BANDRA NORTH GULMOHAR AVENUE

BANDRA NORTH · SHIVALIK VENTURES PRIVATE LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

281units filed as unsoldInventory · 16 September 2026
31 Dec 2026declared completionMahaRERA registration · read 12 Jul 2026
153registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800014036

Delivery and registration

When is the project declared for completion?

BANDRA NORTH GULMOHAR AVENUE is registered with MahaRERA as P51800014036 and the promoter has declared completion for 31 Dec 2026.

31 Dec 2026

declared completion

3months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800014036
Registered on07 Nov 2017
Promoter-declared completion31 Dec 2026
Current statusCertificate Signed
Against today3 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for BANDRA NORTH GULMOHAR AVENUE record 35 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Shivalik Ventures is the promoter of record on 6 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

6projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

How much has actually been sold?

In BANDRA NORTH GULMOHAR AVENUE, 45 of 153 homes filed with MahaRERA are recorded as sold or booked (32 with registered agreements and 13 booked), about 29%, and 108 remain available.

29%sold

45 of 153 homes

₹37.77 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹6.59 Cr (about 17%) is recorded as collected and ₹25.95 Cr as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 45 registered agreements, the effective carpet rate is ₹23,257/sqft, with eight in ten falling between ₹22,327 and ₹28,008 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 16 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 461 homes carry one, and 281 of the 742 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
H-1002641 sqftRs 1.4500 cr typical, over Rs 12.00 lakh to Rs 1.5700 cr23 filed at this size

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today.

In BANDRA NORTH GULMOHAR AVENUE, 238 of the 281 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 280 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+18 and 153 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
GULMOHAR AVENUE WING A1G+1827-
GULMOHAR AVENUE WING B1G+18--
GULMOHAR AVENUE WING C1G+18--
GULMOHAR AVENUE WING D1G+18--
GULMOHAR AVENUE WING E1G+18--
GULMOHAR AVENUE WING F1G+18--
GULMOHAR AVENUE WING G1G+18--
GULMOHAR AVENUE WING H1G+18--
GULMOHAR AVENUE WING I1G+18--
GULMOHAR AVENUE WING J1G+18--
GULMOHAR AVENUE WING K1G+1863-
GULMOHAR AVENUE WING L1G+1863-
DELETED1---
DELETED1---

Unit mix on the filing: 144 residential and 9 non-residential (shops/offices).

Legal and disputes

What disputes are disclosed?

34 complaints are on the MahaRERA record for BANDRA NORTH GULMOHAR AVENUE, with orders passed in 34 of them.

34complaints

34with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000020970917/01/2022Mrs.Bianca Dsa Vincent and Mr.Sneeden AnthonyVincent vs Shivalik Ventures Pvt. Ltd.order passed
CC00600000050047321/07/2024Jay Bhoite vs Shivalik Ventures Pvt Ltdorder passed
CC00600000021052129/03/2022Neeta Sandeep Poyekar vs Shivalik Ventures Pvt. Ltd.order passed
CC00600000029244624/08/2022Poonam Sharma vs SHIVALIK VENTURES PRIVATE LIMITEDorder passed
CC00600000039746111/09/2023Poonam Sharma vs Shivalik Ventures Private Limitedorder passed
CC00600000029248026/08/2022SEJAL GAIKWAD vs SHIVALIK VENTRUES PRIVATE LIMITEDorder passed
CC00600000029248527/08/2022Jaya Midya vs SHIVALIK VENTURES PRIVATE LIMITEDorder passed
CC00600000029249028/08/2022Anthony Dias vs SHIVAILIK VENTURES PRIVATE LIMITEDorder passed
CC00600000029249928/08/2022NADEEM SYED & NAUSHEEN SHAIKH vs shivalik ventures Private Limitedorder passed
CC00600000029251030/08/2022Ronit Bhattacharya vs SHIVALIK VENTURES PRIVATE LIMITEDorder passed
CC00600000039744811/09/2023Ronit Bhattacharya vs Shivalik Ventures Private Limitedorder passed
CC00600000035451004/03/2023MANISHA VIJAY KASARALKAR vs SHIVALIK VENTURES PVT LTDorder passed
CC00600000037540927/04/2023Subhash Nathuram Shiwtarkar vs Shivalik Ventures Pvt Ltdorder passed
CC00600000037541427/04/2023Kiran Subhash Shiwtarkar vs Shivalik Ventures Pvt Ltdorder passed
CC00600000029249628/08/2022Shukla Rani Midya vs shivalik Ventures Private limnitedorder passed
CC00600000039707313/08/2023Mamta Gupta vs Vishal Jadhavorder passed
CC00600000043969417/03/2024Sharokh Allarakhia vs Shivalik Ventures Private Limitedorder passed
CC1240008512/09/2024Sushil Raheja vs SHIVALIK VENTURES PRIVATE LIMITEDorder passed
CC1240083220/11/2024Rajiv Ashim Bhattacharya vs SHIVALIK VENTURES PRIVATE LIMITEDorder passed
CC1240109911/12/2024Jagannath Mukund Gawas vs SHIVALIK VENTURES PRIVATE LIMITEDorder passed
CC1240071609/11/2024Jyoti Jagannath Gawas vs SHIVALIK VENTURES PRIVATE LIMITEDorder passed
CC1240121824/12/2024SHIVALIK VENTURES PRIVATE LIMITED vs Poonam Sharmaorder passed
CC1250000301/01/2025SHIVALIK VENTURES PRIVATE LIMITED vs Romit Bhattacharyaorder passed
CC1250018520/01/2025SHIVALIK VENTURES PRIVATE LIMITED vs Farah Gulamwaris Thakur and Gulamwaris Thakurorder passed
CC1250029827/01/2025SHIVALIK VENTURES PRIVATE LIMITED vs Rajabhau Shriram Phadorder passed
CC1250030828/01/2025SHIVALIK VENTURES PRIVATE LIMITED vs Rajabhau Shriram Phadorder passed
CC1250033831/01/2025SHIVALIK VENTURES PRIVATE LIMITED vs Rajendra Kumar Jeerorder passed
CC1250033931/01/2025SHIVALIK VENTURES PRIVATE LIMITED vs Dr Prakhar Dharamchand Jainorder passed
CC1250057319/02/2025Rajiv Ashim Bhattacharya vs SHIVALIK VENTURES PRIVATE LIMITEDorder passed
CC1250063523/02/2025ANUP KUMAR JOTIBA BAGADI vs SHIVALIK VENTURES PRIVATE LIMITEDorder passed
CC1250101324/03/2025Suraj Umashankar Jaiswar vs SHIVALIK VENTURES PRIVATE LIMITEDorder passed
CC1250334919/09/2025SHIVALIK VENTURES PRIVATE LIMITED vs Tabassum Mohammed Shaikh and Mohammed Yusuf Shaikhorder passed
CC1250335019/09/2025SHIVALIK VENTURES PRIVATE LIMITED vs Dinesh Anant Manjrekar and Sonali Dinesh Manjrekar Nee Sonali Shankar Umbalkarorder passed
SM1250020226/11/2025Komal Mundada vs SHIVALIK VENTURES PRIVATE LIMITEDorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered26 Aug 20241) Our project Bandra North Gulmohar Avenue consiss of 12 wings having ground + 15 upper floors is part of Slum Rehabilitation Scheme at Village Bandra (East) under Regulation 33 (
26 Aug 202431 Dec 2026Dear Sir, The sale building is proposed to be constructed as part of sale component in a Slum Rehabilitation scheme. The 3 wings of the building are almost completed and shall be

Location, Land & Connectivity

Located at BANDRA NORTH, GOLIBAR ROAD, Ward GNorth, Mumbai City, 400051. Per the filed land record, the plot is bounded to the north by CTS 30 PART, to the south by CTS 70 PART 71 PART 73 PART, to the east by GOLIBAR ROAD and to the west by CTS 30 PART 82 PART83 PART 74 PART. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bandra Kurla Complex (BKC)3 km
Chhatrapati Shivaji Int'l Airport3 km
Andheri MIDC / SEEPZ7 km
Powai / Hiranandani business park8 km
Lower Parel / Worli business district8 km
Nariman Point / Fort16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shivalik Ventures Private Limited is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other RERA-registered projects in Bandra East

A And O Estado
Not filing quarterly progress reports · possession by Dec 2026 · Ashapura Builders AND Developers
Antariksh Ace
possession by Dec 2026 · Pittie Antariksh Realty Private Limited
Gurukrupa Nirmalam
possession by Dec 2026 · Gurukrupa Realcon Infrastructure LLP
LEO Eminence
possession by Dec 2026 · LEO Infrastructure Private Limited
Mayur Tower
possession by Dec 2026 · Geopreneur Spire Realty
Nero
possession by Dec 2026 · Super Construction Company

Major developers building in Bandra East

Other RERA-registered projects in Mumbai Suburban

Bandra ONE
declared completion Dec 2025 · KML Estates PVT LTD
Bandstand Cama
possession by Jan 2030 · Imperial Infradevelopers Private Limited
Bank OF India Employees Sukhada Chsl
possession by Dec 2026 · M/S Hirani Realtors
Bansi Terrace Chsl
possession by Dec 2026 · Aadhunik Developers
Barbet At L And T Realty Elixir Reserve
possession by Jul 2029 · Larsen & Toubro Ltd.
Basera CHS LTD
declared completion Jul 2023 · Lakshmi Builders AND Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026