Bangalore/Project record

K-RERA · the public record

SOWPARNIKA INDRAPRASTHA

Hosakote · SOWPARNIKA PROJECTS AND INFRASTRUCTURE

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Mar 2022declared completionK-RERA registration · read 20 Sep 2026
268registered unitsK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Mar 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

Residential Apartments
268

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

1.7registered acres

162.4registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1250/304/PR/180601/001848

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 March 2022
Land area6,678 sq m (1.7 acres)
Homes registered268
Tower/wing entries1
Unit mix268 × Residential Apartments

In context

Density162.4 homes per acre
Density in context96th percentile of 112 Hosakote projects (median 79.1)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units268Total inventory registered with K-RERA.
Official carpet area10,468 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Registered land area6,678 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI1.84Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)194Separate filed counts; these categories may overlap and are not added together.
Open-parking field0Separate filed counts; these categories may overlap and are not added together.
Garage field196Separate filed counts; these categories may overlap and are not added together.
Project start date16-05-2018

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
Residential Apartments268100%10,468 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
13268194-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 268 official flat/unit rows, matching the 268 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2BHK11237.2-38.6 sqm23.6-24.4 sqm112
3BHK8450.7-56.3 sqm31.7-35.7 sqm84
1BHK5322.0-31.1 sqm14.4-20.1 sqm0 (53 with 0)
STUDIO1615.7 sqm11.8 sqm0 (16 with 0)
1.5BHK333.8-33.8 sqm22.1-22.8 sqm0 (3 with 0)

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
126815.7-56.3 sqm11.8-35.7 sqm196 (72 with 0)
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
101103BHK52.1 sqm32.6 sqm1
102103BHK51.3 sqm32.1 sqm1
103103BHK51.3 sqm32.1 sqm1
104103BHK51.3 sqm32.1 sqm1
105102BHK38.6 sqm24.4 sqm1
106102BHK38.6 sqm24.4 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

All 21 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Mar 2022, extended (Covid Extension) to 31 Dec 2022 — both dates have passed with no OC on file.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (BESCOM)
Water & sewage (BWSSB/KWSSB)✓ On file (BWSSB)
Fire NOCNot found in catalog
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearanceNot found in catalog
Airport Authority height clearanceNot found in catalog

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA complaint orders (2 complaints against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
POOJA THAKUR vs SOWPARNIKA INDRAPRASTAJUSTIFICATION FROM BUILDER TO GET MY COMPENSATION AMOUNTAUTHORITY09/05/2024
PREETHI P vs SOWPARNIKA INDRAPRASTHAHelp to get full refund with interest for delay and fraudulent information provided about ColumnsAUTHORITY09/01/2024

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (10 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/190324/0002438
24-03-2019
Flat - 122: Parking issue and delay penalty calculationSOWPARNIKA SANVI PHASE II (another project by this promoter)DISPOSED AO
CMP/190625/0003400
25-06-2019
DEFICIENCY OF SERVICE AND UNFAIR TRADE PRACTICESOWPARNIKA PURPLE ROSE (another project by this promoter)DISPOSED AO
CMP/201201/0007151
01-12-2020
Approval obtained for G+8 floors but selling till G+15 floors, not refunding the amount after cancellationSOWPARNIKA COLUMNS (another project by this promoter)DISPOSED AO
CMP/201201/0007152
01-12-2020
Approval obtained for G+8 floors but selling till G+15 floors, not refunding the amount after cancellationSOWPARNIKA COLUMNS (another project by this promoter)DISPOSED AO
CMP/210803/0008202
03-08-2021
Refund of amount against flat cancellationSOWPARNIKA COLUMNS (another project by this promoter)DISPOSED AO
CMP/220818/0009913
18-08-2022
Sowparnika Ashiyana - Not paying the refundSOWPARNIKA COLUMNS (another project by this promoter)DISPOSED AUTHORITY BENCH6
CMP/220901/0009964
01-09-2022
REFUND OF EXCESS AMOUNT CHARGED & ALLOTMENT OF SUITABLE CAR PARKING ALONG WITH ITS ALLOTMENT LETTERSOWPARNIKA SWASTIKA PHASE II (another project by this promoter)DISPOSED AUTHORITY BENCH6
CMP/220915/0010018
15-09-2022
Compensation for alterations in the original plan without the prior consent of the buyerSOWPARNIKA COLUMNS (another project by this promoter)DISPOSED AO

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Builder track record

RERA filing

Sowparnika Projects has 13 other K-RERA-registered projects in our records (average reported construction progress 100%). 10 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹11.1 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: STATE BANK OF INDIA Mahadevapura (IFSC SBIN0003028, a/c …7094). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.

Location & Connectivity

The nearest major job hub is ~8 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Whitefield IT hub8 km
Bellandur–Marathahalli belt16 km
Outer Ring Road / Manyata23 km
MG Road / city centre23 km
Electronic City24 km
Kempegowda Int'l Airport27 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Sowparnika Projects. View Sowparnika Projects's full track record →
Sowparnika Projects has 14 projects registered in Bangalore, 1 completed.
1 complaints on the K-RERA register against Sowparnika Projects in Bangalore.

Other projects by this builder in Bangalore

Sowparnika Ashiyana Phase II
Filing overdue · 100% built · 99% sold
Sowparnika Purple Rose
No filings
Sowparnika Sanvi Phase II
No filings
Sowparnika Swastika Phase II
No filings

Other RERA-registered projects in M V Extenstion

Major developers building in M V Extenstion

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Sowparnika Indraprastha?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026