MahaRERA Property Intelligence · Mumbai Suburban

Aditya Aryan / Ejaj

P51800011231 · promoter Dinesh Agarwal

Certificate SignedDue 31 Mar 2019

Delivery & Registration

MahaRERA registrationP51800011231
Registered on31 Aug 2017
Promoter-declared completion31 Mar 2019
Current statusCertificate Signed
Against todayabout 88 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Dinesh Agarwal is the promoter of record on 57 projects, of which 5 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+17.

BuildingWingsFloorsDeclared completion
Aditya Aryan / Ejaj1G+17-

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000002390827/03/2018Arunkumar Nair Abhijit Kate vs Dinesh C Agarwalorder passed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Mar 201931 Mar 2019Extension due to BMC Compliacne for OC

Location, Land & Connectivity

Located at Borivali, Mumbai Suburban, 400066. Per the filed land record, the plot is bounded to the north by Shiv Kankan CHS, to the south by D P Road, to the east by Pumping Station and to the west by Chougale nagar. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~12 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Andheri MIDC / SEEPZ12 km
Powai / Hiranandani business park14 km
Chhatrapati Shivaji Int'l Airport17 km
Bandra Kurla Complex (BKC)19 km
Lower Parel / Worli business district27 km
Nariman Point / Fort35 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Borivali East

Rushabh Apartment
possession by Jul 2026 · R R Builders
Rashmi Manorath
possession by Aug 2026 · Modi's Navnirman Limited
Proposed Redevelopment OF Prakashkunj Chsl
possession by Sep 2026 · Yash Realtors & Developers
Chandratej CHS LTD
possession by Oct 2026 · Elesh Ravjibhai Rathod
Eknath Gruh
possession by Oct 2026 · Vastav Developers PVT LTD
NEW Avanti Chsl
possession by Oct 2026 · Balaji Enterprises

Major developers building in Borivali East

Other RERA-registered projects in Mumbai Suburban

Aditya Breeze
possession by Dec 2028 · Aditya Arayn Developers LLP
Aditya Chandrashali
declared completion Dec 2024 · Aditya Arayn Developers LLP
Aditya Chsl
possession by Dec 2026 · Shree Mahavir Developers
Aditya Enterprises
declared completion Jun 2021 · Aditya Enterprise
Aditya Goraswadi Chsl
possession by Dec 2027 · K. Talsania Constructions
Adityaman Chs. LTD
possession by Oct 2029 · Noble Construction

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026