Iris Shopping

P51700019505 · Hiranandani Meadows · promoter Hiranandani Properties Private

Certificate SignedDue 18 Oct 2024

Delivery & Registration

MahaRERA registrationP51700019505
Registered on06 Feb 2019
Promoter-declared completion18 Oct 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Hiranandani Properties Private is the promoter of record on 3 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+11.

BuildingWingsFloorsDeclared completion
Iris Shopping1G+11-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Legal & Litigation

The promoter has declared 4 court cases on this project to MahaRERA. 3 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
High Court Of Mumbai372017Disposed Off
High Court Of Mumbai92302007Pending
Supreme Court Of India226932019Pending
High Court Of Judicature At Bombay929562020Pending

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Mar 202329 Mar 2024We have completed the construction of “Iris Shopping” having RERA registration number P51700019505 (project). We have obtained all the major building related necessary Licenses and
30 Mar 202318 Oct 2024We have completed the construction of ‘Iris Shopping’(Project). All the major building related necessary licences & NOCs such as lift licence, CFO NOC, Tree NOC etc. had been obtai

Location, Land & Connectivity

Located at Hiranandani Meadows, Pokhran Road No II, Mumbai City, Mumbai City, 400610. Per the filed land record, the plot is bounded to the north by Gut No 52 by 11, to the south by Gut No 52 by 13, to the east by 20 m wide DP road and to the west by Gut No 52 by 8. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~14 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park14 km
Andheri MIDC / SEEPZ15 km
Chhatrapati Shivaji Int'l Airport19 km
Bandra Kurla Complex (BKC)21 km
Lower Parel / Worli business district30 km
Nariman Point / Fort37 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Hiranandani Properties Private Limited is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Hiranandani Properties Private Limited

Hiranandani Properties Private Limited
FlaggedThane
Hiranandani Properties Private Limited
FlaggedThane

Other RERA-registered projects in Majiwade

Infinity Towers
possession by Dec 2026 · T Bhimjyani Realty Pvt.ltd.
Raunak Imperial
possession by Dec 2026 · Raunak Avenue Realty
ZEN
possession by Dec 2026 · Neelkanth Realtors PVT LTD
Serein Phase II
possession by May 2027 · Ardent Properties Private Limited
Mahavir Spring -Daffodils-P3
possession by Dec 2027 · Vinayak Developers
Courtyard - Asteria A
possession by Dec 2027 · Courtyard Real Estate Private Limited

Major developers building in Majiwade

Other RERA-registered projects in Thane

Ishanvi Ashapura Tower
possession by Sep 2026 · Ishanvi Ashapura Developers
Ishna Height
declared completion Jun 2023 · S.k. Homes Builder & Developers
Ishwar Bliss
declared completion May 2025 · Ishwar Reality
Ishwar Blossom
declared completion Jun 2026 · Ishwar Lifespace
Ishwar Enclave
declared completion Jun 2018 · Ishwar Enterprises
Ishwar Gajanan
possession by Dec 2027 · Ishwar Reality

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.