SILVER KITES - ELITE

· ESSENN INFRA TOWNSHIP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

100%construction reportedQ4 2025 filing

The record · free to read

Registration read 16 Jul 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q4 2025

declared completion

Not recorded

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 16 Jul 2026

Inventory & scale

What this registration contains.

Plot Size 9.14 X 15.24 Mtrs
82

Filed categories, unchanged · K-RERA registration · read 16 Jul 2026

The whole registration

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1254/465/PR/220923/006287

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Unit mix82 × Plot Size 9.14 X 15.24 Mtrs

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Approved plan numberDTCP-03/CBR/LAY/2022-23Use this to match the sanctioned drawing set shown by the builder.
Plan approval date18-08-2022
Project start date03-08-2023

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
Plot Size 9.14 X 15.24 Mtrs82100%11,422 sqm

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

All 43 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 30 Jun 2026 — which has passed with no OC on file.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (Electricity Permission Letter)
Water & sewage (BWSSB/KWSSB)✓ On file (Water Permission Letter)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

4 of 5 applicable approvals are on file; still outstanding: KPTCL- BESCOM. Confirm each has been granted, not merely applied for, before booking.

6 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved13-05-2024WATER SUPPLY.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved13-10-2021KSPCB - LETTER.pdf
Engineering Department (PWD) for completion of development worksApproved13-05-2024Engineer.pdf
KPTCL- BESCOMApplied25-10-2022View NOC
Horticulture departmentApproved14-05-2024Horticulture.pdf

Project team & certifications

RERA filing

K-RERA names 2 project professional/vendor rows across Chartered accountant, Engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantN.NITYANANDA & Co2289142005Bengaluru Urban, Karnataka - 560004
EngineerDIVAKARA B EBCCL/BL-3.6/E-0140/2023-242023Bengaluru Urban, Karnataka - 560056

Builder track record

RERA filing

Essenn Infra has 2 other K-RERA-registered projects in our records (average reported construction progress 86%). 0 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2025-Q4): ₹0.06 Cr collected from buyers, ₹1.69 Cr withdrawn from the project's escrow account. This quarter the escrow withdrawal (₹1.69 Cr) exceeded buyer collections (₹0.06 Cr) — worth asking the builder to reconcile against certified construction milestones, which is what RERA requires escrow draws to track.

Construction progress95% → 100% (+5 pts)
Buyer collections in available QPRs₹0.36 Cr
Escrow withdrawals in available QPRs₹3.60 Cr (9.91x collections)
  • Construction progress moved from 95% to 100% across the filed QPR window.
  • Across available QPR rows, escrow withdrawals are 9.91x buyer collections. Ask the builder to reconcile this against certified project costs and prior-period balances.
  • In the latest QPR, escrow withdrawal exceeds buyer collections for that quarter. This can be normal if prior balance existed, but it needs a clean explanation.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

The estimated cost above is the developer's declared construction cost only (K-RERA's own label: "Estimated Cost of Construction as certified by Engineer") — it excludes land cost, so it isn't comparable to the buyer-collection figures below or to a sale price.

RERA 70% project account is on file: Punjab National Bank Jayanagar IFSC Code : PUNB0099010 Pin Code : 560041. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~10 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
MG Road / city centre6 km
Outer Ring Road / Manyata10 km
Bellandur–Marathahalli belt16 km
Electronic City19 km
Whitefield IT hub21 km
Kempegowda Int'l Airport29 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Essenn Infra.
Essenn Infra has 3 projects registered in Bangalore, 2 completed.

Other projects by this builder in Bangalore

Silver Kites -Luxus
Filing overdue · 100% built
Silver Kites – Elite-1
Filing overdue · 71% built

Other RERA-registered projects in Rajajinagar

Major developers building in Rajajinagar

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.