Bangalore/Project record

K-RERA · the public record

TRIFECTA VANTO PHASE-2

Bengaluru South · TRIFECTA PROJECTS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

50%construction reportedQ1 2026 filing
132units not bookedof 202 · Q1 2026 filing
31 Mar 2028declared completionK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Promoter-reported construction

K-RERA quarterly filings · Q3 2025 to Q1 2026

declared completion

31 Mar 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

1BHK
4
3 BHK
198

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

3.0registered acres

67.3registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project · Prestige Park Grove

A larger advertised area. Almost the same carpet area.

In Tower 14, E4 has 141 sq ft more saleable area than E2. Its carpet area is only 0.46 sq m larger. The report puts the two layouts side by side.

This illustrates the report format. These findings concern the named sample, not this project.

Read the sample report ↗
Prestige Park Grove · Tower 14 comparison · approved sample report
Prestige Park Grove · Tower 14 comparison · approved sample report

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/310/PR/250625/007871

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 March 2028
Land area12,140 sq m (3.0 acres)
Homes registered202
Tower/wing entries1
Unit mix4 × 1BHK, 198 × 3 BHK

In context

Density67.3 homes per acre
Density in context35th percentile of 787 Bengaluru South projects (median 77.3)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units202Total inventory registered with K-RERA.
Official carpet area27,036 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area38,562 sqmUseful scale context when comparing density and project cost.
Registered land area12,140 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.25Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)202Separate filed counts; these categories may overlap and are not added together.
Covered-parking field202Separate filed counts; these categories may overlap and are not added together.
Open-parking field9Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberBDA/EM/EO-1/TA-2/E/69/2024-25Use this to match the sanctioned drawing set shown by the builder.
Plan approval date01-04-2025
Project start date01-04-2025

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
1BHK42%208 sqm
3 BHK19898%20,298 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
Tower C2420220277 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 202 official flat/unit rows, matching the 202 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
3 BHK19896.0-111.0 sqm57.0-66.0 sqm198
1 BHK446.0-57.0 sqm27.0-34.0 sqm4

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
Tower C20246.0-111.0 sqm27.0-66.0 sqm202
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
F-034Tower C03 BHK106.0 sqm63.0 sqm1
F-035Tower C03 BHK111.0 sqm66.0 sqm1
F-036ATower C01 BHK57.0 sqm34.0 sqm1
F-036BTower C01 BHK46.0 sqm27.0 sqm1
F-037Tower C03 BHK96.0 sqm57.0 sqm1
F-038Tower C03 BHK96.0 sqm57.0 sqm1

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

18 of 34 compliance document slots are filed as Not Applicable; the remaining 16 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)Not found in catalog
Water & sewage (BWSSB/KWSSB)Not found in catalog
Fire NOC✓ On file (Fire Force Department)
Pollution control (KSPCB)Not found in catalog
Environmental clearance✓ On file (SEIAA)
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Statutory approval status

RERA filing

10 further authority slots are marked not applicable by the regulator.

Authority / NOCStatusDateFile

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantB Manohar Babu2214552008Bengaluru Urban, Karnataka - 560020
EngineerRamesh BBCCL/BL.3.6/SE-0204/20-212000Bengaluru Urban, Karnataka - 561257
ArchitectRevathi SRCA/2008/431022008Bengaluru Urban, Karnataka - 560068
ContractorTRIFECTA PROJECTS PRIVATE LIMITED-2020Bengaluru Urban, Karnataka - 560048

Builder track record

RERA filing

Trifecta Projects has 8 other K-RERA-registered projects in our records (average reported construction progress 74%). 4 are past their declared completion deadline with no completion certificate recorded — but because K-RERA publishes OCs inconsistently, a project that has actually been finished and handed over still shows up this way, so this overstates real delays, especially for a high-volume established builder. That is a lower delayed rate than the K-RERA average across Bengaluru on the same measure.

Read this as a list to spot-check for a pattern of genuinely stalled projects, not as a delay rate — pull up a few of the builder’s other K-RERA registrations and check whether they’ve actually been delivered.

Financials & Construction Progress

Financial disclosures

RERA filing

Latest quarterly filing (2026-Q1): ₹22.22 Cr collected from buyers, ₹22.22 Cr withdrawn from the project's escrow account.

Construction progress30% → 50% (+20 pts)
Units sold/booked as registered70/202 (35%)
Buyer collections in available QPRs₹53.99 Cr
Escrow withdrawals in available QPRs₹51.01 Cr (0.94x collections)
  • Construction progress moved from 30% to 50% across the filed QPR window.

QPR figures are developer-filed quarterly disclosures. Collections and withdrawals are not a project valuation; they are a sanity check for whether sales, construction progress, and escrow draws appear directionally aligned.

Declared construction cost ÷ registered units averages to ₹66.1 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: HDFC Mahadevapura Branch IFSC Code : HDFC0001045 Pin Code : 560016. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Electronic City6 km
Bellandur–Marathahalli belt7 km
Whitefield IT hub11 km
MG Road / city centre16 km
Outer Ring Road / Manyata21 km
Kempegowda Int'l Airport36 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Trifecta Projects. View Trifecta Projects's full track record →
Trifecta Projects has 9 projects registered in Bangalore, 1 completed.
2 complaints on the K-RERA register against Trifecta Projects in Bangalore.

Other projects by this builder in Bangalore

Trifecta Vanto Phase-1
On track · 87% built · 50% sold
Trifecta Verde EN Resplandor Phase 1
No filings
Trifecta Verde EN Resplandor ROW House Phase-2
No filings
Trifecta Verde EN Resplandor Villa Phase 3
On track · 92% built
Trifecta Verde Enresplandor Villa Phase-2
No filings

Other RERA-registered projects in Chikkakannalli

Major developers building in Chikkakannalli

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in Trifecta Vanto Phase-2?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026