Bangalore/Project record

K-RERA · the public record

SIDVIN SYMPHONY

Hosakote · AVYANHP SHARAYU

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

100%construction reportedQ4 2025 filing
31 Mar 2026declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q4 2025

declared completion

31 Mar 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

10.69 M X12.19 M
3

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1250/304/PR/270125/007433

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 March 2026
Unit mix3 × 10.69 M X12.19 M

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Approved plan numberHPA/LAO/23/2023-24Use this to match the sanctioned drawing set shown by the builder.
Plan approval date19-11-2024
Project start date19-11-2024

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
10.69 M X12.19 M3100%390 sqm

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

1 of 21 compliance document slots are filed as Not Applicable; the remaining 20 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Mar 2026, extended (an extension) to 30 Aug 2026 — both dates have passed with no OC on file. An extension application filed on 15 Jul 2026 is pending with K-RERA — until it is approved, the registration stands lapsed.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (NOC from ESCOMs)
Water & sewage (BWSSB/KWSSB)✓ On file (NOC for Water)
Fire NOCNot found in catalog
Pollution control (KSPCB)✓ On file (KSPCB (If Applicable))
Environmental clearanceNot found in catalog
Airport Authority height clearanceNot found in catalog

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

Statutory approval status

RERA filing

0 of 5 applicable approvals are on file; still outstanding: Water supply and sewage board, KSPCB- PCB (10 Acres to 125 Acres), Engineering Department (PWD) for completion of development works, KPTCL- BESCOM and Horticulture department. Pollution-control clearance (KSPCB) is among them — a high-importance clearance, so confirm it has been granted (not just applied for) before you book.

6 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardTo Be Applied-View NOC
KSPCB- PCB (10 Acres to 125 Acres)To Be Applied-View NOC
Engineering Department (PWD) for completion of development worksTo Be Applied-View NOC
KPTCL- BESCOMTo Be Applied-View NOC
Horticulture departmentTo Be Applied-View NOC

Project team & certifications

RERA filing

K-RERA names 2 project professional/vendor rows across Chartered accountant, Engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantRaghu Nanda Mandadi G2078462003Bengaluru Urban, Karnataka - 560085
EngineerSHASHIDAR K LBCC/BL-3.3/5-548/97-981997Bengaluru Rural, Karnataka - 562114

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2025-Q4): ₹23.87 Cr collected from buyers, ₹23.87 Cr withdrawn from the project's escrow account.

Construction progress80% → 100% (+20 pts)
Buyer collections in available QPRs₹42.84 Cr
Escrow withdrawals in available QPRs₹42.84 Cr (1.00x collections)
  • Construction progress moved from 80% to 100% across the filed QPR window.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

The estimated cost above is the developer's declared construction cost only (K-RERA's own label: "Estimated Cost of Construction as certified by Engineer") — it excludes land cost, so it isn't comparable to the buyer-collection figures below or to a sale price.

RERA 70% project account is on file: Canara Bank HOSKOTE IFSC Code : CNRB0005580 Pin Code : 562114. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~11 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Whitefield IT hub11 km
Kempegowda Int'l Airport17 km
Outer Ring Road / Manyata18 km
Bellandur–Marathahalli belt18 km
MG Road / city centre21 km
Electronic City28 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Avyanhp Sharayu.

Other RERA-registered projects in M V Extenstion

Major developers building in M V Extenstion

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Sidvin Symphony?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026