Altavista - Phase 1

Mumbai City · SPENTA ENCLAVE PRIVATE LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Jul 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Jul 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800001050

Delivery and registration

When is the project declared for completion?

Altavista - Phase 1 is registered with MahaRERA as P51800001050 and the promoter has declared completion for 31 Jul 2024.

31 Jul 2024

declared completion

26months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800001050
Registered on25 Jul 2017
Promoter-declared completion31 Jul 2024
Current statusCertificate Signed
Against todayabout 26 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Altavista - Phase 1 record 29 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • NCLT / insolvency — the promoter is (or was) before the NCLT for insolvency — the gravest RERA flag; buyer money and possession are at real risk.
  • Filing progress reports — 29 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Spenta Enclave is the promoter of record on 30 projects registered with MahaRERA, 9 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

30projects

registered with MahaRERA

9flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Altavista - Phase 1 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+28.

BuildingWingsFloorsDeclared completion
Wing A1G+2831 Dec 2019
Wing B1G+2831 Dec 2019
Wing C1G+2831 Dec 2019
Wing D1G+2831 Dec 2019

Legal and disputes

What disputes are disclosed?

18 complaints are on the MahaRERA record for Altavista - Phase 1, with orders passed in 18 of them.

18complaints

18with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000001224201/12/2017Subhash Bawa vs Spenta Enclave Private Limitedorder passed
CC00600000019608017/02/2021Debanik Basu vs Spenta Enclave Private Limitedorder passed
CC00600000019816305/12/2021MANISH AGARWAL vs SPENTA ENCLAVE PVT LTDorder passed
CC00600000018211108/01/2020Umesh Prabhakar Dhopate and Pranita Umesh Dhopate vs Spenta Enclave Pvt Ltdorder passed
CC00600000019312925/07/2020Anil Kishinchand Rajani vs Spenta Enclave Private Limitedorder passed
CC00600000019327910/06/2020Mrs Sneha Vijay Nair and Mr Vijaykumar Madhavan vs Spenta Enclave Private Limitedorder passed
CC00600000019350428/07/2020Mr. Dhirendra Kumar Sinha and Mrs. Devyani Singh vs Spenta Enclave Private Limitedorder passed
CC00600000019359827/07/2020Amisha Ghia vs Spenta Enclave Pvt Ltdorder passed
CC00600000019473431/10/2020Geeta PramodKumar Gupta vs SPENTA ENCLAVE PRIVATE LIMITEDorder passed
CC00600000019532521/12/2020Monish Satwe vs Spenta Enclave Pvt. Ltd.order passed
CC00600000019532821/12/2020Monish Satwe vs Spenta Enclave Pvt. Ltd.order passed
CC00600000019598914/05/2021Urvanki I Shah vs Spenta Enclave Pvt Ltdorder passed
CC00600000019620328/02/2021Rajan Singh Chugh vs Alta Vista Builder Builder Spenta Corporationorder passed
CC00600000019754907/07/2021Mr Shrinivas Manche & Mrs Vanita Manche vs Spenta Enclave Private Limitedorder passed
CC00600000022113016/05/2022Ganesh Praful Tondwalkar vs SPENTA ENCLAVE PVT. LTDorder passed
CC00600000029265014/09/2022Smriti Parekh vs spenta enclave pvt ltdorder passed
CC1250000801/01/2025Rajesh Jhunjhunwala vs Anil Kishinchand Rajaniorder passed
CC1250000901/01/2025Rajesh Jhunjhunwala vs Ganesh Praful Tondwalkarorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2020The project being undertaken is being undertaken under the provisions of chapter 33(10) of the DCR pertaining to the rehabilitation of slums. As per provisions of this chapter, OC
30 Dec 202031 Jul 2024In the aforementioned project Altavista Phase 1 we have completed 4 wings having 445 residential flats. Unfortunately, the elevator company messed up the installation of 2 elevator

Location, Land & Connectivity

Located at Ward ABCD, Mumbai City, 400071. Per the filed land record, the plot is bounded to the north by Reahb Building, to the south by Altavista Phase 2, to the east by Hill and to the west by DP Road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bandra Kurla Complex (BKC)2 km
Chhatrapati Shivaji Int'l Airport5 km
Powai / Hiranandani business park8 km
Lower Parel / Worli business district8 km
Andheri MIDC / SEEPZ9 km
Nariman Point / Fort15 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Spenta Enclave Private Limited is the promoter on 6 MahaRERA-registered projects, of which 6 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Spenta Enclave Private Limited project & its RERA track record →

Other flagged projects by Spenta Enclave Private Limited

Spenta Enclave Private Limited
Developer in insolvency (NCLT)Mumbai Suburban
Spenta Enclave Private Limited
Developer in insolvency (NCLT)Mumbai Suburban
Spenta Enclave Private Limited
Developer in insolvency (NCLT)Mumbai Suburban
Spenta Enclave Private Limited
Developer in insolvency (NCLT)Mumbai Suburban
Spenta Enclave Private Limited
Developer in insolvency (NCLT)Mumbai Suburban

Other RERA-registered projects in Chembur

Gurukripa
possession by Sep 2026 · Inspira Realty And Infra Private Limited
Kranti Heights
possession by Sep 2026 · Sidhivinayak Constructions
Mass Metropolis
possession by Sep 2026 · Grace Urban Development Corporation
Mohite Mrugank
possession by Sep 2026 · Mohite Infraprojects Private Limited
Laxmina Krishna Niwas
possession by Oct 2026 · Laxmina Argentum Realties Private Lim
Safal SAI AND Safal Sainath
possession by Oct 2026 · Mangalnath Developers PVT LTD

Major developers building in Chembur

Other RERA-registered projects in Mumbai Suburban

Altavista - Phase 2
possession by Jun 2028 · Spenta Enclave Private Limited
Altavista - Phase 3
possession by Jun 2028 · Spenta Enclave Private Limited
Altavista - Phase 4
possession by Dec 2029 · Spenta Enclave Private Limited
Altus
possession by Dec 2030 · Lodha Developers Limited
Amaha Sunflower
possession by Dec 2030 · Build Confia India LLP
Amaira Pallazo
possession by Nov 2030 · Taramati Builders AND Developers Private

What to verify (NCLT insolvency)

  1. Check the IRP/Resolution Professional's name on the NCLT cause list and contact them for a project status update.
  2. Verify whether a Resolution Plan has been approved — the IRP's report is filed with NCLT and is public.
  3. Look for a homebuyers' association for this project — allottee groups have legal standing in insolvency proceedings.
  4. Consult a RERA or IBC advocate about your rights under Section 7 IBC or Section 18 RERA for possession or refund.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026