Bangalore/Project record

K-RERA · the public record

SOWPARNIKA SWASTIKA PHASE II

Anekal · SOWPARNIKA PROJECTS AND INFRASTRUCTURE

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2017declared completionK-RERA registration · read 20 Sep 2026
280registered unitsK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2017

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

2 BHK & 3 BHK
280

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

2.9registered acres

97.4registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/308/PR/171031/001150

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 December 2017
Land area11,630 sq m (2.9 acres)
Homes registered280
Tower/wing entries1
Unit mix280 × 2 BHK & 3 BHK

In context

Density97.4 homes per acre
Density in context77th percentile of 471 Anekal projects (median 75.8)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units280Total inventory registered with K-RERA.
Official carpet area18,191 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Registered land area11,630 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI1.49Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)280Separate filed counts; these categories may overlap and are not added together.
Open-parking field116Separate filed counts; these categories may overlap and are not added together.
Garage field280Separate filed counts; these categories may overlap and are not added together.
Project start date16-02-2014

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
2 BHK & 3 BHK280100%18,191 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
17280280-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 280 official flat/unit rows, matching the 280 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
2BHK18459.0-64.0 sqm24.5-26.5 sqm184
3BHK8872.7-80.6 sqm30.4-33.5 sqm88
1BHK842.1 sqm16.9 sqm8

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
128042.1-80.6 sqm16.9-33.5 sqm280
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
AG01103BHK78.8 sqm33.5 sqm1
AG02102BHK59.3 sqm24.9 sqm1
AG03102BHK59.0 sqm24.5 sqm1
AG04102BHK59.3 sqm24.9 sqm1
AG05102BHK62.9 sqm26.2 sqm1
AG06102BHK63.2 sqm25.8 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

All 23 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

⚠ Registration validity has lapsed: originally due 31 Dec 2017 — which has passed with no OC on file.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (All NOCs from Authority)
Water & sewage (BWSSB/KWSSB)✓ On file (All NOCs from Authority)
Fire NOC✓ On file (All NOCs from Authority)
Pollution control (KSPCB)✓ On file (All NOCs from Authority)
Environmental clearance✓ On file (All NOCs from Authority)
Airport Authority height clearance✓ On file (All NOCs from Authority)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA complaint orders (1 complaint against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
ARUNENDRA KUMAR SHUKLA vs SOWPARNIKA PROJECTS AND INFRASTRUCTURE PRIVATE LIMITED1)A REFUND OF RS 15,00000/- APPROX AS PER ACTUALS ALONG WITH APPLICABLE BANK INTEREST. 2)SUITABLE CAR PARKING(WITH ALLOTMENT LETTER) AS PER SIZE AND SPECIFICATIONS UPLOADED BY BUILDER ON RERA PORTALAUTHORITY16/03/2023

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (10 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/190324/0002438
24-03-2019
Flat - 122: Parking issue and delay penalty calculationSOWPARNIKA SANVI PHASE II (another project by this promoter)DISPOSED AO
CMP/190625/0003400
25-06-2019
DEFICIENCY OF SERVICE AND UNFAIR TRADE PRACTICESOWPARNIKA PURPLE ROSE (another project by this promoter)DISPOSED AO
CMP/201201/0007151
01-12-2020
Approval obtained for G+8 floors but selling till G+15 floors, not refunding the amount after cancellationSOWPARNIKA COLUMNS (another project by this promoter)DISPOSED AO
CMP/201201/0007152
01-12-2020
Approval obtained for G+8 floors but selling till G+15 floors, not refunding the amount after cancellationSOWPARNIKA COLUMNS (another project by this promoter)DISPOSED AO
CMP/210803/0008202
03-08-2021
Refund of amount against flat cancellationSOWPARNIKA COLUMNS (another project by this promoter)DISPOSED AO
CMP/220818/0009913
18-08-2022
Sowparnika Ashiyana - Not paying the refundSOWPARNIKA COLUMNS (another project by this promoter)DISPOSED AUTHORITY BENCH6
CMP/220901/0009964
01-09-2022
REFUND OF EXCESS AMOUNT CHARGED & ALLOTMENT OF SUITABLE CAR PARKING ALONG WITH ITS ALLOTMENT LETTERSOWPARNIKA SWASTIKA PHASE IIDISPOSED AUTHORITY BENCH6
CMP/220915/0010018
15-09-2022
Compensation for alterations in the original plan without the prior consent of the buyerSOWPARNIKA COLUMNS (another project by this promoter)DISPOSED AO

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Builder track record

RERA filing

Sowparnika Projects has 13 other K-RERA-registered projects in our records (average reported construction progress 100%). 10 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹17.2 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: HDFC OLD AIRPORT ROAD (IFSC HDFC0000075, a/c …0215). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.

Location & Connectivity

The nearest major job hub is ~14 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Electronic City14 km
Bellandur–Marathahalli belt18 km
Whitefield IT hub19 km
MG Road / city centre27 km
Outer Ring Road / Manyata32 km
Kempegowda Int'l Airport45 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Sowparnika Projects. View Sowparnika Projects's full track record →
Sowparnika Projects has 14 projects registered in Bangalore, 1 completed.
1 complaints on the K-RERA register against Sowparnika Projects in Bangalore.

Other projects by this builder in Bangalore

Sowparnika Ashiyana Phase II
Filing overdue · 100% built · 99% sold
Sowparnika Indraprastha
No filings
Sowparnika Purple Rose
No filings
Sowparnika Sanvi Phase II
No filings

Other RERA-registered projects in BEML Cooperative Society Layout

Sobha Manhattan Towers-Town Park Phase 1 W 4 & 5

Major developers building in BEML Cooperative Society Layout

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.