HRERA · the public record
Mapsko Aspr Hills
SECTOR 78, VILL - NAURANGPUR, GURUGRAM, HARYANA · Mapsko Builders
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 20 Sep 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
registration expiry
25 Dec 2027
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
HRERA registration · read 20 Sep 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
HRERA ·
Escrow account
What has moved through the RERA escrow account?
Across 12 filed quarterly reports, Mapsko Aspr Hills records ₹115.79 Cr paid into and ₹115.31 Cr withdrawn from its RERA escrow account, with a latest recorded balance of ₹48 L.
₹115.79 Cr
into the escrow account
₹115.31 Cr
withdrawn
₹48 L
latest balance
Amounts as filed in the developer's own quarterly progress reports to HRERA, summed across the quarters on record.
Source · HRERA quarterly progress reports
Sales Traction, Quarter by Quarter
Units the developer reported booking in each quarterly HRERA filing — the closest public read on real demand.
| Quarter | Units booked | Total units |
|---|---|---|
| 2023 Q2 | 80 | 147 |
| 2023 Q3 | 5 | 147 |
| 2023 Q4 | 2 | 147 |
| 2024 Q1 | 21 | 147 |
| 2024 Q2 | 0 | 147 |
| 2024 Q3 | 2 | 147 |
| 2024 Q4 | 2 | 147 |
| 2025 Q1 | 0 | 147 |
| 2025 Q2 | 4 | 147 |
| 2025 Q3 | -3 | 147 |
| 2025 Q4 | -1 | 147 |
| 2026 Q1 | 3 | 147 |
Escrow Account Activity
Money moving through the RERA-mandated escrow account each quarter. Withdrawals from it are statutorily meant to fund construction milestones.
| Quarter | Deposited | Withdrawn | Balance |
|---|---|---|---|
| 2023 Q2 | ₹12.41 Cr | ₹12.21 Cr | ₹20 L |
| 2023 Q3 | ₹6.80 Cr | ₹6.05 Cr | ₹95 L |
| 2023 Q4 | ₹4.93 Cr | ₹4.84 Cr | ₹1.04 Cr |
| 2024 Q1 | ₹13.39 Cr | ₹13.91 Cr | ₹52 L |
| 2024 Q2 | ₹25.23 Cr | ₹25.35 Cr | ₹40 L |
| 2024 Q3 | ₹7.85 Cr | ₹8.13 Cr | ₹13 L |
| 2024 Q4 | ₹17.26 Cr | ₹17.18 Cr | ₹20 L |
| 2025 Q1 | ₹4.52 Cr | ₹4.55 Cr | ₹17 L |
| 2025 Q2 | ₹4.58 Cr | ₹4.57 Cr | ₹18 L |
| 2025 Q3 | ₹6.79 Cr | ₹6.14 Cr | ₹83 L |
| 2025 Q4 | ₹6.90 Cr | ₹7.48 Cr | ₹25 L |
| 2026 Q1 | ₹5.13 Cr | ₹4.90 Cr | ₹48 L |
Builder Record
Mapsko has 2 other Gurgaon projects on the HRERA register; 0 are past the declared completion date with no OC yet, 1 delivered. Read it as a spot-check list for a pattern, not a delay rate.
- Mapsko Mount Ville — declared 2020-08-30 · OC on record
- Mapsko Mount Ville Phase-ii — declared 2029-01-31
Location & Connectivity
The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.
| Landmark | Straight-line |
|---|---|
| IMT Manesar | 3 km |
| Golf Course Road belt | 16 km |
| Cyber City / DLF Cyber Hub | 19 km |
| Udyog Vihar | 19 km |
| IGI Airport, Delhi | 25 km |
| Connaught Place, Delhi | 39 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.