Mumbai/Project record

MahaRERA · the public record

ANAND TOWER

Mumbai Suburban · ARIHANT ASSOCIATES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Oct 2020declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Oct 2020

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800005015

Delivery and registration

When is the project declared for completion?

ANAND TOWER is registered with MahaRERA as P51800005015 and the promoter has declared completion for 30 Oct 2020.

30 Oct 2020

declared completion

71months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800005015
Registered on09 Aug 2017
Promoter-declared completion30 Oct 2020
Current statusCertificate Signed
Against todayabout 71 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for ANAND TOWER record 14 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 14 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Arihant Associates is the promoter of record on 142 projects registered with MahaRERA, 14 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

142projects

registered with MahaRERA

14flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for ANAND TOWER in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+18.

BuildingWingsFloorsDeclared completion
ANAND TOWER1G+1831 Dec 2018

Legal and disputes

What disputes are disclosed?

14 complaints are on the MahaRERA record for ANAND TOWER, with orders passed in 14 of them.

14complaints

14with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000039558308/05/2023Ragini Chokshi vs Arihant Associatesorder passed
CC00600000005557606/08/2018Mrs. Anita Rajeev Verma vs M/S. Arihant Associatesorder passed
CC00600000005557706/08/2018Mr. Rajeev Radheshyam Verma vs M/S. Arihant Associatesorder passed
CC00600000005557806/08/2018Mrs. Anita Rajeev Verma vs M/s. Arihant Associatesorder passed
CC00600000005557906/08/2018Mr. Rajeev Radheshyam Verma vs M/s Arihant Associatesorder passed
CC00600000005562306/08/2018Mrs. Anita Rajeev Verma vs M/s Arihant Associatesorder passed
CC00600000005562506/08/2018Mr. Rajeev Radheshyam Verma vs M/s Arihant Associatesorder passed
CC00600000017149412/11/2019Alpa Sameer Chitroda vs M/s. Arihant Associatesorder passed
CC00600000017151813/11/2019MRS. SONALI TEJAS KOTHARI vs M/s. Arihant Associatesorder passed
CC00600000017152013/11/2019MR. RITESH DESAI vs M/s. Arihant Associatesorder passed
CC00600000017152112/11/2019MRS. KAMINI SANJAY KOTHARI vs M/s. Arihant Associatesorder passed
CC00600000018195624/12/2019Mrs. Upma Agrawal vs M/s. Arihant Associatesorder passed
CC00600000019213411/01/2020Radha Anand Patil vs M/s. Arihant Associatesorder passed
CC00600000029230010/08/2022Rajeev Radheyshyam Verma vs M/s Arihant Associate and Orsorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Apr 2020a) Shortage of Labours/Contractors. b) Shortage of supply of sand & cement. c) Delay in issuance of Permissions by the authority

Location, Land & Connectivity

Located at Borivali, Mumbai Suburban, 400089. Per the filed land record, the plot is bounded to the north by 40 FEET WIDE ROAD, to the south by 44 WIDE ROAD, to the east by OPEN SPACE AND BLDG NO 37 and to the west by OPEN SPACE AND JUNCTION OF 40 AND 44 FEET WIDE ROA. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bandra Kurla Complex (BKC)3 km
Chhatrapati Shivaji Int'l Airport4 km
Powai / Hiranandani business park6 km
Andheri MIDC / SEEPZ8 km
Lower Parel / Worli business district10 km
Nariman Point / Fort17 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Arihant Associates is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other RERA-registered projects in Chembur

Orient Regency Building No. 1
possession by Dec 2026 · Orient Combine
Sree Sudarshan Heights
possession by Dec 2026 · AUM SAI Constructions Private Limited
Srushtiraj Tower
possession by Dec 2026 · Chinnaiah Venkatesh Gowda
Promesa Midtown
possession by Dec 2026 · Darshan Properties
Vishwasangam
possession by Dec 2026 · Vishwashakti Cooperative Housing Society
Ampple-ONE
possession by Mar 2027 · Amppletech Projects Private Limited

Other RERA-registered projects in Mumbai Suburban

Anand Villa
possession by Dec 2027 · Ivaan Buildcon LLP
Ananda CHS Wing B
possession by Mar 2027 · Ananda Living Spaces LLP
Anandam
declared completion Aug 2026 · M/s Analiza Realty Pvt. Ltd.
Anandi
declared completion Dec 2021 · Sadhna Global Construction
Anant Nakshatra Tower 1
possession by Dec 2026 · M Construction Company
Anant Nakshatra Tower 2
possession by Dec 2026 · M Construction Company

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026