Mumbai/Project record

MahaRERA · the public record

ANANTARA

NALASOPARA EAST · MANGALMURTI REALTY DEVELOPERS LLP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

268units filed as unsoldInventory · 16 September 2026
31 Mar 2030declared completionMahaRERA registration · read 02 Jul 2026
102registered unitsMahaRERA registration · read 02 Jul 2026

The record · free to read

Registration read 02 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Mar 2030

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 02 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · PR1240002503062

Delivery and registration

When is the project declared for completion?

ANANTARA is registered with MahaRERA as PR1240002503062 and the promoter has declared completion for 31 Mar 2030.

31 Mar 2030

declared completion

42months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 02 Jul 2026

MahaRERA registrationPR1240002503062
Registered on27 Mar 2026
Promoter-declared completion31 Mar 2030
Current statusCertificate Signed
Against today42 months to the declared date

Promoter record

What else is this promoter on record for?

Mangalmurti Realty Developers is the promoter of record on 53 projects registered with MahaRERA, 10 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

53projects

registered with MahaRERA

10flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 02 Jul 2026

Construction

How much construction cost has been reported?

In ANANTARA, ₹0 of a declared ₹60.53 Cr estimated project cost is reported as incurred, about 0.0%, as at the last certified filing with MahaRERA.

0.0%

₹0

of ₹60.53 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 02 Jul 2026

Sales

How much has actually been sold?

In ANANTARA, 0 of 268 homes filed with MahaRERA are recorded as sold or booked, about 0%, and 268 remain available.

0%sold

0 of 268 homes

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.

Source · MahaRERA sold/unsold inventory filing · read 02 Jul 2026

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for ANANTARA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 16 September 2026

What the filings record, home by home

Read from MahaRERA on 16 September 2026

No home in ANANTARA carries a registered agreement value on its MahaRERA filing, so there is no record here of what anyone has paid. What the promoter has filed is the government ready reckoner value for 268 homes — the Annual Statement of Rates valuation, with each home’s carpet area and floor already applied. Across them that is Rs 6,726 a sq ft typical, over Rs 6,726 to Rs 6,726.

A reckoner value is the basis stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home to you.

The Reckoner Record lists all 268 of them — each home, its RERA carpet area, the valuation filed against it and the rate that works out to. It is the filing copied, not a reading of it.

See all 268 filed valuations — ₹999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13 and 102 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
BUILDING NO 12G+13102-

Unit mix on the filing: 268 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at NALASOPARA EAST, LINK ROAD, Mumbai City, Mumbai City, 401209. Per the filed land record, the plot is bounded to the north by CHANNEL, to the south by CHANNEL, to the east by OPEN LAND SURVEY NO 34 and to the west by OVERHEAD WATER TANK. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~31 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ31 km
Powai / Hiranandani business park33 km
Chhatrapati Shivaji Int'l Airport35 km
Bandra Kurla Complex (BKC)38 km
Lower Parel / Worli business district45 km
Nariman Point / Fort53 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Nallasopara East

Model Cooperative Housing Society LTD
possession by Oct 2026 · Sai Vaishnav Infra Llp
N G Platinum City
possession by Dec 2026 · J M G Realtors PVT LTD
Rudra Heights Bldg NO 1 Wing -G
possession by Dec 2026 · Aura Navkar Developers
Ajay CO-Operative Housing Society LTD
possession by Dec 2026 · MAA Guru Construction
Imperialparamount
possession by Dec 2026 · Shivganga Construction & Redeveloper
Precilla CHS LTD
possession by Dec 2026 · Blue OAK Infrastructure

Other RERA-registered projects in Palghar

Ananya Residency
declared completion Dec 2025 · Sahyog Group
Ananya Residency
declared completion Mar 2023 · Shreeji Builders
Ananya Residency Wing B Building 3
declared completion Dec 2021 · Vinay Harihar Singh
Angel Apartment
possession by Dec 2029 · Shreenathji Enterprises
Angel Business Centre
declared completion Jun 2023 · Angel Developers
Angel Crescenta
possession by Jun 2027 · JD Infra

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026