HRERA · the public record
Signature Global Park-1
VILLAGE DHUNELA, SECTOR 36 · Signatureglobal Homes
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 20 Sep 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
registration expiry
29 Oct 2026
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
HRERA registration · read 20 Sep 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
HRERA ·
Escrow account
What has moved through the RERA escrow account?
Across 12 filed quarterly reports, Signature Global Park-1 records ₹116.85 Cr paid into and ₹113.48 Cr withdrawn from its RERA escrow account, with a latest recorded balance of ₹3.38 Cr.
₹116.85 Cr
into the escrow account
₹113.48 Cr
withdrawn
₹3.38 Cr
latest balance
Amounts as filed in the developer's own quarterly progress reports to HRERA, summed across the quarters on record.
Source · HRERA quarterly progress reports
Sales Traction, Quarter by Quarter
Units the developer reported booking in each quarterly HRERA filing — the closest public read on real demand.
| Quarter | Units booked | Total units |
|---|---|---|
| 2023 Q2 | 0 | 181 |
| 2023 Q3 | 2 | 181 |
| 2023 Q4 | 0 | 181 |
| 2024 Q1 | 0 | 181 |
| 2024 Q2 | 2 | 181 |
| 2024 Q3 | 0 | 181 |
| 2024 Q4 | 0 | 181 |
| 2025 Q1 | 1 | 181 |
| 2025 Q2 | 0 | 181 |
| 2025 Q3 | 0 | 181 |
| 2025 Q4 | 0 | 181 |
| 2026 Q1 | 0 | 181 |
Escrow Account Activity
Money moving through the RERA-mandated escrow account each quarter. Withdrawals from it are statutorily meant to fund construction milestones.
| Quarter | Deposited | Withdrawn | Balance |
|---|---|---|---|
| 2023 Q2 | ₹4.31 Cr | ₹4.31 Cr | ₹0 L |
| 2023 Q3 | ₹1.69 Cr | ₹1.69 Cr | ₹0 L |
| 2023 Q4 | ₹5.13 Cr | ₹5.13 Cr | ₹0 L |
| 2024 Q1 | ₹2.86 Cr | ₹0 L | ₹2.86 Cr |
| 2024 Q2 | ₹12.84 Cr | ₹13.63 Cr | ₹2.07 Cr |
| 2024 Q3 | ₹8.72 Cr | ₹8.73 Cr | ₹2.06 Cr |
| 2024 Q4 | ₹6.16 Cr | ₹6.12 Cr | ₹2.10 Cr |
| 2025 Q1 | ₹22.85 Cr | ₹21.23 Cr | ₹3.72 Cr |
| 2025 Q2 | ₹28.16 Cr | ₹16.73 Cr | ₹15.14 Cr |
| 2025 Q3 | ₹8.12 Cr | ₹17.53 Cr | ₹5.73 Cr |
| 2025 Q4 | ₹8.55 Cr | ₹10.00 Cr | ₹4.28 Cr |
| 2026 Q1 | ₹7.47 Cr | ₹8.37 Cr | ₹3.38 Cr |
Builder Record
Signature Global has 45 other Gurgaon projects on the HRERA register; 11 are past the declared completion date with no OC yet, 15 delivered. Read it as a spot-check list for a pattern, not a delay rate.
- City of Colours Nh-8 — declared 2028-12-31
- City of Colours Nh-8 Extn.-1 — declared 2028-12-31
- Daxin Gurugram's X Factor — declared 2028-12-31
- Daxin Vistas — declared 2028-01-15
Location & Connectivity
The nearest major job hub is ~15 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.
| Landmark | Straight-line |
|---|---|
| IMT Manesar | 15 km |
| Golf Course Road belt | 18 km |
| Cyber City / DLF Cyber Hub | 23 km |
| Udyog Vihar | 24 km |
| IGI Airport, Delhi | 30 km |
| Connaught Place, Delhi | 41 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.