Mumbai/Project record

MahaRERA · the public record

AVISHA

GIRGAON · NANDIVARDHAN REALTORS LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2020declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2020

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900001451

Delivery and registration

When is the project declared for completion?

AVISHA is registered with MahaRERA as P51900001451 and the promoter has declared completion for 30 Dec 2020.

30 Dec 2020

declared completion

69months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900001451
Registered on28 Jul 2017
Promoter-declared completion30 Dec 2020
Current statusCertificate Signed
Against todayabout 69 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for AVISHA record 14 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 14 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Nandivardhan Realtors Limited is the promoter of record on 2 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

2projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for AVISHA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+23.

BuildingWingsFloorsDeclared completion
AVISHA1G+2330 Jun 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 4 court cases on this project to MahaRERA. 2 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Small Cause Court MumbaiLEC SUIT NO 262/20132013Pending For Steps
Small Cause Court MumbaiRAD SUIT NO 1170/20132013For Filing Written Statement
Bombay City Civil Court BombaySuit no 2669 of 20182018Service Of Summons
Small Cause Court MumbaiRAD SUIT NO 402/20182018Pending For Steps

Location, Land & Connectivity

Located at GIRGAON, MUGBHAT CROSS LANE, Thane, Thane, 400002. Per the filed land record, the plot is bounded to the north by PLOT BEARING CS NO 331, to the south by PLOT BEARING CS NO 334, to the east by MUGBHAT CROSS LANE and to the west by PLOT BEARING CS NO 322. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Nariman Point / Fort3 km
Lower Parel / Worli business district5 km
Bandra Kurla Complex (BKC)13 km
Chhatrapati Shivaji Int'l Airport16 km
Powai / Hiranandani business park20 km
Andheri MIDC / SEEPZ20 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bhuleshwar

Lifescapes Kshitij
Developer in insolvency (NCLT) · possession by Nov 2026 · Roxina Real Estate Pvt. Ltd.
Krishvi Escape
possession by Dec 2026 · Shagun Realty
Soutth Bay
possession by Dec 2026 · M/s. Sambhav Shelters
Ocean Drive
possession by Mar 2027 · Atul Projects GK Private Limited
Ajmera Downtown
possession by Dec 2027 · Ashjit Realties Pvt. Ltd.
Aryam
possession by Dec 2027 · Myra Infrastructure

Major developers building in Bhuleshwar

Other RERA-registered projects in Mumbai City

Avissa
possession by Dec 2029 · Sealink Realtors
Avyukta Imperial
possession by Sep 2028 · Roopventures LLP
Ayesha Residency
possession by Dec 2030 · Not Available
Ayuddha Eved
possession by Dec 2030 · Crystal Progressive LLP
Azad Residency
declared completion Jun 2026 · Dudhwala Construction
Azara Residences
possession by Dec 2027 · Azara Redstone LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026