Ss Linden Residential Floors
SS LINDEN, SECTOR-84 · Ss Group
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 20 Sep 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
registration expiry
28 Feb 2025
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
HRERA registration · read 20 Sep 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
HRERA ·
Escrow account
What has moved through the RERA escrow account?
Across 6 filed quarterly reports, Ss Linden Residential Floors records ₹26.02 Cr paid into and ₹12.39 Cr withdrawn from its RERA escrow account, with a latest recorded balance of ₹18.48 Cr.
₹26.02 Cr
into the escrow account
₹12.39 Cr
withdrawn
₹18.48 Cr
latest balance
Amounts as filed in the developer's own quarterly progress reports to HRERA, summed across the quarters on record.
Source · HRERA quarterly progress reports
Sales Traction, Quarter by Quarter
Units the developer reported booking in each quarterly HRERA filing — the closest public read on real demand.
| Quarter | Units booked | Total units |
|---|---|---|
| 2024 Q2 | 0 | 44 |
| 2024 Q3 | 0 | 88 |
| 2024 Q4 | 0 | 44 |
| 2025 Q1 | 1 | 44 |
| 2025 Q2 | 0 | 44 |
| 2025 Q3 | 0 | 44 |
Escrow Account Activity
Money moving through the RERA-mandated escrow account each quarter. Withdrawals from it are statutorily meant to fund construction milestones.
| Quarter | Deposited | Withdrawn | Balance |
|---|---|---|---|
| 2024 Q2 | ₹0 L | ₹4.85 Cr | ₹0 L |
| 2024 Q3 | ₹22.66 Cr | ₹0 L | ₹22.66 Cr |
| 2024 Q4 | ₹2.68 Cr | ₹7.54 Cr | ₹17.80 Cr |
| 2025 Q1 | ₹37 L | ₹0 L | ₹18.17 Cr |
| 2025 Q2 | ₹0 L | ₹0 L | ₹18.17 Cr |
| 2025 Q3 | ₹31 L | ₹0 L | ₹18.48 Cr |
Builder Record
SS Group has 11 other Gurgaon projects on the HRERA register; 4 are past the declared completion date with no OC yet, 4 delivered. Read it as a spot-check list for a pattern, not a delay rate.
- Commercial Colony — declared 2022-02-27 · OC on record
- Ss 100 — declared 2024-09-30
- Ss High Point — declared 2025-06-29
- Ss Linden — declared 2026-12-31
Location & Connectivity
The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.
| Landmark | Straight-line |
|---|---|
| IMT Manesar | 6 km |
| Golf Course Road belt | 15 km |
| Cyber City / DLF Cyber Hub | 16 km |
| Udyog Vihar | 16 km |
| IGI Airport, Delhi | 21 km |
| Connaught Place, Delhi | 35 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.