HRERA · the public record
Atulyam 83
SECTOR - 83, GURUGRAM · Pegasus Developers
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 20 Sep 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
registration expiry
31 Mar 2026
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
HRERA registration · read 20 Sep 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
HRERA ·
Escrow account
What has moved through the RERA escrow account?
Across 13 filed quarterly reports, Atulyam 83 records ₹8.92 Cr paid into and ₹8.92 Cr withdrawn from its RERA escrow account, with a latest recorded balance of ₹0 L.
₹8.92 Cr
into the escrow account
₹8.92 Cr
withdrawn
₹0 L
latest balance
Amounts as filed in the developer's own quarterly progress reports to HRERA, summed across the quarters on record.
Source · HRERA quarterly progress reports
Sales Traction, Quarter by Quarter
Units the developer reported booking in each quarterly HRERA filing — the closest public read on real demand.
| Quarter | Units booked | Total units |
|---|---|---|
| 2023 Q2 | 47 | 89 |
| 2023 Q3 | 7 | 89 |
| 2023 Q4 | 16 | 89 |
| 2024 Q1 | 2 | 89 |
| 2024 Q2 | 0 | 89 |
| 2024 Q3 | 0 | 89 |
| 2024 Q4 | 0 | 89 |
| 2025 Q1 | 0 | 89 |
| 2025 Q2 | 0 | 89 |
| 2025 Q3 | 0 | 89 |
| 2025 Q4 | 0 | 89 |
| 2026 Q1 | 0 | 89 |
| 2026 Q2 | 0 | 890 |
Escrow Account Activity
Money moving through the RERA-mandated escrow account each quarter. Withdrawals from it are statutorily meant to fund construction milestones.
| Quarter | Deposited | Withdrawn | Balance |
|---|---|---|---|
| 2023 Q2 | ₹2.06 Cr | ₹2.05 Cr | ₹2 L |
| 2023 Q3 | ₹1.73 Cr | ₹1.74 Cr | ₹0 L |
| 2023 Q4 | ₹99 L | ₹98 L | ₹1 L |
| 2024 Q1 | ₹3.24 Cr | ₹3.25 Cr | ₹0 L |
| 2024 Q2 | ₹75 L | ₹75 L | ₹0 L |
| 2024 Q3 | ₹14 L | ₹14 L | ₹0 L |
| 2024 Q4 | ₹0 L | ₹0 L | ₹0 L |
| 2025 Q1 | ₹0 L | ₹0 L | ₹0 L |
| 2025 Q2 | ₹0 L | ₹0 L | ₹0 L |
| 2025 Q3 | ₹0 L | ₹0 L | ₹0 L |
| 2025 Q4 | ₹0 L | ₹0 L | ₹0 L |
| 2026 Q1 | ₹0 L | ₹0 L | ₹0 L |
| 2026 Q2 | ₹0 L | ₹0 L | ₹0 L |
Location & Connectivity
The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.
| Landmark | Straight-line |
|---|---|
| IMT Manesar | 5 km |
| Golf Course Road belt | 14 km |
| Cyber City / DLF Cyber Hub | 16 km |
| Udyog Vihar | 16 km |
| IGI Airport, Delhi | 22 km |
| Connaught Place, Delhi | 35 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.