MahaRERA Property Intelligence · Mumbai City
P51900022725 · CHINCHPOKLI · promoter Chaitya Developers
| MahaRERA registration | P51900022725 |
| Registered on | 16 Oct 2019 |
| Promoter-declared completion | 31 Dec 2031 |
| Current status | Certificate Signed |
| Against today | 65 months to the declared date |
MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.
MahaRERA's cost filing puts construction at ~98.2% of the estimated project cost incurred as of the last certificate (₹134.60 Cr spent against a ₹137.00 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.
Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.
Of 130 homes filed with MahaRERA, 114 are sold/booked and 16 remain available (~88% sold) — nearly sold out — little inventory left, so you're buying into an established buyer base. Buyers have committed ₹204.81 Cr in agreement value so far. Of that, ₹191.49 Cr (~93%) is already collected, ₹13.32 Cr receivable — a read on how far along these sales really are. Note: the project registers 156 homes in total, but this sold/unsold inventory filing covers only 130 of them — the other 26 aren't in the ledger yet. Ask the builder what they are (an unreleased phase, held-back stock, or non-saleable/car-park units) before reading too much into the percentage. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.
What buyers actually paid: across 114 registered agreements, the effective carpet rate is ₹23,159/sqft (typical range ₹22,233–₹25,400) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.
The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:
| Floor | Unit | Carpet | Reckoner value |
|---|---|---|---|
| Floor 14 | 1401 | 967 sqft (89.84 sqm) | ₹1.93 Cr |
| Floor 17 | 1704 | 669 sqft (62.18 sqm) | ₹1.34 Cr |
| Floor 18 | 1806 | 967 sqft (89.84 sqm) | ₹1.93 Cr |
| Floor 26 | 2601 | 967 sqft (89.84 sqm) | ₹1.93 Cr |
| Floor 31 | 3104 | 669 sqft (62.18 sqm) | ₹1.34 Cr |
| Floor 32 | 3204 | 669 sqft (62.18 sqm) | ₹1.34 Cr |
| Floor 33 | 3304 | 669 sqft (62.18 sqm) | ₹1.34 Cr |
| Floor 33 | 3305 | 693 sqft (64.37 sqm) | ₹1.39 Cr |
| Floor 34 | 3401 | 967 sqft (89.84 sqm) | ₹1.93 Cr |
| Floor 34 | 3403 | 669 sqft (62.18 sqm) | ₹1.34 Cr |
| Floor 34 | 3406 | 967 sqft (89.84 sqm) | ₹1.93 Cr |
| Floor 35 | 3501 | 967 sqft (89.84 sqm) | ₹1.93 Cr |
| Floor 35 | 3502 | 703 sqft (65.28 sqm) | ₹1.41 Cr |
| Floor 35 | 3503 | 669 sqft (62.18 sqm) | ₹1.34 Cr |
| Floor 9 | 901 | 967 sqft (89.84 sqm) | ₹1.93 Cr |
| Floor 9 | 906 | 967 sqft (89.84 sqm) | ₹1.93 Cr |
No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+27 and 156 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| CHAITYA 777 | 1 | G+27 | 156 | - |
Unit mix on the filing: 156 residential.
No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.
The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.
| From (declared) | To (revised) | Stated reason |
|---|---|---|
| 30 Dec 2025 | 31 Dec 2031 | We, M/s. Chaitya Developers, Promoter of the above-mentioned project, respectfully submit that the project was originally registered with MahaRERA based on the IOD sanction up to 2 |
Located at CHINCHPOKLI, DR BABASAHEB AMBEDKAR ROAD, Ward E, Mumbai City, 400012. Per the filed land record, the plot is bounded to the north by CS NO 779, to the south by CS NO 776, to the east by DR BA ROAD and to the west by CS NO 778. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.
The nearest major job hub is ~1 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.
| Landmark | Straight-line |
|---|---|
| Lower Parel / Worli business district | 1 km |
| Nariman Point / Fort | 7 km |
| Bandra Kurla Complex (BKC) | 10 km |
| Chhatrapati Shivaji Int'l Airport | 12 km |
| Powai / Hiranandani business park | 16 km |
| Andheri MIDC / SEEPZ | 16 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.
🔒 The verdict & buyer playbook · Compliance report
The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.
🔒 Unit-by-unit guidance · Unit Guidance report
Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.
🔒 Full financial records — escrow, funding & the document catalog · Compliance report
The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.
Should you buy in CHAITYA 777?
This page is the free MahaRERA filing summary. The full RERA Property Intelligence Report gives you the full regulatory standing, declared court litigation, buyer-complaint and adjudication history, quarterly-progress-report discipline, the builder's MahaRERA-wide track record, the building/tower breakdown, and the sanctioned layout plan. See a real one first:
Sample: Lodha Kandivali – Tower 2 → · browse all sample reports →
Compliance Report · ₹999
The regulator’s filing record, read · 1 working day
Scan with any UPI app to pay · quietlist@kotak
Unit Guidance Report · ₹2,999
Everything, down to which unit · 1 working day
Not useful to your decision? Full refund — no questions asked.
Scan with any UPI app to pay · quietlist@kotak
Paying from outside India? Pay $15 (Compliance) or $39 (Unit Guidance) via PayPal, or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
Free · Watch this project
We'll email you when this project's RERA record changes.
Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.
Last checked against the RERA register: 27 Jul 2026