MahaRERA Property Intelligence · Thane

AMAIRA

P51700022122 · Village Ayre · promoter Pacific Excellence

Certificate SignedDue 31 Jul 2023

Delivery & Registration

MahaRERA registrationP51700022122
Registered on27 Aug 2019
Promoter-declared completion31 Jul 2023
Current statusCertificate Signed
Against todayabout 36 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Pacific Excellence is the promoter of record on 5 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12.

BuildingWingsFloorsDeclared completion
AMAIRA1G+1231 Jul 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Village Ayre, Dr R P Road, Kalyan, Thane, 421201. Per the filed land record, the plot is bounded to the north by Tata Power Line, to the south by Dr R P Road, to the east by CTS No 11980 and to the west by CTS No 12000. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~22 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park22 km
Andheri MIDC / SEEPZ25 km
Chhatrapati Shivaji Int'l Airport27 km
Bandra Kurla Complex (BKC)28 km
Lower Parel / Worli business district36 km
Nariman Point / Fort42 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Pacific Excellence is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Pacific Excellence

Other RERA-registered projects in Dombivli East

Premsadan CHS
possession by Jul 2026 · Namrata Realtors
OM Trimurti Darshan
possession by Aug 2026 · Prachi Group
Pannash
possession by Aug 2026 · Technicon
Rashmi Priya CO-OP HSG SOC LTD
possession by Aug 2026 · Shree Riddhi Siddhi Infraproject
Mahalaxmi Ashish D Wing
possession by Sep 2026 · Swastik Enterprises
NAV Pratima CO. OP. Hsg. Soc. LTD
possession by Sep 2026 · Narendra Kalyanji Patel

Major developers building in Dombivli East

Other RERA-registered projects in Thane

Amaira 2
possession by Apr 2027 · Pacific Excellence
Amakin Mohammadiya Complex Phase III
declared completion Dec 2024 · RAJ Corporation
Amakin Mohammadiyah Complex
possession by Dec 2030 · RAJ Corporation
Amakin Mohammediyah Phase 3
declared completion Dec 2024 · Amakin Mohammediyah Private Limited
Amaltas
possession by Dec 2027 · Aarya Developers
Amanda Shopping
declared completion Dec 2019 · Hiranandani Properties Private Limited

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026