Alpine Primo
Andheri West · ALPINE INFRAHEIGHTS LLP
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
31 Dec 2026
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P51800030851
Delivery and registration
When is the project declared for completion?
Alpine Primo is registered with MahaRERA as P51800030851 and the promoter has declared completion for 31 Dec 2026.
31 Dec 2026
declared completion
3months to go
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P51800030851 |
| Registered on | 20 Sep 2021 |
| Promoter-declared completion | 31 Dec 2026 |
| Current status | Certificate Signed |
| Against today | 3 months to the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Alpine Primo record 19 quarterly progress reports since registration.
19quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Suspended / abeyance — the registration is suspended or in abeyance.
- Filing progress reports — 19 quarterly progress reports on record since registration, with no current default.
Promoter record
What else is this promoter on record for?
Alpine Infraheights Llp is the promoter of record on 3 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).
3projects
registered with MahaRERA
1flagged
by MahaRERA
Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.
Source · MahaRERA register, all projects · read 12 Jul 2026
Construction
How much construction cost has been reported?
In Alpine Primo, ₹67.55 Cr of a declared ₹87.67 Cr estimated project cost is reported as incurred, about 77.1%, as at the last certified filing with MahaRERA.
77.1%
₹67.55 Cr
of ₹87.67 Cr declared cost
Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.
Source · MahaRERA quarterly progress filing · read 12 Jul 2026
Sales
How much has actually been sold?
In Alpine Primo, 90 of 112 homes filed with MahaRERA are recorded as sold or booked (85 with registered agreements and 5 booked), about 80%, and 22 remain available.
80%sold
90 of 112 homes
₹126.19 Cr
committed by buyers
Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹92.94 Cr (about 74%) is recorded as collected and ₹25.03 Cr as receivable. The project registers 219 homes in total, while this sold/unsold inventory filing covers 112 of them.
Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026
What buyers actually paid: across 89 registered agreements, the effective carpet rate is ₹23,102/sqft, with eight in ten falling between ₹15,796 and ₹29,159 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.
The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.
| Floor | Unit | Carpet | Govt reckoner value |
|---|---|---|---|
| Floor 1 | 16 | 590 sqft (54.81 sqm) | ₹98.13 Lakh |
| Floor 1 | 20 | 590 sqft (54.81 sqm) | ₹85.33 Lakh |
| Floor 1 | 21 | 555 sqft (51.56 sqm) | ₹80.27 Lakh |
| Floor 10 | 1001 | 606 sqft (56.3 sqm) | ₹87.65 Lakh |
| Floor 10 | 1005 | 422 sqft (39.18 sqm) | ₹61.00 Lakh |
| Floor 11 | 1103 | 597 sqft (55.49 sqm) | ₹86.39 Lakh |
| Floor 11 | 1103 | 606 sqft (56.3 sqm) | ₹87.65 Lakh |
| Floor 12 | 1201 | 606 sqft (56.3 sqm) | ₹87.65 Lakh |
| Floor 12 | 1202 | 632 sqft (58.71 sqm) | ₹91.40 Lakh |
| Floor 12 | 1203 | 606 sqft (56.3 sqm) | ₹87.65 Lakh |
| Floor 13 | 1302 | 639 sqft (59.37 sqm) | ₹92.43 Lakh |
| Floor 13 | 1302 | 635 sqft (58.99 sqm) | ₹91.84 Lakh |
| Floor 13 | 1304 | 948 sqft (88.07 sqm) | ₹1.37 Cr |
| Floor 14 | 1401 | 633 sqft (58.81 sqm) | ₹91.56 Lakh |
| Floor 14 | 1402 | 639 sqft (59.37 sqm) | ₹92.43 Lakh |
| Floor 14 | 1402 | 635 sqft (58.99 sqm) | ₹91.84 Lakh |
| Floor 14 | 1403 | 678 sqft (62.99 sqm) | ₹98.06 Lakh |
| Floor 14 | 1405 | 425 sqft (39.45 sqm) | ₹61.42 Lakh |
| Floor 6 | 602 | 635 sqft (58.99 sqm) | ₹91.84 Lakh |
| Floor 8 | 802 | 597 sqft (55.49 sqm) | ₹86.39 Lakh |
| Floor 8 | 803 | 597 sqft (55.49 sqm) | ₹86.39 Lakh |
| Floor 8 | 803 | 606 sqft (56.3 sqm) | ₹87.65 Lakh |
The inventory filing also declares: 13 reserved.
What the filings record, home by home
Read from MahaRERA on 18 September 2026
MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 89 homes carry one, and 22 of the 125 are recorded unsold.
Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:
| Home | Carpet | Filed for the same home on other floors | Based on |
|---|---|---|---|
| 1401 | 633 sqft | Rs 22,277 a sq ft typical, over Rs 15,185 to Rs 45,663 | 35 filed at this size |
A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.
In Alpine Primo, 21 of the 22 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+17 and 219 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| Alpine Primo -A Wing | 1 | G+16 | 82 | 31 Dec 2024 |
| Alpine Primo -B Wing | 1 | G+16 | 57 | 31 Dec 2024 |
| Alpine Primo - C Wing | 1 | G+17 | 80 | 31 Dec 2024 |
Unit mix on the filing: 145 residential and 74 non-residential (shops/offices).
Legal and disputes
What disputes are disclosed?
3 complaints are on the MahaRERA record for Alpine Primo, with orders passed in 1 of them.
3complaints
1with an order
Counts as disclosed in the project record.
Source · MahaRERA project disclosures · read 12 Jul 2026
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC12400893 | 26/11/2024 | Aniket Mhatre vs Rishabh Rakesh Yadav | order passed |
| CC12601728 | 25/03/2026 | Sandeep Singh vs ALPINE INFRAHEIGHTS LLP | pending / no order on file |
| CC12601868 | 30/03/2026 | Anil Goyal vs ALPINE INFRAHEIGHTS LLP | pending / no order on file |
Deadline Extensions
The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.
| From | Extended to | Stated reason |
|---|---|---|
| as registered | 31 Dec 2025 | We understand the importance of adhering to project timelines as per MahaRERA regulations, and we assure you that our team is working diligently to mitigate these challenges. Howev |
| 31 Dec 2025 | 31 Dec 2026 | due to delay in sanctioned plans from concerned authority, therefore there was delay in completing the project, hence we request you to kindly grant us extension for further period |
Location, Land & Connectivity
Located at Andheri West, J P Road & S N Patil Marg, Borivali, Mumbai Suburban, 400058. Per the filed land record, the plot is bounded to the north by Nalla, to the south by 27 M JP Road, to the east by CTS No - 128 129 and 130 and to the west by 9 M Wide S N Patil Marg. These are the boundaries as recorded in the filed land record.