Bangalore/Project record

K-RERA · the public record

VRR GOLDEN ENCLAVE PHASE II

Anekal · H N VIJAYARAGHAVA REDDY CO

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2027declared completionK-RERA registration · read 20 Sep 2026
46registered unitsK-RERA registration · read 20 Sep 2026

The record · free to read

Registration read 20 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

K-RERA registration · read 20 Sep 2026

Inventory & scale

What this registration contains.

Villa
46

Filed categories, unchanged · K-RERA registration · read 20 Sep 2026

The whole registration

7.0registered acres

6.6registered units per acre

The average covers the registered land and all registered unit types. It does not describe the space, outlook or surroundings of an individual home.

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

K-RERA · PRM/KA/RERA/1251/308/PR/211222/005548

This project, on the record

The comparable facts of this project, from its own RERA registration record. Each context percentile names its exact comparison set, drawn from Quietlist’s full register store. The paid report adds drawing-read rows to this same table — what the filed plans show about the site, its edges and the unit layouts.

On the register

Declared completion31 December 2027
Land area28,327 sq m (7.0 acres)
Homes registered46
Tower/wing entries1
Unit mix46 × Villa

In context

Density6.6 homes per acre
Density in context1st percentile of 471 Anekal projects (median 75.8)

Values as crawled from the official K-RERA record; context percentiles name their comparison population.

Official Registry Facts

Official project scale

RERA filing

Registration-form facts from the K-RERA detail page: use these to sanity-check the builder brochure, parking allotment, and sanctioned-plan references before relying on plan-extracted approximations.

DisclosureOfficial valueWhy it matters
Registered units46Total inventory registered with K-RERA.
Official carpet area20,269 sqmRegulator-disclosed project-level carpet area, not vision-derived room sums.
Official built-up area23,779 sqmUseful scale context when comparing density and project cost.
Registered land area28,327 sqmThe land area attached to this K-RERA registration.
Sanctioned FAR/FSI2.5Higher FAR generally means a denser vertical build, subject to site layout and open-space design.
Registered tower/wing entries1Official tower/wing count in the K-RERA detail page.
Parking total (reconciled)115Separate filed counts; these categories may overlap and are not added together.
Covered-parking field26Separate filed counts; these categories may overlap and are not added together.
Open-parking field209Separate filed counts; these categories may overlap and are not added together.
Garage field0Separate filed counts; these categories may overlap and are not added together.
Approved plan numberNM/AS/AA03/TS02/S/05/2021-22Use this to match the sanctioned drawing set shown by the builder.
Plan approval date13-09-2021
Project start date01-08-2021

Official inventory & towers

RERA filing

K-RERA registration tables showing the project mix and tower/wing scale. Use this to sanity-check sales claims such as "only large homes", "low density", or "plenty of parking" against the filed inventory.

Registered inventory mix

TypeUnitsShareOfficial carpet area
Villa46100%20,269 sqm

Registered tower / wing summary

Tower/wingFloorsUnitsParkingHeight
GOLDEN ENCLAVE PHASE-II34611511 m

Official unit register

RERA filing

K-RERA detail-page flat rows: exact unit numbers, official carpet area, UDS, and parking lots. 46 official flat/unit rows, matching the 46 registered units disclosed above. Use this as a checklist against the specific flat number in your cost sheet and draft agreement.

By unit type

Unit typeRowsCarpet areaUDSParking lots
villa38245.0-265.0 sqm190.0-204.0 sqm76
1 BHK843.0 sqm42.0 sqm8

By tower / wing

Tower/wingRowsCarpet areaUDSParking lots
GOLDEN ENCLAVE PHASE-II4643.0-265.0 sqm42.0-204.0 sqm84
Show sample official unit rows
UnitTowerFloorTypeCarpetUDSParking
A1GOLDEN ENCLAVE PHASE-II0villa245.0 sqm202.0 sqm2
A2GOLDEN ENCLAVE PHASE-II0villa245.0 sqm199.0 sqm2
A3GOLDEN ENCLAVE PHASE-II0villa245.0 sqm202.0 sqm2
A4GOLDEN ENCLAVE PHASE-II0villa262.0 sqm204.0 sqm2
A5GOLDEN ENCLAVE PHASE-II0villa262.0 sqm204.0 sqm2
A6GOLDEN ENCLAVE PHASE-II0villa262.0 sqm204.0 sqm2

Legal, Approvals & Project Team

Litigation & compliance

RERA filing

No litigation declared on this project's K-RERA filing.

4 of 32 compliance document slots are filed as Not Applicable; the remaining 28 slots have usable uploaded filings.

No completion certificate (OC) on file yet — project has not been declared complete.

Named utility/regulatory approvals

Electricity (BESCOM/ESCOM)✓ On file (Electricity Permission Letter)
Water & sewage (BWSSB/KWSSB)✓ On file (Water Permission Letter)
Fire NOCNot found in catalog
Pollution control (KSPCB)Not found in catalog
Environmental clearanceNot found in catalog
Airport Authority height clearance✓ On file (Airport Authority of India)

"Not found in catalog" can mean the approval genuinely isn't on file yet, or that it doesn't apply to this project (K-RERA doesn't tell us which). Ask the builder directly for any marked not found before relying on it.

Project team & certifications

RERA filing

K-RERA names 4 project professional/vendor rows across Chartered accountant, Engineer, Architect, Contractor. Use this to cross-check whose certificates, drawings, and contractor commitments support the filing; final reliance still belongs with your lawyer/technical reviewer.

RoleNameRegistration / licenceSinceLocality
Chartered accountantK Mallappa2030421993Bengaluru Urban, Karnataka - 560003
EngineerY BhaskarBCC/BL-3.6/SE-0315/2019-202019Bengaluru Urban, Karnataka - 560008
ArchitectB.satyanarayanaBCC/BL-3.2.3/A-799/97-981998Bengaluru Urban, Karnataka - 560032
ContractorH.N.Vijaya Raghava Reddy & Co (Self)-1984Bengaluru Urban, Karnataka - 560095

Financials & Construction Progress

Financial disclosures

RERA filing

⚠ No quarterly financial disclosures (collections, escrow withdrawals) on record, despite no completion certificate yet — meaning we can't verify the project's cashflows against its construction progress. Worth asking the builder directly why no quarterly filings are available.

Declared construction cost ÷ registered units averages to ₹56.6 lakhs per unit — the developer's own declared construction/development cost, not a sale price. K-RERA filings don't disclose what the builder is charging, so this can't tell you whether you're getting a fair deal — only you comparing your quoted price against comparable listings nearby can answer that.

RERA 70% project account is on file: Karnataka Bank Ltd. Koramangala IFSC Code : KARB0000094 Pin Code : 560034. RERA requires 70% of buyer collections to sit in this separate, project-specific account, drawn only against certified construction milestones — confirm your payments are made to THIS account (not a general builder account) and that it appears on your allotment letter.

Location & Connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Electronic City3 km
Bellandur–Marathahalli belt13 km
MG Road / city centre18 km
Whitefield IT hub19 km
Outer Ring Road / Manyata25 km
Kempegowda Int'l Airport42 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Built by Vijayaraghava Reddy.
Vijayaraghava Reddy has 2 projects registered in Bangalore, 1 completed.

Other projects by this builder in Bangalore

VRR Golden Enclave Phase-III
On track · 98% built · 46% sold

Other RERA-registered projects in Electronic City

Major developers building in Electronic City

Figures are the developer's own quarterly disclosures on the Karnataka RERA register. "Built" is the highest construction % filed; "sold" is booked units over total. Not a claim about the developer's intent. Explore every project on our Bangalore project-health tool.

Own a unit in VRR Golden Enclave Phase II?

Sell directly to Quietlist's pre-screened buyer list — flat fee, no broker commission.

List your unit →

Last checked against the RERA register: 20 Sep 2026