25 South Tower A 11th to 47th Floor

Prabhadevi · Twenty Five South Realty Limited

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2026declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900011418

Delivery and registration

When is the project declared for completion?

25 South Tower A 11th to 47th Floor is registered with MahaRERA as P51900011418 and the promoter has declared completion for 30 Dec 2026.

30 Dec 2026

declared completion

3months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900011418
Registered on31 Aug 2017
Promoter-declared completion30 Dec 2026
Current statusCertificate Signed
Against today3 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for 25 South Tower A 11th to 47th Floor record 36 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Twenty Five South is the promoter of record on 13 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

13projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for 25 South Tower A 11th to 47th Floor in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+40.

BuildingWingsFloorsDeclared completion
25 South 11th To 47th Floors1G+4031 Dec 2025

Legal and disputes

What disputes are disclosed?

4 complaints are on the MahaRERA record for 25 South Tower A 11th to 47th Floor, with orders passed in 3 of them.

4complaints

3with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000019833114/09/2021Connective Infrastructure Pvt Ltd vs Twenty Five South Realty Limited and Anrorder passed
CC00600000019833214/09/2021RRM Realty Trader Pvt Ltd vs Twenty Five South Realty Limited and Anrorder passed
CC00600000019833314/09/2021Totsol Commercial Pvt Ltd vs Twenty Five South Realty Limited and Anrorder passed
CC1260150718/03/2026Prashant Khandelwal vs Twenty Five South Realty Limitedpending / no order on file

Location, Land & Connectivity

Located at Prabhadevi, Patilwadi, Mumbai City, Mumbai City, 400025. Per the filed land record, the plot is bounded to the north by EWS Bldg, to the south by RG Sub Plot, to the east by Wing C and to the west by RG Sub Plot. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Lower Parel / Worli business district2 km
Bandra Kurla Complex (BKC)7 km
Chhatrapati Shivaji Int'l Airport9 km
Nariman Point / Fort10 km
Andheri MIDC / SEEPZ13 km
Powai / Hiranandani business park14 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Twenty Five South Realty Limited is the promoter on 4 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Twenty Five South Realty Limited project & its RERA track record →

Other flagged projects by Twenty Five South Realty Limited

Twenty Five South Realty Limited
Deregistered by MahaRERAMumbai City
Twenty Five South Realty Limited
FlaggedMumbai City
Twenty Five South Realty Limited
FlaggedMumbai City

Other RERA-registered projects in Prabhadevi

1515 Moneco
possession by Sep 2026 · Lloyds Realty Developers Limited
25 South Tower A Upto 10th Floor
possession by Dec 2026 · Twenty Five South Realty Limited
25 South - Central Tower
Deregistered by MahaRERA · possession by Dec 2028 · Twenty Five South Realty Limited
Kshitij Omkar
possession by Nov 2030 · Omkar CHS Ltd
Vakratunda Crest
possession by Dec 2030 · Inclineestate Properties LLP
Naia
possession by Dec 2030 · Prabhadevi Developer Private Limited

Major developers building in Prabhadevi

Other RERA-registered projects in Mumbai City

25 South Tower A Upto 10th Floor
possession by Dec 2026 · Twenty Five South Realty Limited
379 Vista
possession by Jan 2029 · Ajwaa Developers
41 Grandstand
possession by Jun 2029 · Ramesh Builders
42 East Park
declared completion Apr 2026 · Madhupuri Homes
47 Race Course
possession by Dec 2027 · Akshay Sthapatya Pvt. Ltd.
52 Avenue
declared completion Dec 2024 · Heks Realty

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.