Registration read 20 Sep 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
registration expiry
31 Dec 2031
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
HRERA registration · read 20 Sep 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
HRERA ·
Escrow account
What has moved through the RERA escrow account?
Across 8 filed quarterly reports, Dlf Privana West records ₹1623.83 Cr paid into and ₹-903.04 Cr withdrawn from its RERA escrow account, with a latest recorded balance of ₹1132.80 Cr.
₹1623.83 Cr
into the escrow account
₹-903.04 Cr
withdrawn
₹1132.80 Cr
latest balance
Amounts as filed in the developer's own quarterly progress reports to HRERA, summed across the quarters on record.
Source · HRERA quarterly progress reports
Official Unit Inventory
795 apartments filed across 2 carpet-area configurations, 10 towers, carpet areas from 2,136 to 3,562 sq ft. These are the carpet areas the developer filed with HRERA — match the unit a broker quotes you against this table; a "1,650 sq ft" pitch should map to a filed configuration here (carpet area is the RERA-defined saleable floor).
| Carpet area | (metric) | Units of this size |
|---|---|---|
| 3,562 sq ft | 330.9 sq m | 10 |
| 2,136 sq ft | 198.5 sq m | 785 |
Sales Traction, Quarter by Quarter
Units the developer reported booking in each quarterly HRERA filing — the closest public read on real demand.
| Quarter | Units booked | Total units |
|---|---|---|
| 2024 Q3 | 16 | 795 |
| 2024 Q4 | 6 | 795 |
| 2025 Q1 | 2 | 795 |
| 2025 Q2 | 0 | 795 |
| 2025 Q3 | 0 | 795 |
| 2025 Q4 | 0 | 795 |
| 2026 Q1 | 0 | 795 |
| 2026 Q2 | 0 | 795 |
Escrow Account Activity
Money moving through the RERA-mandated escrow account each quarter. Withdrawals from it are statutorily meant to fund construction milestones.
| Quarter | Deposited | Withdrawn | Balance |
|---|---|---|---|
| 2024 Q3 | ₹517.36 Cr | ₹-112.00 Cr | ₹817.36 Cr |
| 2024 Q4 | ₹99.69 Cr | ₹-105.93 Cr | ₹811.12 Cr |
| 2025 Q1 | ₹411.54 Cr | ₹-84.65 Cr | ₹1138.02 Cr |
| 2025 Q2 | ₹42.71 Cr | ₹-81.46 Cr | ₹1099.27 Cr |
| 2025 Q3 | ₹46.17 Cr | ₹-117.78 Cr | ₹1027.65 Cr |
| 2025 Q4 | ₹367.31 Cr | ₹-82.25 Cr | ₹1312.71 Cr |
| 2026 Q1 | ₹66.36 Cr | ₹-139.20 Cr | ₹1239.88 Cr |
| 2026 Q2 | ₹72.69 Cr | ₹-179.77 Cr | ₹1132.80 Cr |
Builder Record
DLF has 43 other Gurgaon projects on the HRERA register; 0 are past the declared completion date with no OC yet, 33 delivered. Read it as a spot-check list for a pattern, not a delay rate.
- Alameda Central — declared 2027-09-08 · OC on record
- Arcade 68 — declared 2027-11-10 · OC on record
- Central 67 — declared 2027-12-31 · OC on record
- Central 74 — declared 2028-09-06
Location & Connectivity
The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.
| Landmark | Straight-line |
|---|---|
| IMT Manesar | 6 km |
| Golf Course Road belt | 13 km |
| Cyber City / DLF Cyber Hub | 16 km |
| Udyog Vihar | 16 km |
| IGI Airport, Delhi | 22 km |
| Connaught Place, Delhi | 35 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.