Mumbai/Project record

MahaRERA · the public record

VARDHMAN FLORA PHASE I

GHODAPDEO · VARDHMAN DEVELOPERS LTD

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

40units filed as unsoldInventory · 13 September 2026
31 Dec 2026declared completionMahaRERA registration · read 12 Jul 2026
113registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900008829

Delivery and registration

When is the project declared for completion?

VARDHMAN FLORA PHASE I is registered with MahaRERA as P51900008829 and the promoter has declared completion for 31 Dec 2026.

31 Dec 2026

declared completion

3months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900008829
Registered on19 Aug 2017
Promoter-declared completion31 Dec 2026
Current statusCertificate Signed
Against today3 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for VARDHMAN FLORA PHASE I record 36 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Vardhman Developers Ltd is the promoter of record on 29 projects registered with MahaRERA, 4 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

29projects

registered with MahaRERA

4flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

How much has actually been sold?

In VARDHMAN FLORA PHASE I, 73 of 113 homes filed with MahaRERA are recorded as sold or booked, about 65%, and 40 remain available.

65%sold

73 of 113 homes

₹174.68 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹89.82 Cr (about 51%) is recorded as collected and ₹94.49 Cr as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 73 registered agreements, the effective carpet rate is ₹31,675/sqft, with eight in ten falling between ₹25,678 and ₹34,088 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.

FloorUnitCarpetGovt reckoner value
Floor 121201735 sqft (68.31 sqm)₹1.15 Cr
Floor 151501813 sqft (75.5 sqm)₹1.27 Cr
Floor 181801809 sqft (75.14 sqm)₹1.15 Cr
Floor 191901735 sqft (68.31 sqm)₹1.15 Cr
Floor 191902741 sqft (68.88 sqm)₹1.16 Cr
Floor 191903974 sqft (90.45 sqm)₹1.53 Cr
Floor 222202741 sqft (68.88 sqm)₹1.16 Cr
Floor 292902745 sqft (69.22 sqm)₹1.17 Cr
Floor 292903974 sqft (90.45 sqm)₹1.53 Cr
Floor 343403974 sqft (90.45 sqm)₹1.53 Cr
Floor 353503974 sqft (90.45 sqm)₹1.53 Cr
Floor 363603974 sqft (90.45 sqm)₹1.53 Cr
Floor 373703974 sqft (90.45 sqm)₹1.53 Cr
Floor 393903974 sqft (90.45 sqm)₹1.53 Cr
Floor 414103745 sqft (69.22 sqm)₹1.39 Cr
Floor 434302745 sqft (69.22 sqm)₹1.17 Cr
Floor 454501813 sqft (75.5 sqm)₹1.27 Cr
Floor 464603974 sqft (90.45 sqm)₹1.53 Cr
Floor 474702745 sqft (69.22 sqm)₹1.17 Cr
Floor 484801745 sqft (69.22 sqm)₹1.17 Cr
Floor 484802745 sqft (69.22 sqm)₹1.17 Cr
Floor 484803974 sqft (90.45 sqm)₹1.53 Cr
Floor 494901745 sqft (69.22 sqm)₹1.17 Cr
Floor 494902745 sqft (69.22 sqm)₹1.17 Cr
Floor 494903974 sqft (90.45 sqm)₹1.53 Cr
Floor 505001745 sqft (69.22 sqm)₹1.17 Cr
Floor 505002745 sqft (69.22 sqm)₹1.17 Cr
Floor 505003974 sqft (90.45 sqm)₹1.53 Cr
Floor 515102745 sqft (69.22 sqm)₹1.17 Cr
Floor 515103974 sqft (90.45 sqm)₹1.53 Cr
Floor 525201745 sqft (69.22 sqm)₹1.17 Cr
Floor 525202745 sqft (69.22 sqm)₹1.17 Cr
Floor 535301745 sqft (69.22 sqm)₹1.17 Cr
Floor 535302745 sqft (69.22 sqm)₹1.17 Cr
Floor 535303974 sqft (90.45 sqm)₹1.53 Cr
Floor 545401745 sqft (69.22 sqm)₹1.17 Cr
Floor 545402745 sqft (69.22 sqm)₹1.17 Cr
Floor 545403974 sqft (90.45 sqm)₹1.53 Cr
Floor 8803961 sqft (89.31 sqm)₹1.51 Cr
Floor 9903961 sqft (89.31 sqm)₹1.51 Cr

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 13 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 73 homes carry one, and 40 of the 113 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
4103745 sqftRs 2.3600 cr typical, over Rs 23.00 lakh to Rs 2.9117 cr40 filed at this size

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

In VARDHMAN FLORA PHASE I, every one of the 40 unsold homes has agreements filed on its own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 39 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+56 and 113 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
AAA1G+56113-

Unit mix on the filing: 113 residential.

Legal and disputes

What disputes are disclosed?

3 complaints are on the MahaRERA record for VARDHMAN FLORA PHASE I, with orders passed in 3 of them.

3complaints

3with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000019610522/02/2021Mrs. Mangal Namdev Shinde vs M/s Vardhman Developers Ltd.order passed
CC00600000019610622/02/2021NAMDEV DHONDIBA SHINDE vs M/S VARDHMAN DEVELOPERS LTD.order passed
CC00600000019610722/02/2021MRS. MANGAL NAMDEV SHINDE vs M/S VARDHMAN DEVELOPERS LTD.order passed

Legal & Litigation

The promoter has declared 11 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Small Cause Court8872016Issues
Small Cause Court8882016Issues
Small Cause Court8892016Issues
Small Cause Court8902016Issues
Small Cause Court14112015Issues
Small Cause Court14122015Issues
Small Cause Court14132015Issues
Small Cause Court3802013Hearing On Amendment Application
Bombay City Civil19712014Issues
Bombay City Civil43282013Issues
Bombay City Civil10892014Hearing On Specific Relief

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered29 Dec 2024The Project got delayed due to complete lock down in vicinity of the project because of COVID-19 and coupled with acute scarcity of workers. Most workers had left to their native p
29 Dec 202431 Dec 2025That we have taken project loan from L&T finance (The NBFC) & that NBFC was having financial strain which had impacted disbursement of the loan on time as and when required for the
31 Dec 202531 Dec 2026That we have taken project loan from L&T finance (The NBFC) & that NBFC was having financial strain which had impacted disbursement of the loan on time as and when required for the

Location, Land & Connectivity

Located at GHODAPDEO, RAMBHAU BHOGALE MARG, Ward ABCD, Mumbai City, 400033. Per the filed land record, the plot is bounded to the north by C S NO 753 AND 752, to the south by CS NO 2 750 AND 750, to the east by CS NO 9 671 AND 2 671 and to the west by RAMBHAU BHOGALE MARG. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Lower Parel / Worli business district2 km
Nariman Point / Fort7 km
Bandra Kurla Complex (BKC)10 km
Chhatrapati Shivaji Int'l Airport12 km
Powai / Hiranandani business park16 km
Andheri MIDC / SEEPZ16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Vardhman Developers LTD is the promoter on 5 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Vardhman Developers LTD

Vardhman Developers LTD
Past its declared completion dateMumbai City
Vardhman Developers LTD
FlaggedMumbai Suburban

Other RERA-registered projects in Mazgaon

Pier 33
possession by Sep 2026 · Esque Finmark Private Limited
Atlantis Residency
possession by Dec 2026 · JK Builders
Simana - Wing B - Phase 1
possession by Dec 2026 · Bhoomi Properties
Parshwa Lotus & Rangari Heights
possession by Jan 2027 · Gold Plaza Developers PVT LTD
Darshan Aura
possession by Dec 2028 · Darshan SKY High Constructions LLP
Infinity Residences
possession by Dec 2028 · Infinity Associates

Other RERA-registered projects in Mumbai City

Vardhman Flora Phase -II - Vardhman Habitat
declared completion Jun 2024 · Vardhman Developers LTD
Vasant Prabha
possession by Dec 2026 · Sudhir Vasant Mayekar
Veer Square Dadar
possession by Mar 2029 · P D Associates
Verona
possession by Dec 2029 · Adriana Constructions LLP
Verve Mansion
possession by Dec 2027 · Shanti Siddhi Infra LLP
Vida Crest
possession by Dec 2028 · Vida Scapes LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026