MahaRERA Property Intelligence · Thane

Archit Jewel

P51700009850 · Mumbra · promoter Archit Enterprises

Certificate SignedDue 31 Dec 2025

Delivery & Registration

MahaRERA registrationP51700009850
Registered on22 Aug 2017
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 7 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Archit Enterprises is the promoter of record on 7 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15.

BuildingWingsFloorsDeclared completion
Building No 11G+8-
Building No 1A1G+1-
building No 21G+15-
Building No 31G+7-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Aug 202331 Aug 2023We sought an extension for project completion due to the main reason listed below: 1. Our project is badly affected by Covid impact. 2. Due to Skilled labour unavailability and
30 May 202231 Dec 2025This application is for additional 4 Floors in Building no.3. As per earlier CC, we completed work of Building no.1A, 1, 2 and 3 and Form 4 Submitted for the same. In Earlier CC,

Location, Land & Connectivity

Located at Mumbra, Mumbra Road, Thane, Thane, 400612. Per the filed land record, the plot is bounded to the north by Saif Palace, to the south by Baitulnisar Apt, to the east by Alam Mahal and to the west by Wasantrao Apt. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~15 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park15 km
Andheri MIDC / SEEPZ18 km
Chhatrapati Shivaji Int'l Airport20 km
Bandra Kurla Complex (BKC)21 km
Lower Parel / Worli business district29 km
Nariman Point / Fort36 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Mumbra

Celosia Avenue
possession by Sep 2026 · Pratima Construction
Quality Annex
possession by Sep 2026 · Quality Annex
YES Central Galleria
possession by Oct 2026 · Noble Enterprises
YES Central Galleria 1
possession by Oct 2026 · YES Enterprises
Sagar Enclave
possession by Dec 2026 · Kanchan Builders & Developers
Grace Square Type D3
possession by Dec 2026 · Shree Sumatinath Enterprises LLP

Major developers building in Mumbra

Other RERA-registered projects in Thane

Arena
declared completion Mar 2019 · Nakshatra Realtors
Arena Square
possession by Jun 2030 · Empire Arena
Arfa Garden
possession by Dec 2026 · Quba Homes LLP
Arham Residency
declared completion Dec 2023 · Siddhivinayak Enterprises
Arham Vatika
declared completion Jul 2018 · Arham Enterprises
Arihant Aaradhya Phase I
possession by Mar 2029 · Arihant Superstructures Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026