Mumbai/Project record

MahaRERA · the public record

ADICIO

Mumbai Suburban · SHREE AHUJA PROJECT PRIVATE LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

23 Nov 2021declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

23 Nov 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800007289

Delivery and registration

When is the project declared for completion?

ADICIO is registered with MahaRERA as P51800007289 and the promoter has declared completion for 23 Nov 2021.

23 Nov 2021

declared completion

58months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800007289
Registered on17 Aug 2017
Promoter-declared completion23 Nov 2021
Current statusCertificate Signed
Against todayabout 58 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for ADICIO record 18 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 18 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for ADICIO in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
ADICIO1G+523 May 2021

Legal and disputes

What disputes are disclosed?

12 complaints are on the MahaRERA record for ADICIO, with orders passed in 12 of them.

12complaints

12with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000019403221/09/2020Mrs. Hena Deepal Gulabani vs Shree Ahuja Properties Pvt. Ltd. (Also known as Shree Ahuja Project Pvt. Ltd.)order passed
CC00600000005574017/08/2018Shewa Apartments CHS Ltd (society) vs Shree Ahuja Properties Pvt Ltdorder passed
CC00600000039702804/09/2023Avtar Kishan Kaul vs Shree Ahuja properties pvt ltdorder passed
CC00600000039703004/09/2023Sumeet Murli Gulabani vs Shree Ahuja Propoerties Pvt Ltdorder passed
CC00600000039703104/09/2023Kamya Sumeet Gulabani vs Shree Ahuja Properties Pvt.Ltdorder passed
CC00600000039703228/09/2023M/s PKM Holdings vs Shree Ahuja Properties Pvt.Ltdorder passed
CC00600000039703306/09/2023Gaurav Kapoor vs Shree Ahuja Properties Pvt. Ltdorder passed
CC00600000039703405/09/2023Kamya Sumeet gulabani vs Shree Ahuja Propritiesorder passed
CC00600000039703605/09/2023Anil Ganesh Kulkarni vs Shree Ahuja Propertiesorder passed
CC00600000048027204/05/2024ADICIO ASSOCIATION OF PERSON vs Shree Ahuja Propertiesorder passed
CC00600000054074311/06/2024SUNIL KISHINCHAND BHOJWANI vs Shree Ahuja Project Private Limitedorder passed
CC00600000054074611/06/2024SUNIL KISHINCHAND BHOJWANI vs Shree Ahuja Properties Pvte Ltdorder passed

A co-operative housing society is recorded as the complainant (Shewa Apartments CHS Ltd), and MahaRERA has passed an order.

Legal & Litigation

The promoter has declared 2 court cases on this project to MahaRERA. 2 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
The Honble Supreme Court Of IndiaSuit No 232015Pending
The Honble Supreme Court Of India232015Pending

Location, Land & Connectivity

Located at Andheri, Mumbai Suburban, 400052. Per the filed land record, the plot is bounded to the north by CTS No 859 D, to the south by CTS NO 859 1B, to the east by Railway Line and to the west by CTS NO 859 C. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bandra Kurla Complex (BKC)4 km
Chhatrapati Shivaji Int'l Airport4 km
Andheri MIDC / SEEPZ7 km
Lower Parel / Worli business district8 km
Powai / Hiranandani business park9 km
Nariman Point / Fort16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Khar West

Trishaan
possession by Sep 2026 · Raja Builder
Yogi Sea
possession by Sep 2026 · Yogi Limited
Searock Residences
possession by Oct 2026 · Searock Constructions LLP
259 Park Crest
possession by Dec 2026 · Shree Krishna Homes PVT LTD
33 West
possession by Dec 2026 · Silver Lifespaces Private Limited
Benchmark Plaza
possession by Dec 2026 · Benchmark Projects PVT LTD

Major developers building in Khar West

Other RERA-registered projects in Mumbai Suburban

Adinath CHS
declared completion Jul 2023 · Aditya Developers
Adinath Heights
declared completion Mar 2026 · Shri Neelkanth Developers
Aditi CO Operative Housing Society LTD
possession by Mar 2029 · R N Associates
Aditya
declared completion Dec 2021 · Navkar Builder AND Developers
Aditya Chsl
possession by Dec 2026 · Shree Mahavir Developers
Aditya Goraswadi Chsl
possession by Dec 2027 · K. Talsania Constructions

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026