to 17 May 2021 — both dates have passed with no OC on file.
Named utility/regulatory approvals
"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.
K-RERA enforcement record (the regulator's own defaulter list & penalty orders)
⚠ Listed on K-RERA's official DEFAULTER list.
K-RERA complaint orders (1 complaint against a project of this name on K-RERA's orders register)
| Parties | Relief sought | Disposal | Order date |
|---|---|---|---|
| JAGADISH REDDY vs RELIAABLE DOLLAR COLLONY PHASE 2B | Don't give RERA Approval | AUTHORITY | 19/08/2020 |
⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.
Complaints on this project's K-RERA page (10 complaints listed against this promoter)
| Complaint | Subject (as filed) | Project | Status |
|---|---|---|---|
| CMP/190518/0003078 18-05-2019 | Reliaable Developers cheated us | RELIAABLE DOLLAR COLLONY Phase 2B | DISPOSED AO |
| CMP/191025/0004564 25-10-2019 | Original Suit Pending (o.s no 477/2016) in anekal Court. Writ Petition (wp 15040/2019) in the High Court | RELIAABLE DOLLAR COLLONY Phase 2B | DISPOSED AUTHORITY |
| CMP/201118/0007087 18-11-2020 | Advance amount not refunded when I went to office behaving rudely and not ready to refund, they are not not at all professional | RELIAABLE DOLLAR COLLONY (another project by this promoter) | DISPOSED AUTHORITY BENCH4 |
| CMP/210308/0007758 08-03-2021 | cancellation of plot and refund | Reliaable Prime City PHASE 1 (another project by this promoter) | DISPOSED AUTHORITY BENCH4 |
| CMP/210415/0007897 15-04-2021 | REFUND OF THE ENTIRE BOOKING AMOUNT | Reliaable Residenza Phase 1 (another project by this promoter) | DISPOSED AUTHORITY BENCH4 |
| CMP/210917/0008345 17-09-2021 | Denied in refunding the booking amount. | Reliaable Prime City Phase 1A (another project by this promoter) | DISPOSED AUTHORITY BENCH5 |
| CMP/211020/0008451 20-10-2021 | Did not receive refund for Reliaable plot 196 cancellation | Reliaable Prime City PHASE 1 (another project by this promoter) | DISPOSED AUTHORITY BENCH5 |
| CMP/220302/0009060 02-03-2022 | Long delay in Refund of plot booking amount | Reliaable Residenza Phase 1 (another project by this promoter) | DISPOSED AUTHORITY BENCH5 |
Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.
Project team & certifications
RERA filingK-RERA names 3 project professional/vendor rows across Architect, Contractor, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.
| Role | Name | Registration / licence | Since | Locality |
|---|---|---|---|---|
| Architect | Ar.Vinayakaram M S | - | 2011 | Museum Road, Bengaluru |
| Contractor | M/s. PUSHPAGIRI INFRASTRUCTURE COMPANY | - | 2008 | Nagarabhavi II Stage, BANGALORE - 560 072. |
| Structural engineer | Mr.Rajesh - RAJESH CONSULTANTS | - | - | - |
Builder track record
RERA filingRd Buildtech has 12 other K-RERA-registered projects in our records. 12 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a higher delayed rate than the K-RERA average across Bengaluru on the same measure.
Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.
Financials & Construction Progress
Financial disclosures
RERA filing⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.
The estimated cost above is the developer's declared construction cost only (K-RERA's own label: "Estimated Cost of Construction as certified by Engineer") — it excludes land cost, so it isn't comparable to the buyer-collection figures below or to a sale price.
RERA 70% project account is on file: Axis Bank Sadashivanagar (IFSC UTIB0001887, a/c …6750). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.
Location & Connectivity
The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.
| Landmark | Straight-line |
|---|---|
| Electronic City | 5 km |
| Bellandur–Marathahalli belt | 8 km |
| Whitefield IT hub | 13 km |
| MG Road / city centre | 16 km |
| Outer Ring Road / Manyata | 21 km |
| Kempegowda Int'l Airport | 37 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.