Bangalore/Project record

K-RERA · the public record

The Edge

Bengaluru North · Arvind SmartSpaces

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

100%construction reportedQ4 2025 filing
48units not bookedof 116 · Q4 2025 filing
30 Jun 2026declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q4 2025

declared completion

30 Jun 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

Showrooms & Professional Offices
116

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

1.0registered acres

113.4registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/309/PR/190823/002822

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion30 June 2026
Land area4,140 sq m (1.0 acres)
Units registered116
Tower/wing entries1
Unit mix116 × Showrooms & Professional Offices

In context

Density113.4 units per acre
Density in context86th percentile of 525 Bengaluru North projects (median 75.4)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units116Total inventory registered with K-RERA.
Official carpet area10,435 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Registered land area4,140 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI~3.25Sanctioned floor-area ratio (≈13,454 sqm sanctioned FAR area ÷ 4,140 sqm land) — higher means a denser vertical build.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)294Separate filed counts; these categories may overlap and are not added together.
Open-parking field24Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Project start date29-06-2019

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
Showrooms & Professional Offices116100%10,435 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
A13116294-

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 116 official flat/unit rows, matching the 116 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
SHOP11636.3-312.9 sqm0.0 sqm0 (116 with 0)

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
A11636.3-312.9 sqm0.0 sqm0 (116 with 0)
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
00 1A0SHOP174.9 sqm0.0 sqm0
00 2A0SHOP245.5 sqm0.0 sqm0
00 3A0SHOP119.5 sqm0.0 sqm0
00 4A0SHOP88.5 sqm0.0 sqm0
00 5A0SHOP128.8 sqm0.0 sqm0
101A1SHOP312.9 sqm0.0 sqm0

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

All 48 standard compliance document slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (BESCOM)
Water & sewage (BWSSB/KWSSB)✓ On file (BWSSB)
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)✓ On file (KSPCB)
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

K-RERA enforcement record (the regulator's own defaulter list & penalty orders)

2 K-RERA orders on this project (PROJECT EXTENSION, PROJECT MODIFICATION) — read the order copies on the K-RERA portal.

K-RERA complaint orders (1 complaint against a project of this name on K-RERA's orders register)

PartiesRelief soughtDisposalOrder date
PRABHAKAR H N vs THE EDGELooking forward for refund of Booking Amount along with interestAUTHORITY11/06/2024

⚠ Matched by PROJECT NAME (the orders register carries no registration number) — confirm the respondent above is this project's builder before relying on it.

Complaints on this project's K-RERA page (3 complaints listed against this promoter)

ComplaintSubject (as filed)ProjectStatus
CMP/190720/0003648
20-07-2019
Open Car Parking Selling and AllotmentArvind Sporcia (another project by this promoter)DISPOSED AUTHORITY FULLBENCH
CMP/200622/0006062
22-06-2020
Non refundable of booking amount of Rs 6,17,695.00 by builder (10% amount)Arvind Skylands (another project by this promoter)DISPOSED AUTHORITY BENCH4
CMP/221230/0010581
30-12-2022
Seepage and Legal DocumentsArvind Sporcia (another project by this promoter)DISPOSED AUTHORITY BENCH5

Listed on the project's own K-RERA detail page (registration-exact source). Rows on the promoter's other projects are track-record context — read the subject text, it is the complainant's own filed wording.

Statutory approval status

RERA filing

Clean approvals profile: every applicable statutory NOC is on file — including Fire NOC, environmental clearance and pollution-control clearance (KSPCB), the clearances buyers most often find still pending. Nothing is outstanding among the statutory NOCs — which compliance documents are filed versus still under process is a separate matter, covered in Litigation & compliance above. Since these are developer-filed portal statuses, have your lawyer confirm them against the linked NOC copies.

3 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile
Water supply and sewage boardApproved12-03-2019Edge BWSSB NOC.pdf
KSPCB- PCB (10 Acres to 125 Acres)Approved18-05-2019Edge CTE KSPCB NOC.pdf
KSPCB- MOEF (Above 50 Acres)Approved27-03-2019Edge MOEF NOC.pdf
KPTCL- BESCOMApproved22-12-2018Edge BESCOM NOC.pdf
Fire and SafetyApproved11-01-2019Arvind Edge Fire CC Final.pdf
Airport Authority of IndiaApproved07-01-2019Edge AAI NOC.pdf
BSNL/Telecommunication DepartmentApproved14-12-201835BSNL NOC.pdf

Project team & certifications

RERA filing

K-RERA names 3 project professional/vendor rows across Architect, Contractor, Structural engineer. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
ArchitectApurva Amin Architects-1996Off. Sindhu Bhavan Road, Bodakdev
ContractorBHAIRAVA EARTH MOVERS-2014OMBR LAYOUT, BANASWADI
Structural engineerALFA Consultancy services---

Builder track record

RERA filing

Arvind Smartspaces has 3 other K-RERA-registered projects in our records (average reported construction progress 50%). 2 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2025-Q4): ₹12.68 Cr collected from buyers, ₹13.20 Cr withdrawn from the project's escrow account. This quarter the escrow withdrawal (₹13.20 Cr) exceeded buyer collections (₹12.68 Cr) — worth asking the builder to reconcile against certified construction milestones, which is what RERA requires escrow draws to track.

Construction progress100% → 100% (+0 pts)
Units sold/booked as registered68/116 (59%)
Buyer collections in available QPRs₹12.95 Cr
Escrow withdrawals in available QPRs₹16.36 Cr (1.26x collections)
  • Across available QPR rows, escrow withdrawals are 1.26x buyer collections. Ask the builder to reconcile this against certified project costs and prior-period balances.
  • In the latest QPR, escrow withdrawal exceeds buyer collections for that quarter. This can be normal if prior balance existed, but it needs a clean explanation.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹40.9 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: YES BANK C. G. Road Branch (IFSC YESB0000007, a/c …0154). RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Construction photo filings

RERA filing

K-RERA has 1 project-photo upload.

These are developer-uploaded progress photos in the official document catalog. We do not treat them as proof of current site condition; use them as a prompt to ask for newer dated photos or a site visit. Individual filings are listed in the document catalog below.

Location & Connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bellandur–Marathahalli belt2 km
Electronic City8 km
MG Road / city centre10 km
Whitefield IT hub10 km
Outer Ring Road / Manyata15 km
Kempegowda Int'l Airport32 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Arvind Smartspaces.
Arvind Smartspaces has 4 projects registered in Bangalore, 1 completed.

Other projects by this builder in Bangalore

Arvind Forest Trails
On track · 50% built · 55% sold

Other RERA-registered projects in Chikkakannalli

Major developers building in Chikkakannalli

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in The Edge?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026