31 Dec 2018declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2018

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700001169

Delivery and registration

When is the project declared for completion?

ASHAR 16 WING B PHASE IV is registered with MahaRERA as P51700001169 and the promoter has declared completion for 31 Dec 2018.

31 Dec 2018

declared completion

93months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700001169
Registered on27 Jul 2017
Promoter-declared completion31 Dec 2018
Current statusCertificate Signed
Against todayabout 93 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for ASHAR 16 WING B PHASE IV record 6 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 6 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Ashar Realtors is the promoter of record on 43 projects registered with MahaRERA, 6 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

43projects

registered with MahaRERA

6flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for ASHAR 16 WING B PHASE IV in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+22.

BuildingWingsFloorsDeclared completion
ASHAR 16 WING B1G+2231 Dec 2018

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at WAGALE ESTATE , ROAD NO 16, Thane, Thane, 400604. Per the filed land record, the plot is bounded to the north by PODIUM-PLOT NO A-178, to the south by ROAD NO V, to the east by ROAD NO 16 and to the west by ASHAR 16 WING C . These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~10 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park10 km
Andheri MIDC / SEEPZ12 km
Chhatrapati Shivaji Int'l Airport15 km
Bandra Kurla Complex (BKC)17 km
Lower Parel / Worli business district26 km
Nariman Point / Fort33 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Ms Ashar Realtors is the promoter on 8 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Ms Ashar Realtors project & its RERA track record →

Other flagged projects by Ms Ashar Realtors

Other RERA-registered projects in Wagle Estate

One Wagle
possession by Oct 2026 · Sagar Nirman Spaces
Bhairaav Milestone Phase II
possession by Dec 2026 · Sharpmind Consultancy Services Private L
Aura Business Center
possession by Dec 2026 · AUM Developers
Centura Square
possession by Dec 2026 · Supper Squarefeet Infraventures LLP
O22 Business Park
possession by Dec 2026 · Midas Touch
White Rose
possession by Dec 2026 · M/s Eeshan Enterprises

Other RERA-registered projects in Thane

Ashar Arize Galleria
possession by Jan 2027 · Ms Ashar Ventures
Ashar Arize N.m.m. Society Tower A
possession by Jan 2027 · Ms Ashar Ventures
Ashar Arize Tower B AND C
possession by Dec 2027 · Ms Ashar Ventures
Ashar Maple Phase 1 Building No.2
declared completion Dec 2022 · Ms Ashar Realtors
Ashar Merac Phase 3
possession by Dec 2031 · Ajay Pratap Ashar
Ashar Merac Phase I
possession by Dec 2028 · Ajay Pratap Ashar

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026