MahaRERA Property Intelligence · Mumbai Suburban

LEO EMINENCE

P51800046335 · BKC · promoter Leo Infrastructure Private

Certificate SignedDue 31 Dec 2026

Delivery & Registration

MahaRERA registrationP51800046335
Registered on22 Jun 2022
Promoter-declared completion31 Dec 2026
Current statusCertificate Signed
Against today5 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Construction Progress

MahaRERA's cost filing puts construction at ~60.9% of the estimated project cost incurred as of the last certificate (₹65.81 Cr spent against a ₹108.08 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 155 homes filed with MahaRERA, 123 are sold/booked (119 with registered agreements + 4 booked) and 32 remain available (~79% sold) — selling steadily. Buyers have committed ₹216.98 Cr in agreement value so far. Of that, ₹174.85 Cr (~81%) is already collected, ₹42.12 Cr receivable — a read on how far along these sales really are. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 123 registered agreements, the effective carpet rate is ₹31,074/sqft (typical range ₹27,224–₹35,049) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 1101733 sqft (68.08 sqm)₹2.20 Cr
Floor 1101622 sqft (57.79 sqm)₹2.05 Cr
Floor 1102622 sqft (57.79 sqm)₹2.05 Cr
Floor 1103422 sqft (39.2 sqm)₹1.43 Cr
Floor 101004622 sqft (57.79 sqm)₹2.15 Cr
Floor 111103622 sqft (57.79 sqm)₹2.25 Cr
Floor 121201574 sqft (53.33 sqm)₹2.09 Cr
Floor 121202568 sqft (52.77 sqm)₹2.07 Cr
Floor 121204622 sqft (57.79 sqm)₹2.25 Cr
Floor 131302568 sqft (52.77 sqm)₹2.07 Cr
Floor 131303622 sqft (57.79 sqm)₹2.25 Cr
Floor 141404622 sqft (57.79 sqm)₹2.25 Cr
Floor 151503622 sqft (57.79 sqm)₹2.25 Cr
Floor 151504622 sqft (57.79 sqm)₹2.25 Cr
Floor 161603622 sqft (57.79 sqm)₹2.25 Cr
Floor 161604622 sqft (57.79 sqm)₹2.25 Cr
Floor 181804622 sqft (57.79 sqm)₹2.25 Cr
Floor 191903422 sqft (39.2 sqm)₹1.63 Cr
Floor 2203422 sqft (39.2 sqm)₹1.43 Cr
Floor 202002568 sqft (52.77 sqm)₹2.07 Cr
Floor 202004622 sqft (57.79 sqm)₹2.25 Cr
Floor 212101622 sqft (57.79 sqm)₹2.35 Cr
Floor 212102622 sqft (57.79 sqm)₹2.35 Cr
Floor 212103622 sqft (57.79 sqm)₹2.35 Cr
Floor 222201622 sqft (57.79 sqm)₹2.35 Cr
Floor 222201574 sqft (53.33 sqm)₹2.18 Cr
Floor 222202622 sqft (57.79 sqm)₹2.35 Cr
Floor 222202422 sqft (39.2 sqm)₹1.63 Cr
Floor 222202568 sqft (52.77 sqm)₹2.16 Cr
Floor 222204622 sqft (57.79 sqm)₹2.35 Cr
Floor 3302622 sqft (57.79 sqm)₹2.05 Cr
Floor 7703422 sqft (39.2 sqm)₹1.49 Cr

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+22 and 155 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Wing A1G+2255-
Wing B1G+2277-
Wing C1G+2223-

Unit mix on the filing: 155 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
High Court Mumbai42122022Closed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 202531 Dec 2026We, LEO INFRASTRUCTURE PRIVATE LIMITED, are constructing a Residential project called "LEO EMINENCE". We have registered the project under MahaRERA vide RERA registration no. P5180

Location, Land & Connectivity

Located at BKC, Kalanagar, Borivali, Mumbai Suburban, 400051. Per the filed land record, the plot is bounded to the north by 9 15 Mtr Wide Road, to the south by Existing Building No-64, to the east by 18 30 Mtr Wide Road and to the west by 6 Mtr Wide Existing Road. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bandra East

Sajay Avenue 18
possession by Aug 2026 · Vinca Realtors Private Limited
A And O Estado
Not filing quarterly progress reports · possession by Dec 2026 · Ashapura Builders AND Developers
Antariksh Ace
possession by Dec 2026 · Pittie Antariksh Realty Private Limited
Bandra North Gulmohar Avenue
possession by Dec 2026 · Shivalik Ventures Private Limited
Gurukrupa Nirmalam
possession by Dec 2026 · Gurukrupa Realcon Infrastructure LLP
Mayur Tower
possession by Dec 2026 · Geopreneur Spire Realty

Major developers building in Bandra East

Other RERA-registered projects in Mumbai Suburban

LEO Group Housing Complex
declared completion Jun 2019 · SIR George P Joseph
Leo Heights
possession by Dec 2026 · Sir George P Joseph
LEO House
declared completion Aug 2024 · Ranc Developers
Leo Tower
declared completion May 2026 · Dev Land & Housing Private Limited
Level - The Residences
possession by Dec 2026 · M/s Siroya Keystone
Liberte64
possession by Aug 2026 · Jadhwani Infrastructure LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026