CHAITANYA

MAHIM WEST, MUMBAI · CHAITANYA DEVELOPERS PRIVATE LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800032723

Delivery and registration

When is the project declared for completion?

CHAITANYA is registered with MahaRERA as P51800032723 and the promoter has declared completion for 31 Dec 2025.

31 Dec 2025

declared completion

9months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800032723
Registered on24 Jan 2022
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 9 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for CHAITANYA record 16 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Chaitanya Developers is the promoter of record on 86 projects registered with MahaRERA, 14 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

86projects

registered with MahaRERA

14flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for CHAITANYA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+9.

BuildingWingsFloorsDeclared completion
CHAITANYA1G+925 May 2025

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at MAHIM WEST, MUMBAI, MORI ROAD, OPP. POST OFFICE, Mumbai, Mumbai Suburban, 400016. Per the filed land record, the plot is bounded to the north by VRUNDAVAN SOCIETY, to the south by MAULI TOWER, to the east by INEZ TOWER and to the west by COLABA MENSION. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

See every Chaitanya Developers Private Limited project & its RERA track record →

Other RERA-registered projects in Mahim

Makhdoom Heights
possession by Nov 2026 · Naqi Developers Private Limited
Karpur Heights
possession by Dec 2026 · Parvasha Grihnirman Sanstha
ANJ Ananda
possession by Dec 2026 · A N J Recon LLP
Kapil Tirth
possession by Dec 2026 · Prathamesh Projects LLP
Moin Heights
possession by Dec 2026 · Mansoor Mehmood Sayyed
Royal Heights
possession by Dec 2026 · S.a. Enterprises

Major developers building in Mahim

Other RERA-registered projects in Mumbai Suburban

Chaitanya
possession by Dec 2027 · OVK CO-Operative Housing Society Limited
Chaitanya Anand - Lunkhod Chsl
declared completion Aug 2024 · Chaitanya Developers
Chaitanya Krishnai
declared completion Nov 2024 · Chaitanya Realty
Chamaria Residencies
declared completion Apr 2023 · Rajiv Ambrish Agarwal
Chanakya Heights
possession by Dec 2031 · Mahavir AND Magnus Construction Company
Chandak Highscape City 1A
possession by Dec 2030 · Chandak Realtors Private Limited

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026