Registration read 20 Sep 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
registration expiry
30 Sep 2034
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
HRERA registration · read 20 Sep 2026
Inside this project’s sample report
Six towers. Choose the side, then the floor.
B’s north-west living side leads the inward-facing shortlist; C’s east-south-east and D’s east-north-east sides offer morning-facing alternatives. The report compares future Phase IX, refuge-floor services and home layouts. Read 18 September 2026; the draft possession date is 31 December 2034, not current readiness or availability.
Read the sample report ↗
The source record
The details behind the headline.
HRERA ·
Escrow account
What has moved through the RERA escrow account?
Across 4 filed quarterly reports, Dlf Privana North records ₹2339.74 Cr paid into and ₹-783.48 Cr withdrawn from its RERA escrow account, with a latest recorded balance of ₹1949.12 Cr.
₹2339.74 Cr
into the escrow account
₹-783.48 Cr
withdrawn
₹1949.12 Cr
latest balance
Amounts as filed in the developer's own quarterly progress reports to HRERA, summed across the quarters on record.
Source · HRERA quarterly progress reports
Official Unit Inventory
1164 apartments filed across 2 carpet-area configurations, 12 towers, carpet areas from 2,236 to 4,847 sq ft. These are the carpet areas the developer filed with HRERA — match the unit a broker quotes you against this table; a "1,650 sq ft" pitch should map to a filed configuration here (carpet area is the RERA-defined saleable floor).
| Carpet area | (metric) | Units of this size |
|---|---|---|
| 4,847 sq ft | 450.3 sq m | 12 |
| 2,236 sq ft | 207.7 sq m | 1152 |
Sales Traction, Quarter by Quarter
Units the developer reported booking in each quarterly HRERA filing — the closest public read on real demand.
| Quarter | Units booked | Total units |
|---|---|---|
| 2025 Q3 | 0 | — |
| 2025 Q4 | 65 | 1169 |
| 2026 Q1 | 10 | 1169 |
| 2026 Q2 | 14 | 1169 |
Escrow Account Activity
Money moving through the RERA-mandated escrow account each quarter. Withdrawals from it are statutorily meant to fund construction milestones.
| Quarter | Deposited | Withdrawn | Balance |
|---|---|---|---|
| 2025 Q3 | ₹404.02 Cr | ₹-176.87 Cr | ₹620.01 Cr |
| 2025 Q4 | ₹1037.74 Cr | ₹-420.71 Cr | ₹1237.05 Cr |
| 2026 Q1 | ₹485.97 Cr | ₹-108.00 Cr | ₹1615.01 Cr |
| 2026 Q2 | ₹412.01 Cr | ₹-77.90 Cr | ₹1949.12 Cr |
Builder Record
DLF has 43 other Gurgaon projects on the HRERA register; 0 are past the declared completion date with no OC yet, 33 delivered. Read it as a spot-check list for a pattern, not a delay rate.
- Alameda Central — declared 2027-09-08 · OC on record
- Arcade 68 — declared 2027-11-10 · OC on record
- Central 67 — declared 2027-12-31 · OC on record
- Central 74 — declared 2028-09-06
Location & Connectivity
The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.
| Landmark | Straight-line |
|---|---|
| IMT Manesar | 6 km |
| Golf Course Road belt | 13 km |
| Cyber City / DLF Cyber Hub | 16 km |
| Udyog Vihar | 16 km |
| IGI Airport, Delhi | 22 km |
| Connaught Place, Delhi | 35 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.