Mumbai/Project record

MahaRERA · the public record

BADLAPUR LANDMARK

Belavali, Badlapur West · RAVINDRA MATYA PATIL

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2026declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700048379

Delivery and registration

When is the project declared for completion?

BADLAPUR LANDMARK is registered with MahaRERA as P51700048379 and the promoter has declared completion for 31 Dec 2026.

31 Dec 2026

declared completion

3months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700048379
Registered on27 Dec 2022
Promoter-declared completion31 Dec 2026
Current statusCertificate Signed
Against today3 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for BADLAPUR LANDMARK record 15 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Ravindra Matya Patil is the promoter of record on 99 projects registered with MahaRERA, 21 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

99projects

registered with MahaRERA

21flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for BADLAPUR LANDMARK in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
BADLAPUR LANDMARK1G+831 Dec 2026

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Belavali, Badlapur West, Kalyan Badlapur Road, Kalyan, Thane, 421503. Per the filed land record, the plot is bounded to the north by HISSA NO 3 OF SAME SURVEY NO, to the south by SURVEY NO 12, to the east by 3 MITER WIDE ROAD and to the west by SURVEY NO 11B. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~35 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park35 km
Andheri MIDC / SEEPZ38 km
Chhatrapati Shivaji Int'l Airport40 km
Bandra Kurla Complex (BKC)40 km
Lower Parel / Worli business district47 km
Nariman Point / Fort51 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Badlapur

Jagannath Paradise
possession by Sep 2026 · Mayur Group
JAY Meghdoot Chsl
possession by Sep 2026 · S R Developers
Kendale Emeralds
possession by Sep 2026 · Kendale Developers
Krishna Sudama Residency
possession by Sep 2026 · SAI Homes
MAA Bhawani Empire
Deregistered by MahaRERA · possession by Sep 2026 · MAA Bhawani Construction
Raghu Anand Villa
possession by Sep 2026 · United Developers

Other RERA-registered projects in Thane

Bageshri Co - Operative Housing Society Limited
possession by Dec 2027 · APR Realty Bageshri
Bagh-E-Firdous Tower
possession by Dec 2027 · Caption Real Estate
Bakul CO-Operative Housing Society Limited
possession by Jul 2027 · Adhiraaj Developers
Balaji Annex
possession by Dec 2026 · M/S OM Swayambhu Siddhivinayak Builders
Balaji Aqua
possession by Nov 2029 · Balaji World
Balaji Ashish
possession by Dec 2029 · SAI Balaji Emerald Realties

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026