MahaRERA Property Intelligence · Mumbai City

Atlantis Residency

P51900005501 · Mazgaon · promoter Jk Builders

Certificate SignedDue 31 Dec 2026

Delivery & Registration

MahaRERA registrationP51900005501
Registered on11 Aug 2017
Promoter-declared completion31 Dec 2026
Current statusCertificate Signed
Against today5 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Construction Progress

MahaRERA's cost filing puts construction at ~80.0% of the estimated project cost incurred as of the last certificate (₹51.17 Cr spent against a ₹64.00 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 55 homes filed with MahaRERA, 28 are sold/booked and 27 remain available (~51% sold) — selling steadily. Buyers have committed ₹35.53 Cr in agreement value so far. Of that, ₹30.14 Cr (~85%) is already collected, ₹5.40 Cr receivable — a read on how far along these sales really are. Note: the project registers 161 homes in total, but this sold/unsold inventory filing covers only 55 of them — the other 106 aren't in the ledger yet. Ask the builder what they are (an unreleased phase, held-back stock, or non-saleable/car-park units) before reading too much into the percentage. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 28 registered agreements, the effective carpet rate is ₹19,709/sqft (typical range ₹19,003–₹22,851) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 101003993 sqft (92.24 sqm)₹1.89 Cr
Floor 111103993 sqft (92.24 sqm)₹1.89 Cr
Floor 141401993 sqft (92.24 sqm)₹1.89 Cr
Floor 141403993 sqft (92.24 sqm)₹1.89 Cr
Floor 1415031,030 sqft (95.69 sqm)₹1.96 Cr
Floor 151501993 sqft (92.24 sqm)₹1.89 Cr
Floor 161601993 sqft (92.24 sqm)₹1.89 Cr
Floor 161603993 sqft (92.24 sqm)₹1.89 Cr
Floor 171701993 sqft (92.24 sqm)₹1.89 Cr
Floor 171703993 sqft (92.24 sqm)₹1.89 Cr
Floor 181801993 sqft (92.24 sqm)₹1.89 Cr
Floor 181802661 sqft (61.39 sqm)₹1.26 Cr
Floor 181803993 sqft (92.24 sqm)₹1.89 Cr
Floor 191901993 sqft (92.24 sqm)₹1.89 Cr
Floor 191902661 sqft (61.39 sqm)₹1.26 Cr
Floor 191903993 sqft (92.24 sqm)₹1.89 Cr
Floor 202001993 sqft (92.24 sqm)₹1.89 Cr
Floor 202001406 sqft (37.71 sqm)₹77.00 Lakh
Floor 202002661 sqft (61.39 sqm)₹1.26 Cr
Floor 202003993 sqft (92.24 sqm)₹1.89 Cr
Floor 212101993 sqft (92.24 sqm)₹1.89 Cr
Floor 212102661 sqft (61.39 sqm)₹1.26 Cr
Floor 212103993 sqft (92.24 sqm)₹1.89 Cr
Floor 222201406 sqft (37.71 sqm)₹77.00 Lakh
Floor 222205406 sqft (37.71 sqm)₹77.00 Lakh
Floor 8801993 sqft (92.24 sqm)₹1.89 Cr
Floor 88031,030 sqft (95.69 sqm)₹1.96 Cr

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+22 and 161 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Wing A1G+2149-
Wing B1G+22112-

Unit mix on the filing: 148 residential and 13 non-residential (shops/offices).

Complaints & Orders

2 complaints are on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC1240035507/10/2024VILAS BHAGWAN DHOLAM vs JK BUILDERSpending / no order on file
SM1260031311/05/2026Bhakti Achrekar vs JK BUILDERSorder passed

Legal & Litigation

The promoter has declared 4 court cases on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Bombay High Court3942017Closed
Bombay High Court15102015Pending
Bombay High Court8002019Closed
Bombay High Court30472019Closed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 3 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 202431 Dec 2024(a) Several of the occupants who were to be rehabilitated had approached the Hon’ble Bombay High Court by multiple Writ Petitions. The Hon’ble High Court had by an Order dated 21s
30 Dec 202331 Dec 2025(a) Several of the occupants who were to be rehabilitated had approached the Hon’ble Bombay High Court by filing multiple Writ Petitions viz WP 394 of 2017, WP 800 of 2019 and WP 3
30 Dec 202331 Dec 2026Reasons for not completing the development works in 1 the Project within the period declared in the declaration submitted in Form ‘B’ at the time of making application for the regi

Location, Land & Connectivity

Located at Mazgaon, Rambhau Bhogale Marg, Mumbai City, Mumbai City, 400033. Per the filed land record, the plot is bounded to the north by Chapra Building, to the south by Sanghvi Bhavan, to the east by BPT godwon and to the west by 18 mtr Rambhau Bhogle marg. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Lower Parel / Worli business district2 km
Nariman Point / Fort7 km
Bandra Kurla Complex (BKC)9 km
Chhatrapati Shivaji Int'l Airport12 km
Powai / Hiranandani business park16 km
Andheri MIDC / SEEPZ16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Mazgaon

Pier 33
possession by Sep 2026 · Esque Finmark Private Limited
Simana - Wing B - Phase 1
possession by Dec 2026 · Bhoomi Properties
Vardhman Flora Phase I
possession by Dec 2026 · Vardhman Developers LTD
Parshwa Lotus & Rangari Heights
possession by Jan 2027 · Gold Plaza Developers PVT LTD
Darshan Aura
possession by Dec 2028 · Darshan SKY High Constructions LLP
Infinity Residences
possession by Dec 2028 · Infinity Associates

Major developers building in Mazgaon

Other RERA-registered projects in Mumbai City

Atlas Residency A And B
possession by Dec 2028 · Atlas Infratech Pvt.ltd
Atlas Royal - A
declared completion Dec 2025 · Atlas Infratech Pvt.ltd
Atlas Royal B
declared completion Dec 2025 · Atlas Infratech Pvt.ltd
AUM Saheel Tower
declared completion Dec 2023 · Santosh Enterprises
Aura Bliss
possession by Dec 2027 · Aura Monde LLP
Aura-Phase-1
declared completion Jan 2025 · Cosmos Realty

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026