MahaRERA Property Intelligence · Mumbai Suburban

4810 Heights

P51800008732 · Borivali East · promoter Urvi Realtors

Certificate SignedDue 31 Dec 2027

Delivery & Registration

MahaRERA registrationP51800008732
Registered on19 Aug 2017
Promoter-declared completion31 Dec 2027
Current statusCertificate Signed
Against today17 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Urvi Realtors is the promoter of record on 3 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Sales & Inventory

Of 164 homes filed with MahaRERA, 126 are sold/booked (117 with registered agreements + 9 booked) and 38 remain available (~77% sold) — selling steadily. Buyers have committed ₹43.06 Cr in agreement value so far. Of that, ₹37.20 Cr (~86%) is already collected, ₹5.86 Cr receivable — a read on how far along these sales really are. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 126 registered agreements, the effective carpet rate is ₹6,846/sqft (typical range ₹4,465–₹13,417) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 12A-1205483 sqft (44.88 sqm)₹63.72 Lakh
Floor 12B-1201358 sqft (33.23 sqm)₹47.18 Lakh
Floor 13A-1301375 sqft (34.8 sqm)₹49.41 Lakh
Floor 13A-1302412 sqft (38.26 sqm)₹54.32 Lakh
Floor 13B-1304351 sqft (32.57 sqm)₹46.24 Lakh
Floor 14A-1401413 sqft (38.41 sqm)₹54.53 Lakh
Floor 14A-1404594 sqft (55.15 sqm)₹78.30 Lakh
Floor 14A-1406487 sqft (45.27 sqm)₹64.27 Lakh
Floor 14B-1401384 sqft (35.68 sqm)₹50.66 Lakh
Floor 14B-1404401 sqft (37.23 sqm)₹52.86 Lakh
Floor 15A-1501413 sqft (38.41 sqm)₹54.53 Lakh
Floor 15A-1502413 sqft (38.41 sqm)₹54.53 Lakh
Floor 15A-1503594 sqft (55.15 sqm)₹78.30 Lakh
Floor 15A-1505487 sqft (45.27 sqm)₹64.27 Lakh
Floor 15A-1506487 sqft (45.27 sqm)₹64.27 Lakh
Floor 15B-1501384 sqft (35.68 sqm)₹50.66 Lakh
Floor 15B-1502381 sqft (35.39 sqm)₹50.25 Lakh
Floor 15B-1504401 sqft (37.23 sqm)₹52.86 Lakh
Floor 16A-1601413 sqft (38.41 sqm)₹54.53 Lakh
Floor 16A-1602413 sqft (38.41 sqm)₹54.53 Lakh
Floor 16A-1603594 sqft (55.15 sqm)₹78.30 Lakh
Floor 16A-1604594 sqft (55.15 sqm)₹78.30 Lakh
Floor 16B-1601384 sqft (35.68 sqm)₹50.66 Lakh
Floor 16B-1602381 sqft (35.39 sqm)₹50.25 Lakh
Floor 16B-1603381 sqft (35.39 sqm)₹50.25 Lakh
Floor 16B-1604401 sqft (37.23 sqm)₹52.86 Lakh
Floor 17A-1701413 sqft (38.41 sqm)₹54.53 Lakh
Floor 17A-1702413 sqft (38.41 sqm)₹54.53 Lakh
Floor 17A-1703594 sqft (55.15 sqm)₹78.30 Lakh
Floor 17A-1704594 sqft (55.15 sqm)₹78.30 Lakh
Floor 17A-1705487 sqft (45.27 sqm)₹64.27 Lakh
Floor 17A-1706487 sqft (45.27 sqm)₹64.27 Lakh
Floor 17B-1701384 sqft (35.68 sqm)₹50.66 Lakh
Floor 17B-1702381 sqft (35.39 sqm)₹50.25 Lakh
Floor 17B-1703381 sqft (35.39 sqm)₹50.25 Lakh
Floor 17B-1704401 sqft (37.23 sqm)₹52.86 Lakh
Floor 8B-804351 sqft (32.57 sqm)₹46.24 Lakh
Floor 9B-904351 sqft (32.57 sqm)₹46.24 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+18 and 164 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
4810 Heights1G+1816431 Dec 2022

Unit mix on the filing: 164 residential.

Complaints & Orders

7 complaints are on the MahaRERA record for this project, with orders passed in 7. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000005613529/12/2018Mrs Jayshree Arvind Dholakia vs Right Channel Constructions Private Ltdorder passed
CC00600000002345626/02/2018Devang Kakkad vs Right Channel Constructions Pvt Ltd, Urvi Realtors, Shri Sanjay Hanumanprasad Pandeyorder passed
CC00600000002351726/02/2018Bharati Kakkad vs Right Channel Construction Pvt Ltd, Urvi Realtors, Shri Sanjay Hanumanprasad Pandey,order passed
CC00600000019246022/02/2020Devang Kakkad vs Urvi Realtorsorder passed
CC00600000019271822/02/2020Bharti Kakkad vs Urvi Realtorsorder passed
CC00600000002385823/03/2018Nishant S. Shirke vs Right Channel Constructions Private Limitedorder passed
CC00600000016124313/10/2019Sharad Fakir Dayal vs M/s. Right Channel Constructions Pvt Ltdorder passed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 5 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 202430 Dec 2020Dear Sir, We hereby apply for the extension of project and renewal of the registration of the following project: 4810 Heights CTS No.2330 A/1/2 at, Borivali, Mumbai Suburban Di
31 Dec 202431 Dec 2022covid 19
31 Dec 202431 Dec 2023Dear Sir, Due to multiple factors like delay in receiving further CC from the concern authorities in the past before implication of RERA, the project got delayed. However, post RE
31 Dec 202431 Dec 2024This is a project initiated by a joint venture company before enforcementnt of Rera. Due to certain finafinancially inappropriate circumstances, the project got delayed. Currently,
31 Dec 201931 Dec 2027The delay in completion of the project is due to delays in obtaining necessary approvals and clearances from MCGM, unforeseen technical challenges during execution, and shortage of

Location, Land & Connectivity

Located at Borivali East, ASHOKVAN, Borivali, Mumbai Suburban, 400066. Per the filed land record, the plot is bounded to the north by 20 Feet Existing Road, to the south by 44 Feet DP Road, to the east by 44 Feet DP Road and to the west by Slum Property. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~12 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Andheri MIDC / SEEPZ12 km
Powai / Hiranandani business park14 km
Chhatrapati Shivaji Int'l Airport17 km
Bandra Kurla Complex (BKC)19 km
Lower Parel / Worli business district27 km
Nariman Point / Fort35 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Borivali East

Rushabh Apartment
possession by Jul 2026 · R R Builders
Rashmi Manorath
possession by Aug 2026 · Modi's Navnirman Limited
Proposed Redevelopment OF Prakashkunj Chsl
possession by Sep 2026 · Yash Realtors & Developers
Chandratej CHS LTD
possession by Oct 2026 · Elesh Ravjibhai Rathod
Eknath Gruh
possession by Oct 2026 · Vastav Developers PVT LTD
NEW Avanti Chsl
possession by Oct 2026 · Balaji Enterprises

Major developers building in Borivali East

Other RERA-registered projects in Mumbai Suburban

49 Elina
declared completion Dec 2021 · Huges Real Estates Developers LLP
49, Simandhar Royale
possession by Dec 2026 · Simandhar Homes LLP
4th Avenue Sunteck City, Odc, Goregaon West
possession by Dec 2028 · Satguru Corporate Services Pvt. Ltd.
5 Aguada By Skyi
possession by Jun 2029 · Skyi Replete Ventures LLP
52 Park Avenue
declared completion Aug 2024 · DAN Kutir Chsl
54 Park Lane
possession by Dec 2028 · L Nagpal Buildcon LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026