MahaRERA Property Intelligence · Raigarh

ANKIT FIONA PHASE 1

P52000012190 · BHUWANESHWAR · promoter Mahesh Suhas Padalkar

Certificate SignedDue 30 Oct 2020

Delivery & Registration

MahaRERA registrationP52000012190
Registered on01 Sep 2017
Promoter-declared completion30 Oct 2020
Current statusCertificate Signed
Against todayabout 69 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Mahesh Suhas Padalkar is the promoter of record on 2 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
PEARL1G+8-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Oct 202030 Apr 2020Our said project is already completed within the prescribed time, to apply for the occupation certificated we need to attach various documents, but till date, we are waiting for th
30 Oct 202030 Apr 2020non availability of Building materials and skilled Labour,

Location, Land & Connectivity

Located at BHUWANESHWAR, SHANKAR MANDIR ROAD, Thane, Thane, 402109. Per the filed land record, the plot is bounded to the north by SURVEY NO 54, to the south by SURVEY NO 53, to the east by SURVEY NO 54 and to the west by SURVEY NO 52. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~70 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Nariman Point / Fort64 km
Lower Parel / Worli business district70 km
Bandra Kurla Complex (BKC)76 km
Chhatrapati Shivaji Int'l Airport78 km
Powai / Hiranandani business park80 km
Andheri MIDC / SEEPZ82 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Mahesh Suhas Padalkar is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Mahesh Suhas Padalkar

Mahesh Suhas Padalkar
Not filing quarterly progress reportsRaigarh

Other RERA-registered projects in Roha

AK Platinum Tower
possession by Dec 2026 · Amit Shashikant Khatu
Vardhaman Tower
Not filing quarterly progress reports · possession by Dec 2026 · Vardhaman Tower
Ankit Fiona Phase 2
Not filing quarterly progress reports · possession by Dec 2026 · Mahesh Suhas Padalkar
Chandradarshan Empire Phase II
possession by Dec 2026 · M/S R J Infra Developers
Hecc-SAI City
possession by Dec 2026 · Liyakat Anwar Hafiz
Mithila Icon
possession by Mar 2027 · N R Builders AND Develoeprs

Other RERA-registered projects in Raigarh

Ankit Fiona Phase 2
possession by Dec 2026 · Mahesh Suhas Padalkar
Ankita CHS LTD
possession by Sep 2028 · Saigan
Anmol Corner
declared completion Dec 2024 · Jayashri Maya Mundkar
Anmol Nirmiti
declared completion Feb 2025 · Anmol Nirmiti Pvt Ltd
Anmol Sankalp
declared completion Dec 2019 · Meenaskhi Madhavanand Bhatt
Anmol Sonai Heritage
possession by Dec 2029 · Not Available

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026