MahaRERA Property Intelligence · Mumbai Suburban
PM1181012600420 · SANTACRUZ EAST · promoter Jaavi Infra Pvt
| MahaRERA registration | PM1181012600420 |
| Registered on | 15 May 2026 |
| Promoter-declared completion | 31 Dec 2032 |
| Current status | Certificate Signed |
| Against today | 77 months to the declared date |
Of 26 homes filed with MahaRERA, 0 are sold/booked and 26 remain available (~0% sold) — early in sales — more choice of units now, but confirm the developer has the pre-sales to fund the build. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.
The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:
| Floor | Unit | Carpet | Reckoner value |
|---|---|---|---|
| Floor 1 | 101 | 975 sqft (90.58 sqm) | ₹1.65 Cr |
| Floor 1 | 101 | 727 sqft (67.51 sqm) | ₹1.23 Cr |
| Floor 1 | 101 | 955 sqft (88.68 sqm) | ₹1.61 Cr |
| Floor 1 | 102 | 949 sqft (88.13 sqm) | ₹1.60 Cr |
| Floor 1 | 102 | 726 sqft (67.49 sqm) | ₹1.23 Cr |
| Floor 1 | 102 | 726 sqft (67.45 sqm) | ₹1.23 Cr |
| Floor 1 | 103 | 955 sqft (88.68 sqm) | ₹1.61 Cr |
| Floor 1 | 103 | 1,662 sqft (154.36 sqm) | ₹2.80 Cr |
| Floor 1 | 104 | 726 sqft (67.42 sqm) | ₹1.23 Cr |
| Floor 1 | 104 | 975 sqft (90.58 sqm) | ₹1.65 Cr |
| Floor 1 | 105 | 949 sqft (88.13 sqm) | ₹1.60 Cr |
| Floor 2 | 201 | 955 sqft (88.68 sqm) | ₹1.61 Cr |
| Floor 2 | 202 | 726 sqft (67.45 sqm) | ₹1.23 Cr |
| Floor 2 | 203 | 726 sqft (67.45 sqm) | ₹1.23 Cr |
| Floor 2 | 204 | 975 sqft (90.58 sqm) | ₹1.65 Cr |
| Floor 2 | 205 | 949 sqft (88.13 sqm) | ₹1.60 Cr |
| Ground/Floor 0 | 001 | 1,355 sqft (125.89 sqm) | ₹2.29 Cr |
| Ground/Floor 0 | 002 | 1,372 sqft (127.42 sqm) | ₹2.32 Cr |
| Ground/Floor 0 | 003 | 1,784 sqft (165.71 sqm) | ₹3.01 Cr |
| Ground/Floor 0 | 003 | 1,347 sqft (125.13 sqm) | ₹2.27 Cr |
| Ground/Floor 0 | 004 | 1,364 sqft (126.74 sqm) | ₹2.30 Cr |
| Ground/Floor 0 | 005 | 1,361 sqft (126.46 sqm) | ₹2.30 Cr |
| Ground/Floor 0 | shop 1 | 982 sqft (91.24 sqm) | ₹2.28 Cr |
| Ground/Floor 0 | shop 2 | 412 sqft (38.24 sqm) | ₹95.54 Lakh |
| Ground/Floor 0 | shop 3 | 420 sqft (38.99 sqm) | ₹97.42 Lakh |
| Ground/Floor 0 | shop 4 | 310 sqft (28.83 sqm) | ₹72.03 Lakh |
No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4 and 17 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| CENTRAL PARK BUILDING NO 2 | 3 | G+3 | 3 | - |
| CENTRAL PARK BUILDING NO 1 | 1 | G+4 | 14 | - |
Unit mix on the filing: 22 residential and 4 non-residential (shops/offices).
No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.
The promoter has declared 26 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.
| Court | Case no. | Year | Status |
|---|---|---|---|
| High Court Bombay | S/407/2022 | 2022 | Ongoing |
| High Court Bombay | IA/6866/2025 in S/407/2022 | 2022 | Ongoing |
| High Court Bombay | CONP/10/2025 in IA/1239/2021 in S/407/2022 | 2021 | Ongoing |
| High Court Bombay | CONP/49/2025 in IA/1239/2021 in S/407/2022 | 2021 | Ongoing |
| High Court Bombay | IA(L)/1738/2022 in S/407/2022 | 2022 | Ongoing |
| High Court Bombay | CAN/44/2017 | 2017 | Ongoing |
| High Court Bombay | CP/478/2015 | 2015 | Ongoing |
| Civil Court, Dindoshi | Civil Suit/203091/2018 | 2018 | Ongoing |
| Civil Court, Dindoshi | Civil Suit/201147/2016 | 2016 | Ongoing |
| Bandra Small Cause Court | RAD/290/2014 | 2014 | Ongoing |
| Civil Court, Dindoshi | L.C. Suit No. 1518/2023 | 2023 | Ongoing |
| Civil Court, Dindoshi | L.C. Suit No. 1519/2023 | 2023 | Ongoing |
| Civil Court, Dindoshi | L.C. Suit No. 2601/2023 | 2023 | Ongoing |
| Civil Court, Dindoshi | L.C. Suit No. 2605 | 2023 | Ongoing |
| Bombay High Court | Conp./17501/2021 | 2021 | Ongoing |
| City Civil Court Dindoshi | Civil Suit/2696/2024 | 2024 | Ongoing |
| City Civil Court Dindoshi | Civil Suit/2697/2024 | 2024 | Ongoing |
| City Civil Court Dindoshi | Civil Suit/126/2025 | 2025 | Ongoing |
| City Civil Court Dindoshi | Civil Suit/125/2025 | 2025 | Ongoing |
| City Civil Court Dindoshi | Civil Suit/2758/2024 | 2024 | Ongoing |
| City Civil Court Dindoshi | Civil Suit/159/2025 | 2025 | Ongoing |
| City Civil Court Dindoshi | Civil Suit/358/2024 | 2024 | Ongoing |
| Bombay High Court | CRR/369/2022 in S/407/2022 | 2022 | Ongoing |
| Civil Court, Dindoshi | L.C. Suit No. 1929/2022 | 2022 | Ongoing |
| Civil Court, Dindoshi | L. C. Suit No. 2600/2023 | 2023 | Ongoing |
| City Civil Court Dindoshi | Civil Suit/2695/2024 | 2024 | Ongoing |
Located at SANTACRUZ EAST, 18.30 MTR. WIDE ST. ANTHONY ROAD, Ward ABCD, Mumbai City, 400055. Per the filed land record, the plot is bounded to the north by ST ANTONY ROAD, to the south by BOMBAY COLLEGE OF PHARMACY INDIA, to the east by GEETA VIHAR and to the west by RADHAKRISHNA MANDIR PREMISES. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.
The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.
| Landmark | Straight-line |
|---|---|
| Chhatrapati Shivaji Int'l Airport | 1 km |
| Bandra Kurla Complex (BKC) | 2 km |
| Andheri MIDC / SEEPZ | 6 km |
| Powai / Hiranandani business park | 6 km |
| Lower Parel / Worli business district | 9 km |
| Nariman Point / Fort | 17 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.
🔒 The verdict & buyer playbook · Compliance report
The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.
🔒 Unit-by-unit guidance · Unit Guidance report
Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.
🔒 Full financial records — escrow, funding & the document catalog · Compliance report
The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.
Should you buy in CENTRAL PARK?
This page is the free MahaRERA filing summary. The full RERA Property Intelligence Report gives you the full regulatory standing, declared court litigation, buyer-complaint and adjudication history, quarterly-progress-report discipline, the builder's MahaRERA-wide track record, the building/tower breakdown, and the sanctioned layout plan. See a real one first:
Sample: Lodha Kandivali – Tower 2 → · browse all sample reports →
Compliance Report · ₹999
The regulator’s filing record, read · 1 working day
Scan with any UPI app to pay · quietlist@kotak
Unit Guidance Report · ₹2,999
Everything, down to which unit · 1 working day
Not useful to your decision? Full refund — no questions asked.
Scan with any UPI app to pay · quietlist@kotak
Paying from outside India? Pay $15 (Compliance) or $39 (Unit Guidance) via PayPal, or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
Free · Watch this project
We'll email you when this project's RERA record changes.
Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.
Last checked against the RERA register: 19 Jul 2026