AADITYA LUXURIA

Charni road · M/S. A.K. DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

17units filed as unsoldInventory · 13 September 2026
30 Dec 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900003845

Delivery and registration

When is the project declared for completion?

AADITYA LUXURIA is registered with MahaRERA as P51900003845 and the promoter has declared completion for 30 Dec 2025.

30 Dec 2025

declared completion

9months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900003845
Registered on06 Aug 2017
Promoter-declared completion30 Dec 2025
Current statusCertificate Signed
Against todayabout 9 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for AADITYA LUXURIA record 34 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 34 quarterly progress reports on record since registration, with no current default.

What the filings record, home by home

Read from MahaRERA on 13 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 31 homes carry one, and 17 of the 48 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
804856 sqftRs 24,210 a sq ft typical, over Rs 22,760 to Rs 31,2168 filed at this size

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet.

In AADITYA LUXURIA, 16 of the 17 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 16 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+26.

BuildingWingsFloorsDeclared completion
AADITYA LUXURIA1G+26-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2025Due to amendments in development control regulations, the project had to undergo a transition from DCPR 1991 to DCPR 2034. This migration necessitated several planning changes, whi

Location, Land & Connectivity

Located at Charni road, VP ROAD, Ward ABCD, Mumbai City, 400004. Per the filed land record, the plot is bounded to the north by LIC, to the south by MCGM, to the east by BHALERAO AND ORS and to the west by LIC. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Nariman Point / Fort4 km
Lower Parel / Worli business district5 km
Bandra Kurla Complex (BKC)13 km
Chhatrapati Shivaji Int'l Airport15 km
Andheri MIDC / SEEPZ20 km
Powai / Hiranandani business park20 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

M/s. A.k. Developers is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by M/s. A.k. Developers

M/s. A.k. Developers
FlaggedMumbai City

Other RERA-registered projects in Girgaum

Aaditya Residences
possession by Dec 2026 · M/s. A.k. Developers
Shreepati Bayview
Deregistered by MahaRERA · possession by Dec 2026 · Shreepati Build Infra Investment Limited
NEO Amity
possession by Dec 2026 · Naresh Kesarimal Mehta
Onyx
possession by Dec 2026 · Naminath Erector And Developers LLP
Promesa Castor
possession by Dec 2026 · Darshan Group
Raajdeep Arcade
possession by Dec 2026 · Raajdeep Builders AND Developers

Other RERA-registered projects in Mumbai City

Aaditya Residences
possession by Dec 2026 · M/s. A.k. Developers
Aakasa
possession by Dec 2027 · Techno Freshworld LLP
Aakasa Shivaji Park
possession by Mar 2029 · GFT Realtors LLP
Aakash Tower
declared completion Jun 2024 · Aakash Associates Infrastructure
Aaradhya Avaan
possession by Dec 2030 · Shreepati Skies
Aarush
declared completion Sep 2025 · Konark Enterprises

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026