MahaRERA Property Intelligence · Mumbai Suburban

Aryaman Marina

P51800012786 · promoter Aryaman Infratech India

Certificate SignedDue 30 Jun 2022

Delivery & Registration

MahaRERA registrationP51800012786
Registered on07 Sep 2017
Promoter-declared completion30 Jun 2022
Current statusCertificate Signed
Against todayabout 49 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Aryaman Infratech India is the promoter of record on 176 projects, of which 16 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+18.

BuildingWingsFloorsDeclared completion
V-PARIJAT CHSL1G+18-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Andheri, Mumbai Suburban, 400061. Per the filed land record, the plot is bounded to the north by BY ROAD, to the south by CTS NO 1011, to the east by CTS NO 994 and to the west by BY ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ7 km
Chhatrapati Shivaji Int'l Airport9 km
Powai / Hiranandani business park11 km
Bandra Kurla Complex (BKC)11 km
Lower Parel / Worli business district16 km
Nariman Point / Fort24 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Aryaman Infratech India PVT LTD is the promoter on 3 MahaRERA-registered projects, of which 3 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Aryaman Infratech India PVT LTD

Aryaman Infratech India PVT LTD
Past its declared completion dateMumbai Suburban
Aryaman Infratech India PVT LTD
Past its declared completion dateMumbai Suburban

Other RERA-registered projects in Versova

Raheja Exotica Downtown
possession by Dec 2026 · Raheja Universal Ltd.
Ocean View
possession by Dec 2026 · Star Construction
Seabliss
possession by Dec 2026 · Asshna Developers Westin
Amalfi
possession by Dec 2027 · Richfeel Real Estate Pvt. Ltd.
Elysia
possession by Dec 2027 · Olive Developers
Cullinan
possession by Dec 2028 · Lodha Developers Limited

Major developers building in Versova

Other RERA-registered projects in Mumbai Suburban

Aryaman Tanish
declared completion Jun 2024 · Aryaman Infratech India PVT LTD
Aryan Tower
possession by Dec 2026 · Suchit Developers
Aryana Heights
possession by Mar 2027 · M/s M Raveshia Realty LLP
Aryavarta Indraprastha Chsl
declared completion Nov 2025 · Aryavarta Indraprastha Co Operative Hous
Ascend Tower
possession by Dec 2027 · M. Mamtora Associates
Ashar Maple Birch
declared completion Dec 2025 · Ms Ashar Realtors

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026