MahaRERA Property Intelligence · Mumbai Suburban

Rustomjee Pinnacle

P51800006915 · Rajendra Nagar · promoter Keystone Realtors Limited

Certificate SignedDue 31 Dec 2018

Delivery & Registration

MahaRERA registrationP51800006915
Registered on16 Aug 2017
Promoter-declared completion31 Dec 2018
Current statusCertificate Signed
Against todayabout 91 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Keystone Realtors Limited is the promoter of record on 55 projects, of which 4 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+27.

BuildingWingsFloorsDeclared completion
Pinnacle1G+2731 Dec 2018

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Legal & Litigation

The promoter has declared 5 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
High Court Mumbai2572015Matter Kept For Further Hearing In Due Course
City Civil Court Dindoshi10092015Notice Of Motion Was Argued By All Parties However It Needs To Be Reargued Due To Transfer Of Honble
City Civil Court Dindoshi16762016At The Stage Of Reply To Notice Of Motion By Other Defendants
City Civil Court Mumbai96871999Notice Of Motion For Final Hearing
Small Causes Court Bandra1192014Decree Holder Has Taken Out The Present Applicaiton For Execution Of Decree And Has Filed Applicatio

Location, Land & Connectivity

Located at Rajendra Nagar, Dattapada Road, Andheri, Mumbai Suburban, 400066. Per the filed land record, the plot is bounded to the north by 36 MW DP Road, to the south by CTS No 67, to the east by CTS No 87 and to the west by CTS No 89. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~10 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Andheri MIDC / SEEPZ10 km
Powai / Hiranandani business park12 km
Chhatrapati Shivaji Int'l Airport15 km
Bandra Kurla Complex (BKC)17 km
Lower Parel / Worli business district25 km
Nariman Point / Fort33 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Keystone Realtors Limited is the promoter on 19 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Keystone Realtors Limited project & its RERA track record →

Other flagged projects by Keystone Realtors Limited

Keystone Realtors Limited
FlaggedMumbai Suburban
Keystone Realtors Limited
FlaggedMumbai Suburban
Keystone Realtors Limited
FlaggedMumbai Suburban
Keystone Realtors Limited
FlaggedMumbai Suburban
Keystone Realtors Limited
FlaggedMumbai Suburban
Keystone Realtors Limited
FlaggedThane

Other RERA-registered projects in Borivali East

Rushabh Apartment
possession by Jul 2026 · R R Builders
Rashmi Manorath
possession by Aug 2026 · Modi's Navnirman Limited
Proposed Redevelopment OF Prakashkunj Chsl
possession by Sep 2026 · Yash Realtors & Developers
Chandratej CHS LTD
possession by Oct 2026 · Elesh Ravjibhai Rathod
Eknath Gruh
possession by Oct 2026 · Vastav Developers PVT LTD
NEW Avanti Chsl
possession by Oct 2026 · Balaji Enterprises

Major developers building in Borivali East

Other RERA-registered projects in Mumbai Suburban

Rustomjee Prive
possession by Nov 2029 · Keysky Realtors Private Limited
Rustomjee Reserve
declared completion Dec 2025 · Partum Realtors Private Limited
Rustomjee Seasons - Wing A
declared completion Dec 2022 · Keystone Realtors Limited
Rustomjee Seasons - Wing B
declared completion Dec 2021 · Keystone Realtors Limited
Rustomjee Seasons - Wing C
declared completion Dec 2021 · Keystone Realtors Limited
Rustomjee Seasons - Wing D
declared completion Dec 2025 · Keystone Realtors Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026