MahaRERA Property Intelligence · Thane

AMBESH TOWER-1 AND 2

P51700012047 · BHAYANDER EAST · promoter Shalibhadra Reality

Certificate SignedDue 31 Jul 2024

Delivery & Registration

MahaRERA registrationP51700012047
Registered on01 Sep 2017
Promoter-declared completion31 Jul 2024
Current statusCertificate Signed
Against todayabout 24 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+26.

BuildingWingsFloorsDeclared completion
AMBESH TOWER -11G+1731 Jul 2024
AMBESH TOWER-21G+2631 Dec 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at BHAYANDER EAST, VILLAGE GODDEO, Thane, Thane, 401105. Per the filed land record, the plot is bounded to the north by S NO 215 H 3, to the south by S NO 325 H 2, to the east by S NO 215 H-1 and to the west by S NO 77 H 1. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~19 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ19 km
Powai / Hiranandani business park21 km
Chhatrapati Shivaji Int'l Airport23 km
Bandra Kurla Complex (BKC)26 km
Lower Parel / Worli business district34 km
Nariman Point / Fort42 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bhayander East

Gayatri Elegance
possession by Dec 2026 · Gayatrikripa Developers Private Limited
Basera Heights
possession by Dec 2026 · Kamruddin Hasmullah Siddique
Durga Enclave
possession by Dec 2026 · Anmol Developers
Ranuja Ramdev C Type
possession by Dec 2026 · Ranuja Ramdev C Type
Surya Heritage A
possession by Dec 2026 · Arun Construction CO
The Pentagon
possession by Dec 2026 · Anjani Kumar Realty Private Limited

Other RERA-registered projects in Thane

Ambika Estate Phase 1
possession by Dec 2028 · Ambika Brickwell LLP
Ambika Heights
declared completion Jun 2024 · Rajesh Mavji Chheda
Ambika Niwas
declared completion Nov 2018 · Sunil Suresh Honrao
Ambika Palace Phase 1
declared completion Dec 2019 · Dayal Enterprises
Ambika Palace Wing A
declared completion Oct 2021 · Dinesh Narayan Tiwari
Ambika Prassana CHS
declared completion Dec 2024 · Built IN Reality

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026