MahaRERA Property Intelligence · Thane

ARENA

P51700012059 · promoter Nakshatra Realtors

Certificate SignedDue 31 Mar 2019

Delivery & Registration

MahaRERA registrationP51700012059
Registered on01 Sep 2017
Promoter-declared completion31 Mar 2019
Current statusCertificate Signed
Against todayabout 88 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Nakshatra Realtors is the promoter of record on 33 projects, of which 6 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+20.

BuildingWingsFloorsDeclared completion
ARENA1G+2031 Mar 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Thane, Thane, 400604. Per the filed land record, the plot is bounded to the north by 15 MT DP ROAD, to the south by MUNICIPAL HOUSING RESERVATION, to the east by 15 M SERVICE ROAD and to the west by ATHENA BUILDING. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~10 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Powai / Hiranandani business park10 km
Andheri MIDC / SEEPZ11 km
Chhatrapati Shivaji Int'l Airport15 km
Bandra Kurla Complex (BKC)17 km
Lower Parel / Worli business district25 km
Nariman Point / Fort33 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Wagle Estate

Urban Villa
possession by Jul 2026 · Yash Infra
One Wagle
possession by Oct 2026 · Sagar Nirman Spaces
Bhairaav Milestone Phase II
possession by Dec 2026 · Sharpmind Consultancy Services Private L
Aura Business Center
possession by Dec 2026 · AUM Developers
Centura Square
possession by Dec 2026 · Supper Squarefeet Infraventures LLP
O22 Business Park
possession by Dec 2026 · Midas Touch

Other RERA-registered projects in Thane

Arena Square
possession by Jun 2030 · Empire Arena
Arfa Garden
possession by Dec 2026 · Quba Homes LLP
Arham Residency
declared completion Dec 2023 · Siddhivinayak Enterprises
Arham Vatika
declared completion Jul 2018 · Arham Enterprises
Arihant Aaradhya Phase I
possession by Mar 2029 · Arihant Superstructures Limited
Arihant Aaradhya Phase II
possession by Dec 2030 · Arihant Superstructures Limited

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026