ASMEETA TEXPA - II

Additional Kalyan Bhiwandi Industrial Area · MAGUS INFRATECH PRIVATE LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2030declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2030

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700020215

Delivery and registration

When is the project declared for completion?

ASMEETA TEXPA - II is registered with MahaRERA as P51700020215 and the promoter has declared completion for 30 Dec 2030.

30 Dec 2030

declared completion

51months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700020215
Registered on29 Mar 2019
Promoter-declared completion30 Dec 2030
Current statusCertificate Signed
Against today51 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for ASMEETA TEXPA - II record 37 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Deregistered — MahaRERA has deregistered this project — it is off the register.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Magus Infratech is the promoter of record on 183 projects registered with MahaRERA, 16 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

183projects

registered with MahaRERA

16flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for ASMEETA TEXPA - II in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
E6A1G+431 Dec 2022
E6B1G+431 Dec 2022
E3A1G+431 Dec 2023
E3B1G+431 Dec 2023
E71G+431 Dec 2024
E81G+431 Dec 2024
F11G+431 Dec 2026
CFC 41G+631 Dec 2026
Residential Bldg for Workers - 11G+831 Dec 2026
Residential Bldg for Workers - 21G+831 Dec 2026

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Additional Kalyan Bhiwandi Industrial Area, Kalyan Bhiwandi Road, Mumbai City, Mumbai City, 421311. Per the filed land record, the plot is bounded to the north by Asmeeta Texpa Internal Road, to the south by MIDC Boundary, to the east by MIDC Boundary and to the west by Asmeeta Texpa Internal Road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~14 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park14 km
Andheri MIDC / SEEPZ15 km
Chhatrapati Shivaji Int'l Airport19 km
Bandra Kurla Complex (BKC)20 km
Lower Parel / Worli business district29 km
Nariman Point / Fort36 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Magus Infratech Private Limited is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Magus Infratech Private Limited

Magus Infratech Private Limited
FlaggedThane

Other RERA-registered projects in Kongaon

Namo Maxima
possession by Dec 2026 · Viren Kishor Jain
Shree Laxman Apartment
possession by Dec 2026 · Shri Gajanan Enterprises
Tahoora Complex
Not filing quarterly progress reports · possession by Dec 2026 · Shree Harekrishna Realtor
Atlantic
possession by Mar 2027 · Riddhi Siddhi Enterprises
Magus City Tower 1 Selene
possession by Apr 2027 · Magus Infratech Private Limited
SAI Darshan
possession by Apr 2027 · Trimurti Enterprises

Major developers building in Kongaon

Other RERA-registered projects in Thane

Asmita Grand Maison
possession by Dec 2027 · Asmita India Limited
Asteria
possession by Mar 2028 · Aariv Buildcon
Atharv Residency
declared completion May 2022 · Pethe Builders AND Developers
Atharva Heights
possession by Dec 2026 · JAI Shreegurutatvam Engineers AND Develo
Atlanta Avadh
possession by Apr 2028 · Atlanta Globalprojects LLP
Atlanta Crown
possession by Apr 2027 · Atlanta Construction

What to verify (inactive registration)

  1. Download the MahaRERA order stating the reason for deregistration or suspension — this is public on the portal.
  2. Check whether the developer has filed a challenge in the Appellate Tribunal and whether the order is stayed.
  3. Do not make any further payments until the registration status is restored or you obtain legal advice.
  4. Contact MahaRERA's helpdesk for guidance on alternative arrangements or pending dues.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026