Mumbai/Project record

MahaRERA · the public record

Adhiraj Samyama Tower 2B

Taloja · Adhiraj Constructions Private Limited

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

10 Nov 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

10 Nov 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000003039

Delivery and registration

When is the project declared for completion?

Adhiraj Samyama Tower 2B is registered with MahaRERA as P52000003039 and the promoter has declared completion for 10 Nov 2023.

10 Nov 2023

declared completion

34months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000003039
Registered on04 Aug 2017
Promoter-declared completion10 Nov 2023
Current statusCertificate Signed
Against todayabout 34 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Adhiraj Samyama Tower 2B record 26 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 26 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Adhiraj Constructions is the promoter of record on 18 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

18projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Adhiraj Samyama Tower 2B in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+55.

BuildingWingsFloorsDeclared completion
2B1G+5531 Dec 2020

Legal and disputes

What disputes are disclosed?

10 complaints are on the MahaRERA record for Adhiraj Samyama Tower 2B, with orders passed in 10 of them.

10complaints

10with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000000199618/11/2017NIRMALA PETETI vs ADHIRAJ CONSTRUCTIONS PVT. LTD.order passed
CC00600000001216727/11/2017VENKATA SIRISHBABU PETETI vs Adhiraj Constructions Private Limitedorder passed
CC00600000019666507/04/2021Adhiraj Samyama 2A and 2B Buyers Members Association Proposed vs Adhiraj Constructions Pvt Ltdorder passed
CC00600000030322210/11/2022Ashok Tukaram Gade vs Adhiraj Construction Private Limitedorder passed
CC00600000037495228/03/2023MRS FARIDA BEGUM LAYEK vs M/S ADHIRAJ CONSTRUCTIONS PVT LTDorder passed
CC00600000040808710/11/2023MR PRASAD MADHUKAR CHURY vs M/S ADHIRAJ CONSTRUCTIONS PVT LTDorder passed
CC00600000042921514/05/2024Ravindra Mallappa Antin vs Adhiraj Construction Private Limited (ACPL)order passed
CC1240042316/10/2024ASHOK KUMAR PARASRAMKA vs Adhiraj Constructions Private Limitedorder passed
CC1250013414/01/2025Abhishek Saraf vs Adhiraj Constructions Private Limitedorder passed
CC1250026425/01/2025Sharda Prasad Ram Narendra Singh vs Adhiraj Constructions Private Limitedorder passed

Legal & Litigation

The promoter has declared 4 court cases on this project to MahaRERA. 3 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Senior Division Panvel6532007Pending
Senior Division Panvel752014Pending
Senior Division Panvel4592021Suit Is Disposed Of
Senior Division Panvel52022Pending

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2022Extension application attached
30 Jun 202230 Jun 2023Extension application attached
30 Jun 202310 Nov 2023We had duly applied for Occupation Certificate in the month of December 2022, however it is issued by the competent authority on 10th November 2023.

Location, Land & Connectivity

Located at Taloja, Mumbai City, Mumbai City, 410208. Per the filed land record, the plot is bounded to the north by Survey no 91-3, to the south by Survey no 85, to the east by Survey no 88 and to the west by Survey no 92. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~19 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park19 km
Bandra Kurla Complex (BKC)22 km
Chhatrapati Shivaji Int'l Airport22 km
Andheri MIDC / SEEPZ23 km
Lower Parel / Worli business district28 km
Nariman Point / Fort32 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Adhiraj Constructions Private Limited is the promoter on 11 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Adhiraj Constructions Private Limited project & its RERA track record →

Other flagged projects by Adhiraj Constructions Private Limited

Adhiraj Constructions Private Limited
FlaggedRaigarh
Adhiraj Constructions Private Limited
FlaggedRaigarh
Adhiraj Constructions Private Limited
FlaggedRaigarh
Adhiraj Constructions Private Limited
FlaggedRaigarh
Adhiraj Constructions Private Limited
FlaggedRaigarh
Adhiraj Constructions Private Limited
FlaggedRaigarh

Other RERA-registered projects in Taloja

Ayan Skyway
possession by Sep 2026 · Ibrahim Nazirsha Mukadam
K K Residency
Not filing quarterly progress reports · possession by Sep 2026 · Shree SAI Home Makers
Majestic Planet
possession by Sep 2026 · 365days Construction LLP
Royal Yusra Heights
possession by Sep 2026 · AL-Yusra Developers LLP
Om Unnati
possession by Nov 2026 · Om Group
Arihant Amisha Phase II
possession by Dec 2026 · Arihant Aashiyana Private Limited

Other RERA-registered projects in Raigarh

Adhiraj Samyama Tower 3B
declared completion Jun 2025 · Adhiraj Constructions Private Limited
Adhya Bhimashankar
declared completion Sep 2024 · Adhya Properties
Adiba Complex
declared completion Dec 2022 · Iram Construction AND Developers
Adinath Akruti
declared completion Mar 2024 · Shree Riddhi Siddhi Constructions
Adinath Archana
declared completion Dec 2024 · Shree Riddhi Siddhi Constructions
Adinath Crystal
possession by Dec 2028 · Shree Riddhi Siddhi Constructions

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026