Mumbai/Project record

MahaRERA · the public record

ARYAMAN TANISH

MUMBAI · ARYAMAN INFRATECH INDIA PVT LTD

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800012284

Delivery and registration

When is the project declared for completion?

ARYAMAN TANISH is registered with MahaRERA as P51800012284 and the promoter has declared completion for 30 Jun 2024.

30 Jun 2024

declared completion

27months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800012284
Registered on01 Sep 2017
Promoter-declared completion30 Jun 2024
Current statusCertificate Signed
Against todayabout 27 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for ARYAMAN TANISH record 28 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 28 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Aryaman Infratech India is the promoter of record on 183 projects registered with MahaRERA, 16 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

183projects

registered with MahaRERA

16flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for ARYAMAN TANISH in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15.

BuildingWingsFloorsDeclared completion
SBI EMPLOYEES SHIVNER CHSL1G+1530 Jun 2022

Legal and disputes

What disputes are disclosed?

5 complaints are on the MahaRERA record for ARYAMAN TANISH, with orders passed in 4 of them.

5complaints

4with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000000043012/09/2017Sunil Shridhar Mayekar vs ARYAMAN INFRATECH INDIA PVT. LTD.order passed
CC00600000005657419/10/2018Mr Manish Harish Desai vs M/s Aryaman Infratech Pvt Ltdorder passed
CC00600000039774507/10/2023Manisha Mansing Khorate vs Aryaman Infratech India Pvt. Ltd.order passed
CC00600000039774707/10/2023Manisha Mansing Khorate vs Aryaman Infratech India Pvt. Ltd.pending / no order on file
CC1250046812/02/2025Rashmi Rajesh Dahanukar vs ARYAMAN INFRATECH INDIA PVT LTDorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 4 times, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2020MCGM has not given permission in time and delayed permission for more than 7 months.
30 Jun 202030 Jun 2020We Have Approached to National Company Law Board Mumbai Bench NCLT And filed company petition under section 252 of the companies act 203 bearing CP no 3947/25/NCLT/MB/MAH/2018 for
30 Jun 202031 Dec 2021We have applied for the CC in December,2019 but due to delay in MCGM approvals and then in MArch lockdown was started, we are not able to start our work as we get the commencement
31 Dec 202130 Jun 20241) AFTER LOCK DOWN THE SUPPLY OF PARTS FOR LIFT WAS DELAYED BY THE LIFT COMPANY IN THE YEAR 2021, ORDER WAS PLACED AND MATERIAL WERE SUPPLIED IN JUNE 2023. 2) DUE TO ARBITRATIO

Location, Land & Connectivity

Located at MUMBAI, OFF LINK ROAD, Andheri, Mumbai Suburban, 400058. Per the filed land record, the plot is bounded to the north by BHARDAWADI ROAD, to the south by NALLAH, to the east by CTS NO 679 and to the west by NALLAH. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ4 km
Chhatrapati Shivaji Int'l Airport5 km
Bandra Kurla Complex (BKC)8 km
Powai / Hiranandani business park8 km
Lower Parel / Worli business district14 km
Nariman Point / Fort22 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Aryaman Infratech India PVT LTD is the promoter on 3 MahaRERA-registered projects, of which 3 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Aryaman Infratech India PVT LTD

Aryaman Infratech India PVT LTD
Past its declared completion dateMumbai Suburban
Aryaman Infratech India PVT LTD
Past its declared completion dateMumbai Suburban

Other RERA-registered projects in Andheri West

Anutam
possession by Sep 2026 · Truly Highdreams Realtors LLP
Vivan Homes
possession by Dec 2026 · Imprint Estates Pvt Ltd
Alpine Primo
Registration suspended · possession by Dec 2026 · Alpine Infraheights LLP
Bella Casa
possession by Dec 2026 · Konark Bella Casa LLP
Hetali Sagar
possession by Dec 2026 · Jayesh Himatlal Pandya
La Alteza
possession by Dec 2026 · Emerald Developers

Major developers building in Andheri West

Other RERA-registered projects in Mumbai Suburban

Aryan Tower
possession by Dec 2026 · Suchit Developers
Aryana Heights
possession by Mar 2027 · M/s M Raveshia Realty LLP
Ascend Tower
possession by Dec 2027 · M. Mamtora Associates
Ashford Regal - Phase I - Wing A Project
possession by Jun 2027 · WMI Real Estate Developers LLP
Ashford Regal - Phase II - Wing B Project
possession by Dec 2027 · WMI Real Estate Developers LLP
Ashford Regal - Phase III - Wing F Project
possession by Dec 2027 · WMI Real Estate Developers LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026