31 Dec 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700000704

Delivery and registration

When is the project declared for completion?

Amanda Shopping is registered with MahaRERA as P51700000704 and the promoter has declared completion for 31 Dec 2019.

31 Dec 2019

declared completion

81months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700000704
Registered on20 Jul 2017
Promoter-declared completion31 Dec 2019
Current statusCertificate Signed
Against todayabout 81 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Amanda Shopping record 10 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 10 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Hiranandani Properties is the promoter of record on 3 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

3projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Amanda Shopping in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+1.

BuildingWingsFloorsDeclared completion
Amanda Shopping1G+131 Dec 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 2 court cases on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
High Court Of Bombay92302007Pending
High Court Of Bombay372017Disposed Off

Location, Land & Connectivity

Located at Hiranandani Meadows, Pokhran Road no II, Mumbai City, Mumbai City, 400610. Per the filed land record, the plot is bounded to the north by Gut No 45, to the south by Gut No 52 by 14, to the east by 20 m wide DP Road and to the west by Gut No 43 by 1 and 2. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~14 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park14 km
Andheri MIDC / SEEPZ15 km
Chhatrapati Shivaji Int'l Airport19 km
Bandra Kurla Complex (BKC)21 km
Lower Parel / Worli business district30 km
Nariman Point / Fort37 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Hiranandani Properties Private Limited is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Hiranandani Properties Private Limited

Hiranandani Properties Private Limited
FlaggedThane

Other RERA-registered projects in Majiwade

Infinity Towers
possession by Dec 2026 · T Bhimjyani Realty Pvt.ltd.
Raunak Imperial
possession by Dec 2026 · Raunak Avenue Realty
ZEN
possession by Dec 2026 · Neelkanth Realtors PVT LTD
Serein Phase II
possession by May 2027 · Ardent Properties Private Limited
Mahavir Spring -Daffodils-P3
possession by Dec 2027 · Vinayak Developers
Courtyard - Asteria A
possession by Dec 2027 · Courtyard Real Estate Private Limited

Major developers building in Majiwade

Other RERA-registered projects in Thane

Amar Elegance
possession by Sep 2026 · Amar Realty
Amar Galaxy Bldg No. 2 Wing B And C
possession by Dec 2029 · Amar Realty
Amar Galaxy Phase - I
declared completion Nov 2024 · Amar Realty
Amar Majestic
possession by Dec 2029 · Amarmaya & Associates
Amar Pushpakunj
declared completion Jul 2026 · Avighna Redevelopers
Amar Vaishali CO-Operative Housing Society LTD
declared completion May 2023 · Joshi Enterprises

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.