Mumbai/Project record

MahaRERA · the public record

VARDHMAN FLORA PHASE -II - VARDHMAN HABITAT

GHODAPDEO · VARDHMAN DEVELOPERS LTD

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

19units filed as unsoldInventory · 12 September 2026
30 Jun 2024declared completionMahaRERA registration · read 12 Jul 2026
29registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900026521

Delivery and registration

When is the project declared for completion?

VARDHMAN FLORA PHASE -II - VARDHMAN HABITAT is registered with MahaRERA as P51900026521 and the promoter has declared completion for 30 Jun 2024.

30 Jun 2024

declared completion

27months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900026521
Registered on30 Sep 2020
Promoter-declared completion30 Jun 2024
Current statusCertificate Signed
Against todayabout 27 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for VARDHMAN FLORA PHASE -II - VARDHMAN HABITAT record 16 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 16 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Vardhman Developers Ltd is the promoter of record on 29 projects registered with MahaRERA, 4 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

29projects

registered with MahaRERA

4flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

How much has actually been sold?

In VARDHMAN FLORA PHASE -II - VARDHMAN HABITAT, 10 of 29 homes filed with MahaRERA are recorded as sold or booked, about 34%, and 19 remain available.

34%sold

10 of 29 homes

₹13.27 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹6.24 Cr (about 47%) is recorded as collected and ₹7.03 Cr as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 10 registered agreements, the effective carpet rate is ₹31,534/sqft, with eight in ten falling between ₹28,719 and ₹32,557 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.

FloorUnitCarpetGovt reckoner value
Floor 11D-1102430 sqft (39.95 sqm)₹67.45 Lakh
Floor 12D-1202430 sqft (39.95 sqm)₹67.45 Lakh
Floor 13D-1301430 sqft (39.95 sqm)₹67.45 Lakh
Floor 14D-1402430 sqft (39.95 sqm)₹67.45 Lakh
Floor 15D-1501430 sqft (39.95 sqm)₹67.45 Lakh
Floor 17D-1702430 sqft (39.95 sqm)₹67.45 Lakh
Floor 19D-1901430 sqft (39.95 sqm)₹67.45 Lakh
Floor 19D-1902430 sqft (39.95 sqm)₹67.45 Lakh
Floor 20D-2001430 sqft (39.95 sqm)₹67.45 Lakh
Floor 20D-2002430 sqft (39.95 sqm)₹67.45 Lakh
Floor 21D-2101430 sqft (39.95 sqm)₹67.45 Lakh
Floor 21D-2102430 sqft (39.95 sqm)₹67.45 Lakh
Floor 22D-2201430 sqft (39.95 sqm)₹67.45 Lakh
Floor 22D-2202430 sqft (39.95 sqm)₹67.45 Lakh
Floor 23D-2302430 sqft (39.95 sqm)₹67.45 Lakh
Floor 23D-2306430 sqft (39.95 sqm)₹67.45 Lakh
Floor 23D-2307430 sqft (39.95 sqm)₹67.45 Lakh
Floor 6D-602430 sqft (39.95 sqm)₹67.45 Lakh
Floor 8D-802430 sqft (39.95 sqm)₹67.45 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 12 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 10 homes carry one, and 19 of the 29 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
D-2306430 sqftRs 1.3560 cr typical, over Rs 1.2350 cr to Rs 1.4000 cr10 filed at this size

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

In VARDHMAN FLORA PHASE -II - VARDHMAN HABITAT, every one of the 19 unsold homes has agreements filed on its own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 18 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+25 and 29 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
CD BUILDING1G+252931 Dec 2023

Unit mix on the filing: 29 residential.

Legal and disputes

What disputes are disclosed?

3 complaints are on the MahaRERA record for VARDHMAN FLORA PHASE -II - VARDHMAN HABITAT, with orders passed in 3 of them.

3complaints

3with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC1240016120/09/2024Manoj Kumar Mishra vs VARDHMAN DEVELOPERS LTDorder passed
CC1250113805/04/2025Rohit Tejbahadur Singh vs VARDHMAN DEVELOPERS LTDorder passed
CC1260085215/02/2026- vs VARDHMAN DEVELOPERS LTDorder passed

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Bombay City Civil15432017Draft Issues

Location, Land & Connectivity

Located at GHODAPDEO, RAMBHAU BHOGALE MARG, Ward ABCD, Mumbai City, 400033. Per the filed land record, the plot is bounded to the north by C S NO 753 AND 752, to the south by C S NO 2 750 AND 750, to the east by C S NO 9 671 AND 2 671 and to the west by RAMBHAU BHOGALE MARG. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~18 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park18 km
Andheri MIDC / SEEPZ19 km
Chhatrapati Shivaji Int'l Airport23 km
Bandra Kurla Complex (BKC)25 km
Lower Parel / Worli business district34 km
Nariman Point / Fort41 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Vardhman Developers LTD is the promoter on 5 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Vardhman Developers LTD

Vardhman Developers LTD
FlaggedMumbai City
Vardhman Developers LTD
FlaggedMumbai Suburban

Other RERA-registered projects in Mazgaon

Pier 33
possession by Sep 2026 · Esque Finmark Private Limited
Atlantis Residency
possession by Dec 2026 · JK Builders
Simana - Wing B - Phase 1
possession by Dec 2026 · Bhoomi Properties
Vardhman Flora Phase I
possession by Dec 2026 · Vardhman Developers LTD
Parshwa Lotus & Rangari Heights
possession by Jan 2027 · Gold Plaza Developers PVT LTD
Darshan Aura
possession by Dec 2028 · Darshan SKY High Constructions LLP

Other RERA-registered projects in Mumbai City

Vasant Prabha
possession by Dec 2026 · Sudhir Vasant Mayekar
Veer Square Dadar
possession by Mar 2029 · P D Associates
Verona
possession by Dec 2029 · Adriana Constructions LLP
Verve Mansion
possession by Dec 2027 · Shanti Siddhi Infra LLP
Vida Crest
possession by Dec 2028 · Vida Scapes LLP
View Villa
declared completion Dec 2018 · Manilal Keshavlal Saraiya Trust

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026