Bangalore/Project record

K-RERA · the public record

SOVEREIGN UNNATHI

Bengaluru East · Sovereign Developer And Infrastructure

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2019declared completionK-RERA registration · read 20 Sep 2026
0registered unitsK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

RESIDENTIAL
115

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

10.8registered acres

0.0registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/446/PR/181219/002229

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 December 2019
Land area43,519 sq m (10.8 acres)
Unit mix115 × RESIDENTIAL

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Official carpet area18,482 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Registered land area43,519 sqmThe land area attached to this K-RERA registration.
Parking total (reconciled)1,812Separate filed counts; these categories may overlap and are not added together.
Open-parking field362Separate filed counts; these categories may overlap and are not added together.
Garage field1,812Separate filed counts; these categories may overlap and are not added together.
Project start date05-04-2010

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
RESIDENTIAL115100%18,482 sqm

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

All 14 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Dec 2019 — which has passed with no OC on file.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)Not found in catalog
Water & sewage (BWSSB/KWSSB)Not found in catalog
Fire NOCNot found in catalog
Pollution control (KSPCB)Not found in catalog
Environmental clearanceNot found in catalog
Airport Authority height clearanceNot found in catalog

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

⚠ Listed on K-RERA's official DEFAULTER list.

K-RERA complaint orders (2 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
GAURAV GUPTA vs SOVEREIGN DEVELOPERS & INFRASTRUCTURE LTD.Take action as per section 59(1) and 59(2)AUTHORITY23/08/2022
RACHIT GARG vs SOVEREIGN UNNATHIAs prayed in attached complaintAUTHORITY17/06/2025

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (7 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/181128/0001680
28-11-2018
Execution of sale deeds of flats despite project being not registered with RERASOVEREIGN UNNATHIDISPOSED AUTHORITY BENCH4
CMP/190418/0002639
18-04-2019
Refund of agreement amount with agreed compensation.SOVEREIGN UNNATHIDISPOSED AO
CMP/190627/0003360
27-06-2019
Pending Complaint and RERA registeration on fraudlent documentsSOVEREIGN UNNATHIDISPOSED AUTHORITY FULLBENCH
CMP/190711/0003521
11-07-2019
Flat No. B-03-09-01 Construction of the Flats are delayedSOVEREIGN UNNATHIDISPOSED AO
CMP/191021/0004529
21-10-2019
RETURN OF AMOUNT AND COMPENSATIONSOVEREIGN UNNATHIDISPOSED AO
CMP/191023/0004550
23-10-2019
RETURN OF AMOUNT AND COMPENSATIONSOVEREIGN UNNATHIDISPOSED AO
CMP/191023/0004555
23-10-2019
RETURN OF AMOUNT AND COMPENSATIONSOVEREIGN UNNATHIDISPOSED AO

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

The estimated cost above is the developer's declared construction cost only (K-RERA's own label: "Estimated Cost of Construction as certified by Engineer") — it excludes land cost, so it isn't comparable to the buyer-collection figures below or to a sale price.

RERA 70% project account is on file: KOTAK MAHINDRA BANK MALLESWARAM (IFSC KKBK0000418, a/c …1411). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Outer Ring Road / Manyata5 km
MG Road / city centre9 km
Bellandur–Marathahalli belt11 km
Whitefield IT hub11 km
Kempegowda Int'l Airport19 km
Electronic City21 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Sovereign Developer.
16 complaints on the K-RERA register against Sovereign Developer in Bangalore.

Other RERA-registered projects in Horamavu

Major developers building in Horamavu

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Sovereign Unnathi?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →